Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMP Project Management Professional (PMBOK 7th Version) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMP Practice Questions

Project Management Professional (PMBOK 7th Version)

Last Update 17 hours ago
Total Questions : 2191

Dive into our fully updated and stable PMP practice test platform, featuring all the latest Project-Management-Professional exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free Project-Management-Professional practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMP. Use this test to pinpoint which areas you need to focus your study on.

PMP PDF

PMP PDF (Printable)
$139.65
$399

PMP Testing Engine

PMP PDF (Printable)
$157.15
$449

PMP PDF + Testing Engine

PMP PDF (Printable)
$209.65
$599
Question # 451

A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?

Options:

A.  

Focus on remediation not merely on correcting symptoms

B.  

Compare the team's performance against other project teams

C.  

Identify potential failure points based on the iteration workload

D.  

Motivate the team to perform better

Discussion 0
Question # 452

A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.

What should the project manager do in this situation?

Options:

A.  

Review the work allocation and reassign some tasks to shorten the critical path.

B.  

Maintain the task assignments as planned and compress the other tasks to keep the project on schedule.

C.  

Ask the team members to work overtime to finish the tasks on time according to the schedule.

D.  

Keep the task assignments unchanged since the project management plan has been approved.

Discussion 0
Question # 453

A project manager is managing a hybrid project A stakeholder has directly contacted a team member and has requested a change Due to the request, the team member was distracted from their work, which caused a loss in productivity.

What should the team member do?

Options:

A.  

Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the project manager.

B.  

Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity.

C.  

Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the change control board (CCB).

D.  

Inform the scrum master so that the change can be discussed directly with the stakeholder.

Discussion 0
Question # 454

A project manager is using a hybrid approach for project delivery. The

development team was sized, but is not yet fully resourced. The project manager is working

on defining the project schedule.

What should the project manager do to address the issue of developer availability?

Options:

A.  

Organize a planning session with the development team and use their estimations to complete the schedule.

B.  

Ask the resource manager when the new contractor is available to start and change the delivery date for the project schedule.

C.  

Ask the sponsor to provide the desired completion date for project activities and complete the schedule.

D.  

Use expert judgment to estimate all of the tasks and complete the schedule in the allocated time.

Discussion 0
Question # 455

A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.

% What should the project manager do next?

Options:

A.  

Update the assumptions log and change log, and implement the change control process.

B.  

Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests.

C.  

Inform the client that the project cannot meet the project timeline and additional costs will be incurred.

D.  

Deliver what was planned in the project management document according to the specifications.

Discussion 0
Question # 456

A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.

What should the project manager do?

Options:

A.  

Schedule a meeting with the previous project manager

B.  

Submit a change request to the change control board (CCB)

C.  

Schedule training for project team members

D.  

Conduct an earned value analysis (EVA)

Discussion 0
Question # 457

An agile project team discovers that they are unable to implement a feature completely in the first iteration The team believes it may not be able to complete the tasks in the second iteration. The feature is a critical component that the customer has prioritized.

What should the team do?

Options:

A.  

Go back to the customer and explain that they cannot implement the feature completely in one iteration.

B.  

Reduce the scope of the feature to fit into one iteration and deliver it to the customer

C.  

Ask the customer to simplify the feature so that it can be implemented in one iteration

D.  

Split the feature into smaller subfeatures. implement them, and then deliver them incrementally in multiple iterations

Discussion 0
Question # 458

A project manager is preparing a project closure report. The project sponsor is confident about the success of the project, but the client is not sure that the project outputs will achieve their business needs.

Which aspect should the project manager highlight in the closure report to address the stakeholder's concern?

Options:

A.  

How the quality was managed

B.  

How the acceptance criteria were met

C.  

How the scope was managed

D.  

How the stakeholders were managed

Discussion 0
Question # 459

Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised What should the project manager do to ensure success of the project?

Options:

A.  

Review and prioritize new requirements with stakeholders to determine which change requests are needed.

B.  

Escalate the issue to the project sponsor and seek support to keep the original requirements.

C.  

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements

D.  

Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project

Discussion 0
Question # 460

In a fixed time and budget project the customer wants the development of a core component to be based on agile practices, as the final scope of (he requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.

Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two)

Options:

A.  

Limit the number of iterations for development in the contract.

B.  

Establish a governance committee to review the contract delivery

C.  

Tier the contract for fixed and agile components

D.  

Provide alternatives to scope change at specific project phases within the contract.

E.  

