Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Free Certified Associate in Project Management (CAPM) Certification Practice Questions

Exams4sure Dumps

Exam style questions across every CA0-001 domain

Last Update 4 days ago
Total Questions : 525

Start with our free CA0-001 practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real CAPM exam. Each CA0-001 exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your PMI weak domains, see where you're losing marks, and build a focused study plan in minutes.

CA0-001 PDF

CA0-001 PDF (Printable)
$54.25
$154.99

CA0-001 Testing Engine

CA0-001 PDF (Printable)
$59.5
$169.99

CA0-001 PDF + Testing Engine

CA0-001 PDF (Printable)
$74.55
$212.99
Question # 51

You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?

Options:

A.  

Schedule

B.  

Assumption

C.  

Constraint

D.  

Planning process

Discussion 0
Question # 52

A Reserve Analysis is a technique for:

Options:

A.  

Estimate Activity Durations

B.  

Estimate Activity Resources

C.  

Sequence Activities

D.  

Define Activities

Discussion 0
Question # 53

What does a CPI value greater than 1.0 indicate?

Options:

A.  

Cost right at the estimated value

B.  

Cost under the estimated value

C.  

Cost right at the actual value

D.  

Cost over the estimated value

Discussion 0
Question # 54

In what type of contract is the seller reimbursed for all allowable costs for performing the contract work and receives a predetermined fee based upon achieving certain performance objectives as set forth in the contract?

Options:

A.  

Cost-plus-fixed-fee

B.  

Cost-plus-incentive-fee

C.  

Firm-fixed-price

D.  

Fixed-price-incentive-fee

Discussion 0
Question # 55

Which of the following is defined by a project's life cycle and varies by application area?

Options:

A.  

Product

B.  

Product-oriented processes

C.  

Project management process groups

D.  

Project-oriented processes

Discussion 0
Question # 56

What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

Options:

A.  

Pareto

B.  

Ishikawa

C.  

Shewart-Deming

D.  

Delphi

Discussion 0
Question # 57

Which activity is an input to the select sellers process?

Options:

A.  

Organizational process assets

B.  

Resource availability

C.  

Change control process

D.  

Team performance assessment

Discussion 0
Question # 58

As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods?

Options:

A.  

BAC

B.  

EAC

C.  

ETC

D.  

WBS

Discussion 0
Question # 59

Which of the following is an output of the Estimate Activity Resources process?

Options:

A.  

Alternative analysis

B.  

Bottom-up estimating

C.  

Resource breakdown structure

D.  

Enterprise environmental factors

Discussion 0
Question # 60

Which is the total float for the activity G?

Options:

A.  

0

B.  

3

C.  

5

D.  

10

Discussion 0