Start with our free PgMP practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real PMI Certification exam. Each PgMP exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your PMI weak domains, see where you're losing marks, and build a focused study plan in minutes.
An infrastructure program has 20 projects. The first half of these projects incurred multiple change orders and failed to be completed on time. The program manager meets with the project managers to discuss lessons learned and to understand the challenges. During the meeting, the project managers complain that key risks and a lack of resources resulted in missing deadlines.
What should the program manager do to ensure that the remaining 10 component projects stay on track?
A program manager takes over a global program from another program manager. Upon arriving on-site, the program manager immediately sees that stakeholders are upset, because of a lack of updates and communications about the program.
What should the program manager do first?
The program selection committee presents several programs for approval:
Program A is estimated to cost US$250,000, and has an annual cash inflow of US$75,000. Program B is estimated to cost US$150,000, and has an annual cash inflow of US$55,000. Program C is estimated to cost US$100,000, and has an annual cash inflow of US$45,000. Program D is estimated to cost US$200,000, and has an annual cash inflow of US$35,000.
Which program was selected based solely on a three-year return on investment?
The program sponsor returns from a board of directors meeting after identifying a significant risk to the program schedule. This may impact the program's benefits realization.
What should the program manager do next?
After an organization initiates a strategic program, several project managers express interest in joining the program team. The program manager’s supervisor recommends a list of project managers to be part of the team.
What should the program manager do to select the project managers?
Which one of the following is not considered one of the three components of the Iron Triangle?
Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.
What should be done with the identified potential risk?
Which of the following risk identification techniques is described in the statement below?
"It is used to gather information where participants don't know each other nor do they have to be present at the same location."
A new program is being initiated for the HNQ Organization. The program manager is working with the
business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?
You are the program manager for your organization. Your program is about to being initiated and management is asking you for a document that will define all of the required resources, skills, and competencies you'll need in your program. What document defines the skills and competencies for a program?