Require that only internal resources be utilized for this project

Discussion 0
Question # 461

A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?

Options:

A.  

Determine a leadership style that is suitable for that location.

B.  

Check if resources from headquarters can also be assigned to the project.

C.  

Mentor the team members to perform project management.

D.  

Assign a local resource to manage communication with the team.

Discussion 0
Question # 462

A project manager is working with an agile team. A key stakeholder who does not

join the sprint planning session is very unhappy, as the delivery date for the final product has

been pushed back three times. What should the project manager do?

Options:

A.  

Meet with the stakeholder to understand the concern and business impact, reprioritize as necessary, and invite them to join the sprint planning session.

B.  

Direct the product owner to drop other work in progress and work on this stakeholder’s requirement as the top-priority item.

C.  

Share the prioritized items that the team is working on with the stakeholder and invite them to join the sprint planning session.

D.  

Secure some additional funding to recruit more resources to the project team to enable faster delivery.

Discussion 0
Question # 463

A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

Question # 463

Options:

Discussion 0
Question # 464

An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country’s unique requirements. The expected revenue for the product is the same for each country.

Which release strategy should the project manager recommend?

Options:

A.  

A risk-based strategy to maximize the perceived value of the product by launching it to the countries with the lowest technical complexity

B.  

An iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country

C.  

A quality-based strategy to maximize post-market adoption by releasing the product to the countries with the lowest probability of reporting field issues

D.  

A financial-based strategy to reduce the roll-out effort and costs by planning a single, bundled release to all countries at the same time

Discussion 0
Question # 465

A company has agreed to run a transformation project using agile approaches.

During the implementation, there is pushback from the functional groups that the project is moving too fast.

What should the project manager have done at the beginning of the project to prevent this from happening?

Options:

A.  

Circulated the project charter

B.  

Assessed the organizational culture

C.  

Determined the level of maturity of the employees

D.  

Communicated the project schedule

Discussion 0
Question # 466

The portfolio management office wants to cut costs by suspending some ongoing

projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio

management office has not backed down on their plan.

What should the project manager do to continue the project?

Options:

A.  

Meet with the project team and revise the project goals.

B.  

Update the project charter to make it align with organizational strategy.

C.  

Demonstrate the project alignment to the organizational strategy.

D.  

Escalate the issue with the project sponsor to request support.

Discussion 0
Question # 467

After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.

How should the project manager handle this situation?

Options:

A.  

Comply with the project sponsor's request to not archive the project artifacts.

B.  

Document the project sponsor's instructions as the archived project artifacts.

C.  

Archive the project artifacts on the project manager's local computer for future reference

D.  

Consult with the project management office (PMO) for guidance on project artifacts.

Discussion 0
Question # 468

A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

What are the first two actions the project manager should perform? (Choose two)

Options:

A.  

Create a change request to discuss with the change control board (CCB).

B.  

Request additional budget for contingency.

C.  

Perform a risk identification process with the project team.

D.  

Consult with the project stakeholders.

E.  

Discuss the possible impacts with subject matter experts (SMEs).

Discussion 0
Question # 469

A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.

How should the project manager handle this issue?

Options:

A.  

Disregard these stakeholders since the relevant documents have been secured to execute this project.

B.  

Update the stakeholder register and risk management plan.

C.  

Update the stakeholder register and revise the stakeholder engagement plan.

D.  

Explain to the community members why they were not included as stakeholders for the project.

Discussion 0
Question # 470

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)

Options:

A.  

Look for processes that cause bottlenecks and slow down the team's agility

B.  

Assign the items with high complexity lo senior developers

C.  

Empower the learn to make decisions to remove impediments

D.  

Work with the team to remove impediments as quickly as possible

E.  

Move the items with high complexity to the last iterations

Discussion 0
Question # 471

A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.

What should the project manager do next?

Options:

A.  

Contact the human resource (HR) department for a solution.

B.  

Speak with the key team member to clarify the situation.

C.  

Conduct a meeting with the team to deliberate on a decision.

D.  

Suspend the team member until further notice.

Discussion 0
Question # 472

The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.

What should the project manager do to resolve and prevent additional arguments?

Options:

A.  

Monitor the interactions between the vendor and infrastructure manager going forward.

B.  

Host a meeting with the vendor and infrastructure manager to help resolve their disagreement.

C.  

Escalate the issue to the sponsor so appropriate action can be taken.

D.  

Instruct the vendor to correct the problem without additional arguments.

