PMP Practice Questions

Project Management Professional (PMBOK 7th Version)

Last Update 20 hours ago
Total Questions : 2191

Dive into our fully updated and stable PMP practice test platform, featuring all the latest Project-Management-Professional exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free Project-Management-Professional practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMP. Use this test to pinpoint which areas you need to focus your study on.

PMP PDF

PMP PDF (Printable)
$139.65
$399

PMP Testing Engine

PMP PDF (Printable)
$157.15
$449

PMP PDF + Testing Engine

PMP PDF (Printable)
$209.65
$599
Question # 551

A project is being planned with two hardware deliverables and one software deliverable that will be used to monitor the operation of the two hardware deliverables. When preparing the consolidated project schedule, what should be the top priority for the project manager?

Options:

A.  

The interdependencies between the deliverables

B.  

The business continuity plan of the deliverables

C.  

The stakeholder engagement plan

D.  

The user stories and story points

Discussion 0
Question # 552

A project manager is leading a highly visible project initiative. A few weeks after kickoff, the project manager starts receiving requests for updates from various stakeholders. What should the project manager do?

Options:

A.  

Remove those stakeholders from the project since they may negatively affect project goals

B.  

Invite all project stakeholders to join the daily standup meeting to ensure they are informed

C.  

Schedule a meeting with relevant stakeholders to review the project communications plan

D.  

Explain to the stakeholders that they must request project updates from the project sponsor

Discussion 0
Question # 553

A new project manager has been hired at a company that has suffered many project failures. The project manager has been tasked with delivering a software product for the company’s biggest customer. The customer has not been able to articulate how a major piece of functionality should work. The project manager wants to deliver value immediately. How should the project manager approach the software development life cycle with this customer?

Options:

A.  

Assign a business analyst to build detailed requirements so the project manager can estimate the project duration

B.  

Explain that the team will build a production prototype model to help the customer visualize how the features should work

C.  

Add extra time and resources to the estimating phase to accommodate the lack of requirements

D.  

Raise a risk that scoping and estimating will be delayed if the customer cannot approve requirements

Discussion 0
Question # 554

A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory-How should the project manager support their claim to the vendor?

Options:

A.  

Share unsuccessful results from previous projects with a similar scope

B.  

Provide the failed test results along with the agreed-upon acceptance criteria

C.  

Show that the acceptance criteria were changed by the vendor without approval.

D.  

Document in the risk log that the issues in the system were already identified

Discussion 0
Question # 555

A project manager is defining the sprint goals with the team, A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team members.

How should the project manager handle this situation?

Options:

A.  

Request to meet with the team member and ask that any issues be escalated separately.

B.  

Reprimand the team member and provide immediate coaching on goal alignment.

C.  

Proceed with defining the goals with the team members given the majority approval from the team.

D.  

Approach the team member with empathy and obtain agreement through collaboration.

Discussion 0
Question # 556

A project manager works at an organization that is transitioning to agile The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.

What should the project manager do to ensure effective communication throughout the project?

Options:

A.  

Advise the project management office (PMO) to use the burndown chart as the single communication channel.

B.  

Develop a communications management plan for each category in the stakeholder register.

C.  

Include the burndown chart in a monthly report that is distributed to all stakeholders.

D.  

Postpone the recommendation since the organization does not currently have a defined agile methodology.

Discussion 0
Question # 557

A project manager has been assigned to a new project. There is one team member

who never says anything during meetings. After meetings, however, the team member sends

detailed emails with very good suggestions that help with project execution.

How should the project manager guide the team members?

Options:

A.  

Review the communications management plan with the team members.

B.  

Remind the team members to follow the team charter.

C.  

Motivate the team members to speak freely in the meeting.

D.  

Arrange a team-building activity to involve all team members.

Discussion 0
Question # 558

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?

Options:

A.  

Update the project management plan in order to get back on track.

B.  

Ensure the team receives continuous feedback from customers users.

C.  

Submit a change request to adjust the project scope.

D.  

Ensure the team understands all additional project requirements.

Discussion 0
Question # 559

A project manager is assigned to a project related to taxes, which will be managed

using an agile approach. By reviewing lessons learned from a previous project, the project

manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

Options:

A.  

