Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Free Certified Associate in Project Management (CAPM) Certification Practice Questions

Exams4sure Dumps

Exam style questions across every CA0-001 domain

Last Update 4 days ago
Total Questions : 525

Start with our free CA0-001 practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real CAPM exam. Each CA0-001 exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your PMI weak domains, see where you're losing marks, and build a focused study plan in minutes.

CA0-001 PDF

CA0-001 PDF (Printable)
$54.25
$154.99

CA0-001 Testing Engine

CA0-001 PDF (Printable)
$59.5
$169.99

CA0-001 PDF + Testing Engine

CA0-001 PDF (Printable)
$74.55
$212.99
Question # 1

PMI discusses procurement focusing on the ______ relationship.

Options:

A.  

Buyer or seller

B.  

Vendor or seller

C.  

Purchasing

D.  

Sellino-

Discussion 0
Question # 2

You are project manager of a project, which of the following is not your responsibility?

Options:

A.  

Quality in the organization

B.  

Acquiring HR resources for the project team

C.  

Overall responsibility for risk on the project

D.  

Al1 of the above

Discussion 0
Question # 3

Collect Requirements process starts in Project Planning Phase and uses the outputs of the __________.

Options:

A.  

Initiation Process

B.  

Project closer Process

C.  

Estimation Process

D.  

Closing process

Discussion 0
Question # 4

Which of the following is not a form a leadership power?

Options:

A.  

Compromise

B.  

Smoothing

C.  

Foimal

D.  

Coercive

Discussion 0
Question # 5

The work breakdown structure is ________.

Options:

A.  

Used to break down the project into manageable pieces

B.  

Set and does not change throughout the project

C.  

Needed as part of the project charter

D.  

[Needed as part of the project scope statement

Discussion 0
Question # 6

Assumptions are factors that, for planning purposes, are considered to be ______.

Options:

A.  

True, real, or certain

B.  

True, real, or uncertain

C.  

Real

D.  

Verbal

Discussion 0
Question # 7

Which of the following subsidiary plan contains the quality objectives for the project?

Options:

A.  

Quality baseline

B.  

Quality management plan

C.  

Process improvement plan

D.  

QA checklist

Discussion 0
Question # 8

Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?

Options:

A.  

Parametric estimating

B.  

Funding limit reconciliation

C.  

Reserves analysis

D.  

None of the above

Discussion 0
Question # 9

_________ is always the lowest risk for the buyer if the scope of work is not well defined.

Options:

A.  

Cost plus incentive fee

B.  

F'xed P|ice

C.  

Time and material

D.  

"'s^ 's nc* 'elated to price

Discussion 0
Question # 10

Which statement is true about Bottom-up estimating?

Options:

A.  

Estimating the cost of individual work items and then rolling up the costs to arrive at a project total.

B.  

Uses the actual cost of a previous similar project as the basis for estimating the cost of the current project.

C.  

Using project characteristics (or parameters) in a mathematical model to predict costs.

D.  

Cost of quality can also be used to prepare the schedule activity cost estimate.

Discussion 0