Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-200 PMI Agile Certified Practitioner (PMI-ACP) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-200 Practice Questions

PMI Agile Certified Practitioner (PMI-ACP)

Last Update 17 hours ago
Total Questions : 482

Dive into our fully updated and stable PMI-200 practice test platform, featuring all the latest PMI ACP exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI ACP practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-200. Use this test to pinpoint which areas you need to focus your study on.

PMI-200 PDF

PMI-200 PDF (Printable)
$43.75
$124.99

PMI-200 Testing Engine

PMI-200 PDF (Printable)
$50.75
$144.99

PMI-200 PDF + Testing Engine

PMI-200 PDF (Printable)
$63.7
$181.99
Question # 21

During an iteration planning meeting, the team suggests changes to add product value that will require extra work and impact the schedule. What should the agile project leader do?

Options:

A.  

Re-estimate the project.

B.  

Finish the product as it was initially planned.

C.  

Try to include as many changes as possible.

D.  

Ask the product owner for approval to proceed.

Discussion 0
Question # 22

During backlog refinement, the team uses an online planning poker tool for estimation. The junior developers change their number of story points after they see the estimations provided by the developers. The junior developers state that the reason for this is that they do not have enough experience and do not want to be blamed for sizing it wrong.

What should the scrum master do?

Options:

A.  

Ask the developers to keep their estimation so that the team is transparent with their level of understanding of work.

B.  

Agree with the team to keep their estimation as the final number of story points will be the average of all team members.

C.  

Propose to consider the estimations of only senior developers and have the junior developers learn from them.

D.  

Encourage the team to keep their estimation as this will help surface different constraints and assumptions that others might have missed.

Discussion 0
Question # 23

An agile team is building a training safety video based on current government regulations. The agile coach knows the regulations are likely to change before the release date.

How should the agile coach address this change?

Options:

A.  

Plan for the second release to include regulatory changes and new features.

B.  

Hold off making changes during the current release because the regulatory changes cannot be planned for.

C.  

Verify the team is building the product in increments which can be adapted at the last minute if necessary.

D.  

Monitor regulatory discussions to get a head start on the upcoming regulatory changes.

Discussion 0
Question # 24

A development team is working on the implementation of a human resources (HR) solution. The team has decided to work together with different business units to deliver value early and often.

Which agile values are being practiced in this scenario?

Options:

A.  

The importance of customer-centric product development practices over product-centric approaches.

B.  

Deliver working software often with a preference for shorter timescales and changing requirements

C.  

The belief that contributions and interactions are more important to success than processes and tools.

D.  

The best architectures, requirements, and designs emerge from self-organizing teams.

Discussion 0
Question # 25

The agile lead is told by executive leadership that the team needs to work faster because the release date has been moved up three months. The agile lead communicates the updated timeline to the team. One of the junior team members objects and feels the timeline is unrealistic.

What should the junior team member do?

Options:

A.  

Speak to the agile lead about the concerns.

B.  

Follow the agile lead's instructions.

C.  

Increase the time worked to meet objectives.

D.  

Speak to all team members about the concerns.

Discussion 0
Question # 26

Stakeholders are unhappy because they have not been consulted on a user interface (UI) for a project that will have a significant impact on end users once it is launched. How should this situation be handled?

Options:

A.  

The agile team should engage stakeholders regarding the proposed designs and ensure that sufficient engagement occurs throughout the project in an adaptive way.

B.  

The agile practitioner should inform the stakeholders that the Ul has already been approved by the project team and the project sponsor, so the team is committed to staying the course.

C.  

All stakeholders should go through the approved project charter and the business requirements document to reduce the number of late changes or requests.

D.  

The stakeholders should contact the project sponsor to get the project halted until new requirements are agreed upon.

Discussion 0
Question # 27

A product's scope and acceptance criteria have been defined, and the product is planned for release at the end of the next quarter. What should the project team do next?

Options:

A.  

Estimate the project team's capacity.

B.  

Determine how much work can be delivered.

C.  

Calculate how much work will fit into the next iteration.

D.  

Estimate items in the product backlog.

Discussion 0
Question # 28

Question # 28

Based on the backlog metrics in the chart what can explain the jump in points at the end of iteration 4?

Options:

A.  

The team neglected to account for support and maintenance costs associated with other supported products

B.  

The team discovered that previously accepted work could be greatly improved and added story points associated with thatwork.

C.  

The team realized that some stories were underestimated relative to other stories and reestimated as needed

D.  

The team learned that the product owner needed to increase the output in the next release

Discussion 0
Question # 29

Prior to a retrospective, discussions among team members indicate conflict. An agile practitioner wants to ensure an open and safe environment during the retrospective.

What should the agile practitioner do?

Options:

A.  

Review established ground rules with the team

B.  

Ask team members specific questions to identify the cause

C.  

Encourage the team to continue working to maintain the iteration's schedule

D.  

Meet with the product owner and stakeholders to discuss the issue

Discussion 0
Question # 30

During an interview for an agile team lead for a global company, a candidate is asked: "How do you ensure your project is aligned with the stakeholders' priorities?"

How should the candidate respond?

Options:

A.  

Engage the change management team to determine prioritization of the backlog.

B.  

Allow the stakeholders to decide on the priority and build the backlog.

C.  

The entire team should discuss and prioritize the backlog factoring in stakeholder input.

D.  

Only the agile team lead and team need to decide how to prioritize the project deliverables.

Discussion 0