Discussion 0
Question # 473

While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report:

Approved Work Package Cost Estimates: US$9,500

Contingency reserves: $500 %

Management reserves: 10% of contingency reserves

Percent complete of the project: 50%

Planned percent of the project: 40%

Actual costs of the project: US$4,500

What is accurate about the project status?

Options:

A.  

The actual work is 25% more than the planned work.

B.  

The project cost is 10% lower than planned.

C.  

The actual work is 25% less than the planned work.

D.  

The project cost is 10% higher than planned.

Discussion 0
Question # 474

A project manager is assigned to a large complex project with cross-functional dependencies. The project enters a new phase requiring new stakeholders to be added with conflicting priorities. How should the project manager ensure successful engagement with the stakeholders?

Options:

A.  

Invite all stakeholders to status meetings.

B.  

Identify and categorize the stakeholders.

C.  

Interact individually with the stakeholders.

D.  

Recognize the diversity of the stakeholders.

Discussion 0
Question # 475

A new project manager is taking over a project to deliver a new payroll management system that is running behind schedule. In addition, costs are rising due to many late changes requested by the client. What should the project manager do first?

Options:

A.  

Schedule a meeting with stakeholders and explain the situation.

B.  

Discuss the situation with the sponsor and seek their guidance.

C.  

Arrange a time to meet with the team to understand the parameters.

D.  

Meet with the team to understand the areas of concern.

Discussion 0
Question # 476

A new stakeholder is unaware of the existence of the project a few weeks before the final deliverable and project completion. What should the project manager do first?

Options:

A.  

Escalate this issue to the project sponsor.

B.  

Communicate the full details of the project activities to the stakeholder and solicit input.

C.  

Analyze this stakeholder’s interest and impact.

D.  

Share the summary of the project activities with the stakeholder and conclude the project.

Discussion 0
Question # 477

A project manager is assigned to lead a team comprised of business executives. After several roadmaps were denied by the sponsor, the project manager asks to be removed from the project. The sponsor urges the project manager to find a solution as the sponsoring organization requested their assignment. What should the project manager do?

Options:

A.  

Emphasize to the executives that the project manager was specifically requested for this project

B.  

Schedule deliverables solely based on priorities and must-have-by dates, and gauge responses

C.  

Hold a team meeting emphasizing existing governance policies and procedures

D.  

Adopt a project framework aligned to the executives’ availabilities and then evaluate the risks

Discussion 0
Question # 478

A project to develop a new service is initiated by a telecommunications operator. The project management plan was developed, approved, and shared with respective stakeholders. What should the project manager do next?

Options:

A.  

Define deliverables, activities, and scheduling information.

B.  

Estimate activity durations and list resource requirements.

C.  

Incorporate the project's scope baseline in the scope statement.

D.  

Start execution of the work packages according to the plan.

Discussion 0
Question # 479

A project manager is hired to work on a very large, complex project that requires the team to complete a significant number of specialized tasks. What strategy should the project manager incorporate to help organize, assign, and monitor these tasks?

Options:

A.  

Create a list of the tasks and send it to the project sponsor for review and approval.

B.  

Develop a work breakdown structure (WBS) that decomposes the project deliverables into work packages.

C.  

Schedule a meeting with the stakeholders to determine which tasks can be eliminated.

D.  

Prepare a resource management plan that details all the resources needed to complete the tasks.

Discussion 0
Question # 480

A project manager is working on a large event and developing budgets for sign-off. The stakeholders and project sponsor are all working remotely using various tools to ensure that all documentation is tracked and handled discretely and appropriately. The primary stakeholder has missed several deadlines for the milestone sign-offs, resulting in the project manager being forced to find alternative suppliers for items, now at higher costs. When questioned regarding the delays, the stakeholder says the notifications hadn’t appeared in their email inbox. How should the project manager proceed?

Options:

A.  

Escalate the issue to the IT department and request they check the software on the stakeholder's computer.

B.  

Request human resources (HR) intervene and send the stakeholder to appropriate technical training.

C.  

Assess whether the communications channels are appropriate for the primary stakeholder and amend accordingly.

D.  

Request the primary stakeholder be replaced to avoid any more delays and budget issues.

Discussion 0
Question # 481

A project manager is leading a hybrid project. A project team member has not been delivering on time; as a result, the project is about to be delayed. What should the project manager do?

Options:

A.  

Revise the project schedule with the customer

B.  

Schedule a meeting with the project team to address timelines

C.  