Recognize the stakeholder's skills are important for the project and evaluate thepossibility of the stakeholder supporting the project team.

B.  

Request the functional manager to assign the team from the lessons learned project tothe current project to avoid a learning curve.

C.  

Ask the project team to review the lessons learned and have the team contact thestakeholder directly if there are any questions.

D.  

Send a request to the project sponsor to hire the stakeholder and have them becomepart of the project team.

Discussion 0
Question # 560

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

Options:

A.  

Communicate the task assignments to the team members in a clear manner.

B.  

Verify that the product owner has made the task assignments clear.

C.  

Confirm that the agile coach has made the task assignments clear.

D.  

Verify that the team members have made the task assignments clear.

Discussion 0
Question # 561

An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.

What should the project manager do?

Options:

A.  

Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.

B.  

Ask the project team to address the product owner's issues since the product owner is responsible for the scope in agile.

C.  

Ask the product owner to accept the outcome since the team delivered what was agreed in the sprint planning.

D.  

Create a record in the issue register and escalate the issue to the project steering committee.

Discussion 0
Question # 562

A key team member has recently gone through some personal issues that has affected their performance. The project manager noticed that the

team member's emotional situation has affected the rest of the team's performance.

How should the project manager handle this situation?

Options:

A.  

Help all team members learn to deal with their emotions by building a culture of empathy.

B.  

Separate the key team member and replace them while they emotionally recover.

C.  

Meet with the team to discuss how to handle the performance problem.

D.  

Ask the human resources (HR) department for their support providing emotional help.

Discussion 0
Question # 563

During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the

required IT system. What should the project manager do?

Options:

A.  

Fast track this dependency to avoid delaying the project.

B.  

Perform Integrated Change Control.

C.  

Include the dependency in the project schedule.

D.  

Ask IT to prioritize the needed system to meet the schedule.

Discussion 0
Question # 564

Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information

should the project manager provide so that senior management can get a broader view of the project?

Options:

A.  

Risk register information

B.  

Higher-level activities completed

C.  

Milestones status report

D.  

Resource breakdown structure (RBS)

Discussion 0
Question # 565

In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope.

What should the project manager do?

Options:

A.  

Organize a meeting with the team and update the work breakdown structure (WBS).

B.  

Raise this issue, and review and update the progress report for the next monthly project meeting.

C.  

Start the organization's change control process via a change request.

D.  

Communicate with an officer in the environmental protection department to check if it is necessary.

Discussion 0
Question # 566

In an agile project, the learn planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?

Options:

A.  

30/40

B.  

40/70

C.  

30/70

D.  

40/30

Discussion 0
Question # 567

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?

Options:

A.  

Ask the team to collect the knowledge locally and share it at the end of the project.

B.  

Utilize the cloud wiki to collect the necessary knowledge.

C.  

Coordinate with the team and the project stakeholders to collect the knowledge.

D.  

Provide just-in-time knowledge to the client, upon request.

Discussion 0
Question # 568

During a project's initiation phase a lessons learned sharing session was held with the team from another project Low construction productivity was discussed as a potential delay to project completion

What should the project manager do next?

Options:

A.  

Discuss this issue with the project sponsor to request additional funding to implement mitigation

B.  

Hire a construction management consultant to develop a comprehensive site execution plan

C.  

Prequalify contractors with proven track records to eliminate productivity concerns

D.  

Add construction productivity to the risk register and develop a mitigation strategy for site execution

Discussion 0
Question # 569

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle

What should the project manager do next?

Options:

A.  

Escalate the obstacle to a servant leader for resolution.

B.  

Ignore the obstacle and present the partial solution to the customer

C.  

Focus on generating business value despite the obstacle

D.  

Make changes to reprioritize the backlog because of the obstacle.

Discussion 0
Question # 570

A project manager is assigned to a project with a long timeline and complex scope. The client requires a high-level, long-term plan as well as

something that will work immediately, adding features to the product as the project progresses.

How should the project manager plan and deliver this project?

Options:

A.  

