Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-200 PMI Agile Certified Practitioner (PMI-ACP) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-200 Practice Questions

PMI Agile Certified Practitioner (PMI-ACP)

Last Update 17 hours ago
Total Questions : 482

Dive into our fully updated and stable PMI-200 practice test platform, featuring all the latest PMI ACP exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI ACP practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-200. Use this test to pinpoint which areas you need to focus your study on.

PMI-200 PDF

PMI-200 PDF (Printable)
$43.75
$124.99

PMI-200 Testing Engine

PMI-200 PDF (Printable)
$50.75
$144.99

PMI-200 PDF + Testing Engine

PMI-200 PDF (Printable)
$63.7
$181.99
Question # 51

During refinement, the team tester has a question about part of the acceptance criteria for a given user story. Who should clarify the acceptance criteria?

Options:

A.  

The sponsor, since they understand the business value.

B.  

The scrum master, since they coordinate with the team and define the acceptance criteria.

C.  

The product owner, since their vision is the basis for the acceptance criteria.

D.  

The developer, since they write the code that would be tested.

Discussion 0
Question # 52

A key stakeholder cannot attend the project vision statement development workshop. The stakeholder has emailed their requirements to the agile team lead, and believes that the vision statement is not critical.

How should the agile team lead respond?

Options:

A.  

Emphasize to the stakeholder that a common, detailed vision will better ensure team understanding of the project.

B.  

Personally meet with the stakeholder to understand their requirements, and then share the vision with the team.

C.  

Work with the team to create a vision from the stakeholder's supplied requirements.

D.  

Explain to the team that creating a vision is not critical in agile projects, as requirements may change over time.

Discussion 0
Question # 53

During product development, changes in technology and regulations require the team to reassess product architecture How should this technical debt be captured?

Options:

A.  

Include it in the product backlog and use a new indicator to annotate that it is technical debt

B.  

Include it in the product backlog as a low-priority issue

C.  

Since it is not a part of agile methodologies, it should not be tracked

D.  

Have team members maintain personal lists of issues and consolidate the lists during review

Discussion 0
Question # 54

When considering impact on a project, to whom should an agile project manager give top priority on the stakeholder list?

Options:

A.  

The stakeholder who can prevent the project from delivering within budget

B.  

The stakeholder who can prevent the project from achieving its goals

C.  

The stakeholder who can delay the project

D.  

The stakeholder who can work as a friend and help prepare the stakeholder list

Discussion 0
Question # 55

An agile lead is working on a project to build a new product that will bring substantial business value to a company. Company executives want to present the first release at an important industry fair the following month. The agile lead started the project the previous month, and the team planned the release to take 8 iterations. For the past 4 iterations, work has been performed as planned and on time. In the current iteration, however, one team member will be out for the remainder of the project. Without this team member, velocity would drop 30%.

What should the agile lead do to ensure the release will be on time for the fair?

Options:

A.  

Reduce the scope of the release to meet the deadline.

B.  

Deliver as many features as possible based on the new velocity.

C.  

Extend the project timeline to accommodate the missing team member.

D.  

Hire a new team member to replace the missing one.

Discussion 0
Question # 56

An agile team delivered a feature in the last iteration. The product owner, who missed the planning and review meetings, was dissatisfied with the feature. The team conducted a retrospective and reviewed the user stories related it.

What should the agile team do next?

Options:

A.  

Ensure that the product owner reviews the acceptance criteria for delivered user stories.

B.  

Augment the quality assurance and continuous integration processes for delivery.

C.  

Approach the relevant developers and testers regarding quality issues in upcoming iterations.

D.  

Ask the product owner to define the entire scope of delivery two to three iterations in advance.

Discussion 0
Question # 57

What should a product owner do when a new stakeholder is complaining that they are not receiving the relevant financial data regarding the project.

Options:

A.  

Work with the scrum master to give the stakeholder access to the related information radiator

B.  

Invite the stakeholder to the next sprint planning session so they can ask questions of the team

C.  

Ask the team to prepare the requested data in the next iteration

D.  

Direct the stakeholder to the project team so they can provide more data

Discussion 0
Question # 58

An agile coach is guiding a team across multiple locations. They need a united communication approach that involves task-oriented communications and discussion boards with effectiveness.

Which method of communication would be most effective?

Options:

A.  

Interactive communication

B.  

Pull communication

C.  

Interpersonal communication

D.  

Push communication

Discussion 0
Question # 59

A new CIO advocates an agile framework for new IT projects, but the team has reservations. How should the CIO ensure that the team will be aligned with this?

Options:

A.  

Obtain executive team buy-in by conducting a meeting to present the advantages of agile principles and processes.

B.  

Issue a memo of understanding that agile principles should be implemented for all new projects.

C.  

Introduce agile principles and processes, then make the change an experiment to obtain buy-in.

D.  

Require all staff and management to attend agile training and adhere to its principles.

Discussion 0
Question # 60

An organization highly values security. However, a team member on a project has found a way to save time and money with less robust security features.

What should the team member do?

Options:

A.  

Influence the customer

B.  

Mention the idea at the next retrospective

C.  

Show the customer how much time and money would be saved

D.  

Present the idea at the next ceremony attended by stakeholders to obtain their input

Discussion 0