Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-200 PMI Agile Certified Practitioner (PMI-ACP) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-200 Practice Questions

PMI Agile Certified Practitioner (PMI-ACP)

Last Update 20 hours ago
Total Questions : 482

Dive into our fully updated and stable PMI-200 practice test platform, featuring all the latest PMI ACP exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI ACP practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-200. Use this test to pinpoint which areas you need to focus your study on.

PMI-200 PDF

PMI-200 PDF (Printable)
$43.75
$124.99

PMI-200 Testing Engine

PMI-200 PDF (Printable)
$50.75
$144.99

PMI-200 PDF + Testing Engine

PMI-200 PDF (Printable)
$63.7
$181.99
Question # 101

A scrum team has eight developers, but only two are database engineers. During the last few retrospectives, the team identified that most sprint stories are dependent upon database engineers. This has created a bottleneck in completing stories.

What should be proposed to the team?

Options:

A.  

Have other team developers attend training to learn database skills.

B.  

Monitor the retrospectives of two additional sprints before taking action.

C.  

Plan fewer stories for the sprint to reduce the database engineers' workload.

D.  

Ask the scrum master to work with the product owner to remove backlog stories that have database dependency.

Discussion 0
Question # 102

Question # 102

A project team's manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (see Exhibit A).

At the end of which sprint will the minimum viable product (MVP) be completed?

Options:

A.  

7

B.  

8

C.  

9

D.  

10

Discussion 0
Question # 103

An agile project manager is working on a project to develop a customer service website. The project manager is organizing a workshop to plan the next release: To add the feature of receiving and resolving customer complaints. Which two actions should the project manager ask the team members to take before the workshop? (Choose two.)

Options:

A.  

Prepare an effort estimation for each story based on their technical expertise.

B.  

Compile a list of ideas to improve the velocity of the team so they can plan more story points in the next sprint.

C.  

Prepare a list of tasks required to accomplish the goal and the order in which they should be executed.

D.  

Read and identify user stories from the backlog that will contribute to accomplishing the goal.

E.  

Consider the possible risks of each selected user story and the value they add for the final user.

Discussion 0
Question # 104

The scrum master for a large project must provide an estimate of what can be delivered in six months What should the scrum master do?

Options:

A.  

Commit to a specific feature set for delivery

B.  

Explain that a commitment will be provided after planning

C.  

Have the team estimate in story points to commit to a specific set of features

D.  

Use the team's historical velocity to calculate a range of features that can be delivered

Discussion 0
Question # 105

A project team realizes that an important task on the iteration backlog will take more time than originally estimated What should the project team do?

Options:

A.  

Continue working on the task until it is completed

B.  

Remove the task owner from the project team

C.  

Add resources to reduce time to task completion

D.  

Stop working on the task and include it in the next iteration

Discussion 0
Question # 106

Question # 106

An agile development team is working on a digital transformation project and is facing challenges in obtaining consistent feedback from stakeholders who are dispersed around the world. The product owner is under pressure as this lack of engagement has led to prolonged decision-making cycles and has adversely affected the outcomes of sprints.

How should the team improve stakeholder engagement to help ensure timely feedback and better decision-making? (Refer to Stakeholder Power/Interest Grid)

Options:

A.  

Implement a dynamic feedback platform leveraging collaboration tools, accommodating diverse schedules and enabling stakeholders to provide feedback asynchronously.

B.  

Establish a rotating stakeholder committee composed of representatives from different regions and departments, ensuring diverse perspectives are considered in decision-making processes.

C.  

Enforce a strict policy requiring stakeholders to attend weekly synchronous feedback sessions, leveraging technology to accommodate various time zones and scheduling conflicts.

D.  

Appoint regional liaison officers responsible for coordinating stakeholder interactions within their respective time zones, facilitating regular communication and feedback exchange.

Discussion 0
Question # 107

Several team members have complained to senior management about their scrum master's processes. What should the scrum master do to address the team's process concerns?

Options:

A.  

Include senior management in the process decisions.

B.  

Communicate the processes and expectations to the team.

C.  

Conduct retrospectives at the end of every sprint.

D.  

Include process feedback in the next sprint planning session.

Discussion 0
Question # 108

During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points. How should this be handled?

Options:

A.  

The story should be assigned eight story points as per the majority vote

B.  

The story should be added to the backlog and reassessed later

C.  

The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached

D.  

The decision for the number of story points should be made by the customer

Discussion 0
Question # 109

An agile lead is experienced with predictive and agile approaches. The agile lead was recently invited by human resources (HR) to be part of a learning team. During roundtable discussions with the project management team, the agile lead states: "I foster a safe environment for disagreement so my team feels empowered to move forward without obstacles."

What is the agile lead attempting to highlight?

Options:

A.  

Ownership, because team members will be in charge of whatever happens during the project life cycle.

B.  

Conflict is not productive and team members should resolve issues by themselves.

C.  

Better decision-making, because the team is encouraged to join in constructive conflict.

D.  

Leaders should incentivize conflict because it is inevitable in the workplace.

Discussion 0
Question # 110

An agile team has started to worry because lately they have seen an increase in the number of issues. There seems to be a large variance in the quality of the work items delivered. The team now realizes that a shared understanding of quality may not exist among team members.

What should the team do?

Options:

A.  

The team should move to test-driven development as defects are not being detected during testing.

B.  

The team should account for the increased problems in their velocity forecasts since unexpected changes occur in agile projects.

C.  

The team should discuss their definition of done (DoD) and make changes to ensure there is common understanding of the acceptance criteria.

D.  

The team's agile project manager should facilitate the development of a new, detailed test procedure that all team members must follow.

Discussion 0