Plan the project with a predictive approach with a work breakdown structure (WBS) and then execute it using an agile approach to delivervalue incrementally.

B.  

Plan the project with a predictive approach and a work breakdown structure (WBS) following the plan and deliver value at the end of theproject.

C.  

Agree on a minimum viable product (MVP) first to be delivered immediately with the client and then release the rest of the scope at the endof the project.

D.  

Select an agile approach and manage the project according to best practices to ensure value is delivered to the client.

Discussion 0
Question # 571

A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product. What should the project manager do

next?

Options:

A.  

Request approval from the company director to conduct training for the team.

B.  

Ask the senior developer to rewrite all the stories.

C.  

Engage with the customer and rewrite all the stories.

D.  

Rewrite the stories to include the technical vision of the product.

Discussion 0
Question # 572

A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.

What should the project manager do?

Options:

A.  

Ask the project management office (PMO) to support and review all deliverables.

B.  

Log the issue in the risk register and the issue log.

C.  

Assign a technical writer to the project.

D.  

Develop a standard for document quality control.

Discussion 0
Question # 573

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change

requests issued due to the nature of the project.

What should the project manager do?

Options:

A.  

Add a fixed number of change requests allowed by the client on the project baseline.

B.  

Request sponsor approval for all change requests to reduce the number of changes.

C.  

Initiate the number of iterations to reduce the number of change requests.

D.  

Reduce the number of approvers required to implement a change request.

Discussion 0
Question # 574

A project manager notices that the project team is unlikely to complete the development of a system on time before the testing start date, which was based on the technical

complexity of the project. What should the project manager do before communicating with the client during the regular project progress meeting?

Options:

A.  

Tell the client about the chance for the potential delay.

B.  

Work with the project team to evaluate the potential delay.

C.  

Do not disclose the likelihood of a delay as it is yet to happen.

D.  

Ask the project sponsor to inform the client in the next update.

Discussion 0
Question # 575

An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing

the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and very complex to define at this stage.

What should the project manager do?

Options:

A.  

Recommend splitting the project into two smaller projects in order to work exclusively in an agile environment without interference from a predictive approach.

B.  

Propose that the well-defined scope items be delivered using a predictive approach and use an agile approach to deal with the complexitems.

C.  

Maintain stakeholder momentum in working on the scope definition until a full detailed scope is achieved prior to starting the project.

D.  

Update the risk register and escalate the issue to the project management office (PMO), requesting more resources be added to help definethe project scope.

Discussion 0
Question # 576

During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project

manager is not sure if some of the project deliverables will be fully compliant with the new requirements.

What should the project manager do?

Options:

A.  

Stop the project until someone in the organization can identify all the new requirements and how they impact the project.

B.  

Request the project management office (PMO) to assign a dedicated resource to monitor the external environment to enable more reactiontime.

C.  

Agree with the project team that the new requirements will be applied to the next project, not the one already under development.

D.  

Evaluate the consequences of noncompliance with relevant stakeholders and update the risk register with agreed actions.

Discussion 0
Question # 577

A project manager has been assigned to a project where the budget is very tight. Incurring extra costs is not an option.

What should the project manager do to manage this situation?

Options:

A.  

File a change request to make the customer billable for all extra costs incurred for the project.

B.  

Ask the accounting department to forward all project expenses to the project manager's email.

C.  

Monitor the budget for the project continually and anticipate any issues if possible.

D.  

Ask the project resources to finish their assignments in less time than originally planned.

Discussion 0
Question # 578

A project manager for a technologically complex engagement reviews the key project indicators with the main stakeholders on a regular basis. During one of the meetings,

the project sponsor explains that they are using the project manager's risk register as a way to communicate about the project at the executive level.

How should the project manager ensure that project risks are reported accurately in the risk register?

Options:

A.  

Review the risks throughout project execution.

B.  

Plan to update the risks at project closure.

C.  

Update the risks in the risk management plan.

D.  

List the project risks identified in the kick-off meeting.

Discussion 0
Question # 579

A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer.

What conclusion should the project manager come to with regard to the product owner's statement?

Options:

A.  

The product owner does not have visibility into what the team has done in the product increment.

