Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PgMP Program Management Professional (PgMP) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PgMP Practice Questions

Program Management Professional (PgMP)

Last Update 3 days ago
Total Questions : 452

Dive into our fully updated and stable PgMP practice test platform, featuring all the latest PMI Certification exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI Certification practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PgMP. Use this test to pinpoint which areas you need to focus your study on.

PgMP PDF

PgMP PDF (Printable)
$43.75
$124.99

PgMP Testing Engine

PgMP PDF (Printable)
$50.75
$144.99

PgMP PDF + Testing Engine

PgMP PDF (Printable)
$63.7
$181.99
Question # 21

A software development program will launch iterative versions of new software called Alpha over two years. Following that, a program will be released to the program team and developers to create new software called Beta. While the program manager prepares the program closure plan for Alpha, the program sponsor expresses concern about its support after program closure.

What should the program manager do as part of Alpha’s program closure plan?

Options:

A.  

Execute the transition plan, and include knowledge transfer to transition Alpha support to operations.

B.  

Keep the Alpha program open until support is no longer required, then execute program closure.

C.  

Adjust Alpha’s exit criteria to ensure its support is included in the Beta program.

D.  

Document the program closure procedure to ensure that resources are released from Alpha to develop Beta.

Discussion 0
Question # 22

You are the program manager for your organization. Management is considering a new program but they are worried about the program risks that may affect the program success. You know that there are three positive risks responses and three negative risk responses that each risk can have. Management asks you which risk response would be most appropriate for a large risk event if they wanted to hire a third-party to own the risk event for the program. What risk event is most appropriate?

Options:

A.  

Transference

B.  

Mitigation

C.  

Avoidance

D.  

Sharing

Discussion 0
Question # 23

You are a program manager of a program. You are required to compile performance data of your program. These data will be sent to relevant stakeholders. You are reviewing the status reports of all projects including the costs, schedule, scope, risks, and other performance data.

In which of the following processes are you working on?

Options:

A.  

Plan Communication

B.  

Distribute Information

C.  

Report Program Performance

D.  

Monitor and Control Program Performance

Discussion 0
Question # 24

A program manager is leading a program to transform an organization's sales and customer service operations by introducing a new customer relationship management (CRM) solution. As the program progresses, the sponsor and other stakeholders are satisfied with the pace of the program's performance.

A stakeholder from the sales department now requests a new feature to integrate the CRM platform with another application. The program manager advises that this is out of scope, as it will require analysis and development and be a project on its own. The program manager then requests additional funding via the formal change management process and the new scope is approved.

What should the program manager do next?

Options:

A.  

Secure additional approvals from senior stakeholders.

B.  

Assign a new project manager to own the delivery of the new project.

C.  

Redefine the priorities of the existing program components to ensure optimal resource allocation and management of interdependencies.

D.  

Discontinue one of the existing program components, and reallocate all of that component's resources to the newly approved project.

Discussion 0
Question # 25

Robert is the program manager for his organization which operates in a matrix structure.

Resources in Robert's program will be utilized on several projects in and out of his program. He wants to be certain that all of the resources will be planned accordingly and that the project managers communicate with one another about when the resources will be needed and utilized in the projects. What plan should Robert create along with the project managers to ensure that the resources are scheduled and managed effectively?

Options:

A.  

Resource management plan

B.  

Program management calendar

C.  

Schedule management plan

D.  

Resource calendar

Discussion 0
Question # 26

After program closure, the lessons learned document becomes the part of?

Options:

A.  

The risk register

B.  

The company's organizational process assets

C.  

The program's performance record

D.  

The program charter

Discussion 0
Question # 27

Which of the following documents sets the project objectives?

Options:

A.  

Project charter

B.  

Project schedule

C.  

Project scope statement

D.  

Project organization chart

Discussion 0
Question # 28

The program director of a four-year program, estimated to require 600,000 person-days effort, notices that team morale has decreased over the last three months. The program is at a critical stage with 70% completion

through the test phase. A number of defects are found that result in teams working additional hours. The program director requests that the program management office (PMO) gather metrics to monitor the situation.

Which of the following metrics should the PMO capture on a monthly basis?

Options:

A.  

Billable hours charged to the program, non-billable hours charged to the program, quantity of defects per full-time equivalent (FTE)

B.  

Absenteeism rate, staff turnover, quantity of defects, total hours worked, average number of FTEs

C.  

Amount of hours spent on rework of software coding, retesting, and on non-rework activities

D.  

Absenteeism rate, staff turnover and leave liability

Discussion 0
Question # 29

You are hosting a meeting with all of the vendors that have received a copy of your statement of work. In this meeting, you'll be discussing the statement of work, clarifying the details, and answering any QUESTION NO:s the vendors may have about the project. What is this meeting called?

Options:

A.  

Sales meeting

B.  

Select sellers process

C.  

Bidder conference

D.  

Negotiations

Discussion 0
Question # 30

You are the program manager for your organization. Management has asked you to create a method to track the program stakeholders' concerns, threats, and demands for communication. They would like you to map out each stakeholder or stakeholder group and identify trends within the chart to help your program communicate better. What type of a chart should you create for management?

Options:

A.  

RACI chart

B.  

Stakeholder analysis chart

C.  

Roles and responsibilities chart

D.  

Communication matrix

Discussion 0
Get PgMP dumps and pass your exam in 24 hours!

Free Exams Sample Questions