Negotiate revised timelines with the project sponsor

D.  

Discuss the situation with the project team member

Discussion 0
Question # 482

A project manager notices a product owner has been unresponsive over the last few weeks. During one-on-one sessions, the product owner is unable to provide complete information, leading to rework of the project stories. What should the project manager do first?

Options:

A.  

Increase the sprint duration to accommodate the additional work

B.  

Conduct a root cause analysis before addressing the issue

C.  

Escalate the issue to the stakeholder's functional manager

D.  

Cancel the one-on-one sessions and obtain the information via email

Discussion 0
Question # 483

There are several dependent work streams in a project. Some project stakeholders feel that coordination among team members and progress visibility are lacking. What should the project manager do?

Options:

A.  

Discuss the concerns with the project sponsor

B.  

Organize a team meeting to review the project status

C.  

Review and update the communications management plan

D.  

Escalate the concerns to the project steering committee

Discussion 0
Question # 484

A project manager has been informed by a vendor that a shipment with supplies needed for the project will be delayed by six weeks. What should the project manager do first?

Options:

A.  

Find another vendor to deliver the required supplies on time

B.  

Ask the procurement manager to resolve the issue with the vendor

C.  

Document this as a risk and define a risk response plan

D.  

Treat the risk as an issue and launch the risk response plan

Discussion 0
Question # 485

After a project review meeting, a key stakeholder tells another stakeholder they do not trust the project status report. The second stakeholder approaches the project manager and mentions the conversation. What should the project manager do?

Options:

A.  

Request the sponsor ask the key stakeholder to be attentive during the project review meeting

B.  

Schedule a meeting with the key stakeholder to address the issue and obtain direct feedback

C.  

Email the status report to all stakeholders and ask them to review and provide feedback

D.  

Present the status report in a chart and assume everyone understands the report

Discussion 0
Question # 486

A construction project is in its final stage when the owner of a private property where the pipeline is routed refuses to collaborate. The lack of collaboration causes a project delay, but the client insists that the project must be completed as per the contract. What should the project manager do next?

Options:

A.  

Request additional budget from the project sponsor and raise a dispute with the property owner to force them to collaborate.

B.  

Use the contingency reserve, add more resources, and reroute the pipeline to complete the project as per the contract timeline.

C.  

Escalate the routing pipeline issue to the project change control board (CCB) and wait for a resolution to the conflict.

D.  

Review the agreement with the property owner, schedule a meeting with them to discuss their concerns, and inform the client.

Discussion 0
Question # 487

A project sponsor is upset that a vital project might miss an agreed-upon delivery deadline. The sponsor asks the project manager to check whether the project team can do anything to deliver on time. What should the project manager do first?

Options:

A.  

Increase project team resources to maintain the timeline

B.  

Conduct simulations to determine the best way forward to ensure timely delivery

C.  

Reduce scope to deliver on time

D.  

Work with the team to ensure the project is delivered on time

Discussion 0
Question # 488

A project manager is leading a project and is asked to negotiate on behalf of their organization. The organization requires that three quotes from different suppliers be acquired prior to submitting a purchase request to the finance department. What should the project manager do to align with this requirement?

Options:

A.  

Perform a make-or-buy analysis

B.  

Review the statement of work (SOW)

C.  

Leverage the enterprise environmental factors (EEFs)

D.  

Refer to the organizational process assets (OPAs)

Discussion 0
Question # 489

The execution stage of a construction project is beginning. There are many areas and phases to be built. The project team wants to review the relationships between the most important tasks to ensure that major items are executed properly during this stage. What project artifact should the project manager review with the team?

Options:

A.  

Project milestone chart

B.  

Project schedule management plan

C.  

Project statement of work (SOW)

D.  

Project program evaluation review technique (PERT)

Discussion 0
Question # 490

A project manager is leading a complex project. The team is being challenged with frequent, incremental, and uncontrolled changes to the project. What should the project manager do?

Options:

A.  

Establish a detailed quality management plan.

B.  

Establish a detailed risk management plan.

C.  

Establish a detailed scope management plan.

D.  

Establish a detailed schedule management plan.

Discussion 0
Question # 491

A project lead conducted coordination meetings to estimate the budget and confirm the timeframe for a new project. Due to internal resource challenges, outsourcing some activities could be implemented during execution. What should the project lead ensure before submitting the project for a stage gate review to receive the needed investment?

Options:

A.  

Add a percentage for management reserve

B.  

Conduct a retrospective with all involved stakeholders

C.  