B.  

The product owner trusts the team and is marking the product as complete.

C.  

The product owner has evaluated the product against the definition of done (DoD).

D.  

The product owner will release the product to customers without showing them a demo.

Discussion 0
Question # 580

A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist

from the team was average.

What should the project manager do to help the new compliance specialist improve?

Options:

A.  

Escalate this situation to the manager of the area for a possible solution.

B.  

Provide time for the specialist to adjust to the pace of the project.

C.  

Coordinate a one-to-one meeting with the specialist to assess the situation.

D.  

Contact the human resources (HR) manager about the team's feedback.

Discussion 0
Question # 581

A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely Some team members returned to their hometowns and they are now requesting reimbursement for operational expenditures

What should the project manager do?

Options:

A.  

Follow the Perform integrated Change Control process and submit a change request

B.  

Ask the team members to draft a justification before processing the reimbursements

C.  

Update the project management plan with the incurred costs

D.  

Review the budget and allocate funds for the reimbursements

Discussion 0
Question # 582

During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager

react to ensure the project remains successful?

Options:

A.  

Focus the discussion on recovery and ways to get back on track.

B.  

Act in a way to highlight the criticality of the situation.

C.  

Punish the team member for providing negative data that will affect the team's morale.

D.  

Thank the team member for raising this issue, log it, and move on to the next topic.

Discussion 0
Question # 583

Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to

ensure the project is delivered successfully?

Options:

A.  

Ask the vendor to communicate via the established channels.

B.  

Invite the vendor to a meeting to discuss the concerns.

C.  

Escalate the vendor's lack of responsiveness to the project sponsor.

D.  

Proceed with other tasks while awaiting a response from the vendor.

Discussion 0
Question # 584

A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.

What should the project manager have done to avoid this situation?

Options:

A.  

Ensured reports with significant information were not included in the communications management plan

B.  

Defined the appropriate recipients for the report in the communications management plan

C.  

Included noncompliance punishment measures in the communications management plan

D.  

Validated the information and the appropriate recipients per the communications management plan

Discussion 0
Question # 585

An agile project to provide a material information system has started. During the kick-off meeting, the team realizes that the stakeholders require a solution in 2 months, but it will take at least 4 months to deliver the entire project.

Who should the project manager contact to help the team accelerate the delivery?

Options:

A.  

The human resources (HR) department—to ask for more resources to add to the project team.

B.  

The product owner and the stakeholders—to prioritize the requirements in the product backlog.

C.  

The team—to have them increase their velocity to accomplish the stakeholders requirements.

D.  

The stakeholders—to have them prioritize the requirements in the product backlog.

Discussion 0
Question # 586

A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.

What should the project manager do first?

Options:

A.  

Update the definition of done (DoD) to include a review by the new team member to ensure the best outcome of each deliverable.

B.  

Ask the new team member to create a wiki that the rest of the team can reference in the future for all questions.

C.  

Ask the new team member to size all the stories in the backlog so that the rest of the team can focus on delivery.

D.  

Let the new team member know that even if they know the answer, it is better to give the team a chance to solve their own problems

Discussion 0
Question # 587

A functional manager is concerned that the project's quality management techniques have advanced beyond the department's capabilities and wants the project team to review all quality management activities in two full-day workshops the following week. What should the project manager do next?

Options:

A.  

Draft a project decision request to include in the scope for the current iteration and ask the sponsor to approve.

B.  

Explain that the team is fully dedicated to the current sprint activities and negotiate a mutually agreeable time.

C.  

Add this to the project backlog and have the product owner determine where it fits in terms of priority.

D.  

Indicate that this was a not a requirement identified during project planning and it is outside of the scope.

Discussion 0
Question # 588

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.

What should the project manager do?

Options:

A.  

Communicate the risk to the steering committee and request a mitigation plan from senior management.

B.  

Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register.

C.  

Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders.

D.  

Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.

Discussion 0
Question # 589

A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.

Which technique will best serve this purpose?

Options:

A.  

Personas

B.  

Power influence grid

C.  

Power user grid

D.  

