Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-200 PMI Agile Certified Practitioner (PMI-ACP) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-200 Practice Questions

PMI Agile Certified Practitioner (PMI-ACP)

Last Update 17 hours ago
Total Questions : 482

Dive into our fully updated and stable PMI-200 practice test platform, featuring all the latest PMI ACP exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI ACP practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-200. Use this test to pinpoint which areas you need to focus your study on.

PMI-200 PDF

PMI-200 PDF (Printable)
$43.75
$124.99

PMI-200 Testing Engine

PMI-200 PDF (Printable)
$50.75
$144.99

PMI-200 PDF + Testing Engine

PMI-200 PDF (Printable)
$63.7
$181.99
Question # 71

Conversation transcript between the customer and the product owner (PO):

Customer: I am requesting a calendar feature for scheduling and reminding of upcoming releases that we can manage. We also need the calendar to indicate quarterly metrics deadlines, code freeze dates for financial close, and things like that.

PO: My understanding is that this is for tracking project deadlines. Would you need to see the project deadlines on your phone calendar?

Customer: Yes. I need to see a single snapshot on my phone. So, is it possible for me to connect my phone to this calendar app?

PO: Let me write up the requirements and get the development team on board with the deadlines. What phone do you own?

Customer: I own an Android phone, but I also need integration with the Apple phones.

Identify three minimum viable product (MVP) items. (Refer to Conversation transcript between the customer and the product owner (PO). Choose three.)

Options:

A.  

Monthly calendar view

B.  

Android phone integration

C.  

Windows end of support deadlines

D.  

Vacation calendar for team members

E.  

Scheduler to add events

F.  

Product increment release dates

Discussion 0
Question # 72

A team is building a product in three-week iterations. During the last retrospective, it was identified that there was a 20 percent increase from previous iterations in the number of reported defects and change requests.

Since this is causing the product's value to decrease, what should the team do?

Options:

A.  

Reevaluate the duration of the cycles, as faster cycles may allow for earlier detection of defects.

B.  

Run a sprint to clear all reported defects before taking new stories.

C.  

Change the control mechanism so that items are better tested before delivery.

D.  

Increase the opportunities to confirm common understanding with the client.

Discussion 0
Question # 73

How can a scrum team obtain more feedback from a minimally responsive outside stakeholder?

Options:

A.  

Keep sprints short.

B.  

Invite the stakeholder to the daily stand ups.

C.  

Ask the stakeholder for estimates for each user story.

D.  

Schedule more demos during each sprint.

Discussion 0
Question # 74

A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?

Options:

A.  

Capture risks and make them visible, and use a burn down chart to focus on reducing risks early in the project.

B.  

Ask the scrum master to extend the sprint's duration to allow more time to work through technical issues.

C.  

Place the impacted stories on the story board, and use daily stand ups to make the product owner aware of the technical issues.

D.  

Seek guidance from the development manager

Discussion 0
Question # 75

An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?

Options:

A.  

Add a goal to the current iteration to fully mitigate or control the risk.

B.  

Balance risk reduction and value adding activities in the next iteration.

C.  

Continue with the current plan to maintain team velocity.

D.  

Update the risk register and seek direction from a risk specialist.

Discussion 0
Question # 76

An agile team had unexpected technical problems in a project and was not able to complete the deliverables on time. During the retrospective meeting, the team openly discussed the causes for these issues and what can be done to avoid similar situations in the future.

What agile values and principles did the team demonstrate?

Options:

A.  

The team is being proactive by discussing how to better balance demands and capacity and make sure they have the right competencies.

B.  

The team shows respect for one another by listening to everyone's opinions and valuing human interaction during face-to-face meetings.

C.  

The team is providing one another with fast feedback to find those responsible for any mistakes so they can be avoided in the future.

D.  

The team eliminates potential waste by discussing who should be responsible for future risk management by actively applying the pi an-do-check-act (PDCA) method.

Discussion 0
Question # 77

An agile practitioner is in the process of refining requirements. The requirements keep changing based upon with whom the agile practitioner speaks.

What should the agile practitioner do in this situation?

Options:

A.  

Ask the scrum master to help reduce the rate of change.

B.  

Work with the agile coach to document the requirements in a collaborative way.

C.  

Work with the stakeholder directly rather than go through different layers of people.

D.  

Work with the development team to confirm the requirements.

Discussion 0
Question # 78

A newly formed team is struggling to work together and agree on how to complete tasks in the upcoming sprint. What should the scrum master do to support the team?

Options:

A.  

Resolve the disagreement for the team as a servant leader.

B.  

Encourage the team to continue trying to resolve their disagreements.

C.  

Advise the team on the correct course of action to avoid disagreements.

D.  

Remove the team members that are in disagreement to ensure unity in the team.

Discussion 0
Question # 79

The first project vision statement meeting for a newly formed team did not achieve its outcome. Lack of participation combined with conflicting views of those who participated led to disagreement on how to proceed.

How can the team improve their collaboration?

Options:

A.  

Set clear expectations and allow everyone to contribute.

B.  

Prepare the project vision statement and then present it to the team.

C.  

Ask senior management to address the situation.

D.  

Seek assistance from the scrum master to mediate the conflict.

Discussion 0
Question # 80

A product owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog. What should the product owner do next?

Options:

A.  

Remove the second half of the backlog, and communicate their decision in the next backlog grooming meeting

B.  

Reprioritize backlog items to future iterations

C.  

Work with the team to deploy the first half of the backlog to ensure that value is realized

D.  

Meet with project stakeholders to review the backlog and determine if the scope should be adjusted

Discussion 0