Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-RMP Practice Questions

PMI Risk Management Professional (PMI-RMP) Exam

Last Update 3 days ago
Total Questions : 284

Dive into our fully updated and stable PMI-RMP practice test platform, featuring all the latest PMI Certification exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI Certification practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-RMP. Use this test to pinpoint which areas you need to focus your study on.

PMI-RMP PDF

PMI-RMP PDF (Printable)
$54.25
$154.99

PMI-RMP Testing Engine

PMI-RMP PDF (Printable)
$59.5
$169.99

PMI-RMP PDF + Testing Engine

PMI-RMP PDF (Printable)
$74.55
$212.99
Question # 1

The scope of a large mobile network deployment project includes equipment to be furnished by the customer. The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.

What should the risk manager do?

Options:

A.  

Follow up on the schedule and assess the best course of action if any delays are detected.

B.  

Ensure the equipment constraint is well-documented and manage it as a high-impact project risk.

C.  

Raise the issue with the project sponsor so it can be handled as a sales or contractual matter.

D.  

Obtain a signed commitment from the customer that equipment will be delivered on time. 

Discussion 0
Question # 2

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

Options:

A.  

Ask the project sponsor if every risk in the risk register can have the same priority.

B.  

Mark every identified risk as an extremely high priority and any future risks as a lower priority.

C.  

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.

D.  

Perform a sensitivity analysis and determine the correct priority of every identified risk.

Discussion 0
Question # 3

A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?

Options:

A.  

Risk assessment criteria

B.  

Project management plan

C.  

Project assumptions

D.  

Risk management plan 

Discussion 0
Question # 4

Business rhythm can fluctuate greatly between different industries and vary between companies within the same industry. What should be used 10 determine how often a project ' s risk register should be updated or reviewed in a given year when the project is in an industry with a very high business rhythm?

Options:

A.  

The risk management plan

B.  

The risk triggers

C.  

The risk prioritization criteria

D.  

The portfolio management plan

Discussion 0
Question # 5

A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.

What three artifacts should the project manager consult or review during this process? (Choose three.)

Options:

A.  

Project contracts

B.  

Lessons learned registers from analogous projects

C.  

Risk register

D.  

Risk management plan

E.  

Code of regulations

Discussion 0
Question # 6

An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?

Options:

A.  

Ensure sufficient resources are available

B.  

Revise the risk management plan

C.  

Update the risk register

D.  

Meet with the project ' s stakeholders

Discussion 0
Question # 7

The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GT

G.  

What should the project manager do first?

Options:

A.  

Include the risk in the register and communicate with the stakeholders.

B.  

Communicate with the client to provide the previous shutdown plan.

C.  

Review and update the project schedule.

D.  

Interview the other project manager to learn more details.

Discussion 0
Question # 8

 

One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.

Which risk response strategy is the program manager using in this scenario?

Options:

A.  

Escalate

B.  

Transfer

C.  

Enhance

D.  

Exploit 

Discussion 0
Question # 9

A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

What should the risk manager do in this scenario?

Options:

A.  

Review project schedule estimates.

B.  

Change the response strategies.

C.  

Reduce the contingency reserves.

D.  

Conduct a risk planning workshop.

Discussion 0
Question # 10

A company is preparing a formal response to bid for an infrastructure engineering, procurement, and construction project. When should a risk register be developed to identify risks?

Options:

A.  

During the project execution phase to allow the project manager to understand the risk attitudes of stakeholders.

B.  

When a client project kick-off meeting is held to introduce risk assessment process to the client.

C.  

Before a formal bid response is provided to the client to gain a greater understanding of the project’s risk profile.

D.  

After a project budget is set up with a purchase order to charge hours for a risk workshop.

Discussion 0
Get PMI-RMP dumps and pass your exam in 24 hours!

Free Exams Sample Questions