Salience model

Discussion 0
Question # 590

At a meeting, the project manager for an agile project indicates that the sprint goals were not met. The product owner leaves the meeting early. and the team discusses how the meeting went. Team members are confused as there were no defects for the new user stories and no new requirements were discussed.

What should the project manager do in the future to avoid this situation?

Options:

A.  

Create better plans to test the functionality in more detail.

B.  

Review the definition of done (DoD) with the product owner.

C.  

Include previous sprint defects and close them in the actual sprint.

D.  

Get approval from the product owner on the user stories.

Discussion 0
Question # 591

The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team

Which two actions should the project manager take? (Choose two)

Options:

A.  

Review the issue with project sponsor and submit a change request

B.  

Report the issue to the product manager and business segments

C.  

Analyze the business benefits criteria and assumptions

D.  

Discuss the issue with the operations team to assess expense overruns

E.  

Schedule a project review meeting to analyze the root cause

Discussion 0
Question # 592

A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The

engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to

complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete

items with associated regulatory components as they are essential items.

How should the project manager prioritize the work items?

Options:

A.  

Complete tasks associated with regulatory components as the team cannot deliver business value that does not adhere to complianceregulations.

B.  

Ensure that the team assesses opportunities to deliver the highest business value items incrementally.

C.  

Ensure that the project value is within the quality guidelines by prioritizing and completing intricate tasks earlier in the project.

D.  

Complete the smaller tasks first to allow the team opportunities to prototype and evaluate development processes.

Discussion 0
Question # 593

During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?

Options:

A.  

Reevaluate the project schedule as the velocity will be impacted by the loss of resources

B.  

Reevaluate the backlog priority with the product owner since the velocity has been impacted

C.  

Reevaluate the scope of the current iteration to keep the same velocity and timeline

D.  

Reevaluate the velocity as the iteration duration will be impacted by new requirements

Discussion 0
Question # 594

A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.

Question # 594

Options:

Discussion 0
Question # 595

During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail

the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.

What should the project manager do next?

Options:

A.  

Escalate the issue to the engineer's functional manager.

B.  

Discuss the issue with the engineer and determine how to prevent another problem.

C.  

Document the task on the kanban board and make it the highest priority.

D.  

Assign another engineer to the task due to the urgency.

Discussion 0
Question # 596

An agile team wants to maximize the work delivered for the upcoming project that involves considerable product complexity. What should the

project manager do to help improve the team's collaboration approach?

Options:

A.  

Meet with the human resources (HR) department to ask for team support.

B.  

Follow the process of the most successful team in the organization.

C.  

Compare the team's velocity with other teams in the organization.

D.  

Focus on the team's engagement during the next retrospective meeting.

Discussion 0
Question # 597

A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.

What should the project manager do?

Options:

A.  

Design an updated status report.

B.  

Request a meeting with the stakeholder.

C.  

Escalate this to the project sponsor.

D.  

Forward the project status reports.

Discussion 0
Question # 598

During project planning, a development team is assigned an agreed-upon work package to determine the appropriate pattern for integrating a new service with a legacy system. The lead developer has requested a meeting with the project manager and Is looking for direction as to which technology to select.

How should the project manager help guide the lead developer?

Options:

A.  

Advise the lead developer and team to consult with the project architect and for their development team leader.

B.  

Reassign this work package to another area given the lead developer's concerns,

C.  

Direct the lead developer to conduct a weighted evaluation of all products and solutions.

D.  

Listen to the concerns and suggest that the lead developer and the team be empowered to recommend the best approach.

Discussion 0
Question # 599

A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing

adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.

What should the project manager do?

Options:

A.  

Review the adaptive tools' impact and obtain agreement from the functional manager.

B.  

Follow the functional manager's recommendation to implement only predictive tools in the project.

C.  

Make the decision on which project approach to use that would best fit the project.

D.  

Follow the project management office's (PMOs) request to implement the adaptive tools in the project.

Discussion 0
Question # 600

A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?

Options:

A.  

Monitor all stakeholders.

B.  

Keep all stakeholders informed.

C.  

Analyze the stakeholders.

D.  

Engage the stakeholders.

Discussion 0