Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Free Certified Associate in Project Management (CAPM) Certification Practice Questions

Exams4sure Dumps

Exam style questions across every CA0-001 domain

Last Update 4 days ago
Total Questions : 525

Start with our free CA0-001 practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real CAPM exam. Each CA0-001 exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your PMI weak domains, see where you're losing marks, and build a focused study plan in minutes.

CA0-001 PDF

CA0-001 PDF (Printable)
$54.25
$154.99

CA0-001 Testing Engine

CA0-001 PDF (Printable)
$59.5
$169.99

CA0-001 PDF + Testing Engine

CA0-001 PDF (Printable)
$74.55
$212.99
Question # 61

The risk register contains which of the following?

Options:

A.  

Identified risks and potential responses

B.  

Identified risks and updates to scope baseline

C.  

Risk management plan

D.  

Risk related contract decisions

Discussion 0
Question # 62

Who selects the appropriate processes for a project?

Options:

A.  

Project stakeholders

B.  

Project sponsor and project stakeholder

C.  

Project manager and project team

D.  

Project manager and project sponsor

Discussion 0
Question # 63

What provides information regarding the ways people, teams, and organizational units behave?

Options:

A.  

Organizational chart

B.  

Organizational theory

C.  

Organizational structure

D.  

Organizational behavior

Discussion 0
Question # 64

What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?

Options:

A.  

Organizational process assets

B.  

Enterprise environmental factors

C.  

Project management processes

D.  

Project scope management plan

Discussion 0
Question # 65

Which analysis helps to determine the risks that have the most potential for impacting the project?

Options:

A.  

Expected monetary value analysis

B.  

Sensitivity analysis

C.  

Modeling and simulation

D.  

Expert judgment

Discussion 0
Question # 66

Which of the following equations is used to calculate cost variance?

Options:

A.  

EV-AC

B.  

AC-EV

C.  

AC+EV

D.  

AC/EV

Discussion 0
Question # 67

What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?

Options:

A.  

Failure modes and effects analysis

B.  

Design of experiments

C.  

Quality checklist

D.  

Risk analysis

Discussion 0
Question # 68

What is risk tolerance?

Options:

A.  

Ability to manage risks

B.  

Willingness to accept varying degrees of risks

C.  

Ability to mitigate risks

D.  

Willingness to develop a risk management plan

Discussion 0
Question # 69

What causes replanning of the project scope?

Options:

A.  

Requested changes

B.  

Project scope statement changes

C.  

Variance analysis

D.  

Approved change requests

Discussion 0
Question # 70

The decision to approve or reject a particular change request is made in which of the following processes?

Options:

A.  

Perform Integrated Change Control

B.  

Monitor and Control Project Work

C.  

Develop Project Management Plan

D.  

Direct and Manage Project Execution

Discussion 0