Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Free PMI Risk Management Professional (PMI-RMP) Exam Practice Questions

Exams4sure Dumps

Exam style questions across every PMI-RMP domain

Last Update 3 days ago
Total Questions : 333

Start with our free PMI-RMP practice questions, carefully crafted to mirror the domains, phrasing, and difficulty of the real PMI Certification exam. Each PMI-RMP exam question comes with a detailed rationale that explains not just which answer is correct but why the others fall short. That's how concepts stick. Use the free set to benchmark yourself: identify your PMI weak domains, see where you're losing marks, and build a focused study plan in minutes.

PMI-RMP PDF

PMI-RMP PDF (Printable)
$54.25
$154.99

PMI-RMP Testing Engine

PMI-RMP PDF (Printable)
$59.5
$169.99

PMI-RMP PDF + Testing Engine

PMI-RMP PDF (Printable)
$74.55
$212.99
Question # 51

An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?

Options:

A.  

Update the risk register

B.  

Meet with the project ' s stakeholders

C.  

Revise the risk management plan

D.  

Ensure sufficient resources are available

Discussion 0
Question # 52

The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?

Options:

A.  

Review the assumptions analysts

B.  

Conduct a checklist analysis on each risk

C.  

Create a risk response plan for those risks

D.  

Review the risk register to check for the new risks

Discussion 0
Question # 53

When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project ' s contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.

What should the project manager do?

Options:

A.  

Process the freight invoices at higher shipping costs against the project ' s contingency allowance.

B.  

Request a formal change order from the customer to increase the project ' s total budget.

C.  

Process the freight invoices for the budgeted amount and hope the shipping company will forgive the difference.

D.  

Ask the project sponsor to cover the additional shipping costs on the company ' s reserves account.

Discussion 0
Question # 54

A risk manager has noticed that response actions are not working as expected when a risk occurs, mainly because the risk triggers are not well-defined. Which tool should the risk manager use to facilitate risk trigger identification in the upcoming risk review assessment?

Options:

A.  

Risk burndown chart

B.  

Ishikawa diagram

C.  

Risk breakdown structure (RBS)

D.  

Affinity diagram

Discussion 0
Question # 55

A project team ' s manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (Refer to the email exhibit).

How many total story points is the entire initiative?

Options:

A.  

72

B.  

60

C.  

40

D.  

32

Discussion 0
Question # 56

A project team is discussing which risk requires more attention and resources for response planning. The team evaluated the schedule to determine which activity had the greatest impact on the project ' s total duration.

After analyzing the quantitative analysis results, which activity should the team pay more attention to?

Use the chart for the analysis.

Options:

A.  

Activity 3.2

B.  

Activity 2.3

C.  

Activity 3.5

D.  

Activity 1.2

Discussion 0
Question # 57

At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it ' s complete since it is such a short and simple project.

How should the risk manager respond to this comment?

Options:

A.  

The risk register must only be updated if a change is approved during the project.

B.  

Agree on the condition that the risk register be updated if the project environment changes.

C.  

Compromise by updating the risk register at the end of each phase only.

D.  

Insist on continuous review and updating of the risk register during the project.

Discussion 0
Question # 58

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.

How should the risk manager interpret such a low CPI value?

Options:

A.  

The cost control processes is ineffective.

B.  

The cost baseline is inaccurate.

C.  

The actual reported costs are inaccurate.

D.  

The cost related risks are effectively managed.

Discussion 0
Question # 59

The project manager performed ' a variance analysis on the project during the execution phase. The variances were shown as increasing

What does this result imply?

Options:

A.  

The uncertainty and risk are increasing.

B.  

The project schedule is lagging behind.

C.  

There is no potential for future deviation.

D.  

The project is over budget.

Discussion 0
Question # 60

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

Options:

A.  

Close and communicate the results of the risk response actions.

B.  

Run a workshop to analyze the effectiveness of the risk plan.

C.  

Conduct a risk reserve analysis and document the results.

D.  

Verify that all risk response actions have been documented. 

Discussion 0

Free Exams Sample Questions