Initiate a recruitment plan to explore the market situation

D.  

Align with relevant stakeholders on the procurement strategy

Discussion 0
Question # 492

During the project planning phase, the customer explained the importance of delivering the project results proposed in the scope as soon as possible. What should the project manager do first to address this?

Options:

A.  

Assess the opportunities to deliver project value incrementally

B.  

Gather all the requirements’ details and schedule a refinement meeting

C.  

Prepare a project management plan for the full scope using an agile approach

D.  

Approve a change request to change the project approach to agile

Discussion 0
Question # 493

A project manager recently took over an ongoing project. Within a few weeks on the project, the project manager discovers that there are continuous change requests from different project end users. What is the probable cause for this?

Options:

A.  

Undefined change control process

B.  

Unidentified project risks

C.  

Improper work breakdown structure (WBS)

D.  

Incomplete requirements

Discussion 0
Question # 494

An experienced project manager has recently joined a troubled project. The project is impacted by multiple delays caused by a vendor’s late delivery of new servers. Due to budget restrictions, the project manager cannot switch vendors, and the project must be completed within a maximum of 90 days as agreed. What should the project manager do?

Options:

A.  

Request the vendor to provide the servers on time as penalties may be applied

B.  

Wait until the project deadline is reached in order to use contingency funds

C.  

Reach out to the vendor to determine a plan to get the project back on track

D.  

Review lessons learned from previous projects and take action accordingly

Discussion 0
Question # 495

An agile team of specialized engineers has completed some tasks later than planned and with a lower quality than expected. The situation is limiting the value the team is creating for the business. What should the project manager do next?

Options:

A.  

Execute the next iteration planning considering the quality issues.

B.  

Schedule quality reviews to obtain stakeholder approvals and feedback.

C.  

Confirm the right quality tests are applied before moving to the next iteration.

D.  

Include all the quality problems found in the technical debt backlog.

Discussion 0
Question # 496

A project has a schedule performance index (SPI) of 0.75 and a cost performance index (CPI) of 1.1. As a result, the project manager is considering either fast-tracking or crashing the project schedule to bring the project back on track again. What could be a secondary result of these actions?

Options:

A.  

A decrease in the project cost

B.  

An increase in the project risk

C.  

Additional project scope

D.  

Additional resources

Discussion 0
Question # 497

A project manager has recently been appointed to lead a critical software development project in a hybrid environment. What should the project manager do first to understand the project quickly and manage the project effectively?

Options:

A.  

Identify key stakeholders and hold a project kickoff meeting to engage the stakeholders and obtain commitment.

B.  

Assess the project management plan for dependencies and possible risks then validate stakeholder understanding.

C.  

Review the project charter to understand the objectives, high-level scope, and business need.

D.  

Share project objectives and scope with the team to ensure it understands the project value.

Discussion 0
Question # 498

A project manager is assigned to an IT project to deliver a new accounting system. Some managers at the company do not see the value of this project and say they will not use the new system. What two actions should the project manager take? (Choose 2)

Options:

A.  

Review the list of stakeholders that will be affected by starting this business initiative.

B.  

Continue with the project the way it was planned and validated by the sponsor.

C.  

Describe the outcome of the project and business value to all company stakeholders.

D.  

Add this issue to the risk register and monitor stakeholder engagement at the next milestone.

E.  

Modify the project management plan and scope of work to avoid future difficulties.

Discussion 0
Question # 499

During the requirements gathering and analysis stage for the project, the team members are debating some functionality issues that are expected to be included in the scope. Due to this discussion, the planning activity for the scope definition is running late. What should the project manager do?

Options:

A.  

Timebox the team members’ debate to ensure the activity is completed on time.

B.  

Review expectations with all team members who are working on this activity.

C.  

Discuss the issue with the team members who are delaying the activity.

D.  

Ask team members to document all points that will need to be refined later.

Discussion 0
Question # 500

A project is almost complete when a key stakeholder raises a concern because the functionality of their preferred requirement was not showcased in the prototype. The prototype has already been approved and developers have started work on the final application. What should the project manager do next?

Options:

A.  

Be firm with the stakeholder, since they would push through any unreasonable requirement

B.  

Document the stakeholder's requirements and validate those requirements by engaging stakeholders more often

C.  

Inform the stakeholder that little can be done at this time, since core development has begun and the project must be delivered on time

D.  

Inform the stakeholder that the requirement will be included in the next deliverable cycle

Discussion 0