Free Certified Associate in Project Management (CAPM) Certification Practice Questions

Question # 31

Which of the following relationship is used in the Arrow Diagramming Method [ADM] :

Options:

A.  

Start-to-Finish

B.  

Finish-to-Start

C.  

Start-to-Start

D.  

Finish-to-Finish

Discussion 0
Question # 32

Which is not the tools and techniques used in Contract Administration:

Options:

A.  

Contract change control system

B.  

Contract negotiation

C.  

Payment system

D.  

Performance rating

Discussion 0
Question # 33

When should a project manager be assigned to a project?

Options:

A.  

As early in the project as feasible.

B.  

Preferably before much project planning has been done.

C.  

At least prior to the start of project plan execution.

D.  

All of the above.

Discussion 0
Question # 34

_________ is the best choice for buyer when the item is well defined.

Options:

A.  

Cost plus incentive fee

B.  

F'xed P|ice

C.  

Time and material

D.  

None

Discussion 0
Question # 35

Which of the following is NOT an input of Estimate Costs?

Options:

A.  

Earn Value Analysis

B.  

Scope Baseline

C.  

P'sk Register

D.  

Human Resource Plan

Discussion 0
Question # 36

Another term for top down estimating is:.

Options:

A.  

Analogous estimating

B.  

Life-cycle costing

C.  

Parametric modeling

D.  

Bottom up estimating

Discussion 0
Question # 37

What are the outputs of Initiation process?

Options:

A.  

Project charter and PM assigned

B.  

Constraints

C.  

Assumptions

D.  

Al1 of the above

Discussion 0
Question # 38

In PMBOK, the buyer is ________ to the project team.

Options:

A.  

Internal

B.  

External

C.  

Outside

D.  

Assigned

Discussion 0
Question # 39

You are the project manager of a project .You have just completed the Define Activities, activity resources estimating, and Estimate Activity Durations processes. Which process have you left out?

Options:

A.  

Control Schedule

B.  

Create WBS

C.  

Sequence Activities

D.  

Operations

Discussion 0
Question # 40

The project management plan:

Options:

A.  

Identifies all the steps and processes that will be used after a project is initiated

B.  

Steps needed to complete a project task

C.  

Prepared at the beginning and fixed throughout the execution of the project

D.  

Includes project charter

Discussion 0

CA0-001 PDF

CA0-001 PDF (Printable)
$46.5
$154.99

CA0-001 Testing Engine

CA0-001 PDF (Printable)
$51
$169.99

CA0-001 PDF + Testing Engine

CA0-001 PDF (Printable)
$63.9
$212.99

Free Exams Sample Questions