Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMP Project Management Professional (PMBOK 7th Version) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMP Practice Questions

Project Management Professional (PMBOK 7th Version)

Last Update 17 hours ago
Total Questions : 2191

Dive into our fully updated and stable PMP practice test platform, featuring all the latest Project-Management-Professional exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free Project-Management-Professional practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMP. Use this test to pinpoint which areas you need to focus your study on.

PMP PDF

PMP PDF (Printable)
$139.65
$399

PMP Testing Engine

PMP PDF (Printable)
$157.15
$449

PMP PDF + Testing Engine

PMP PDF (Printable)
$209.65
$599
Question # 301

A project manager is leading a meeting with key stakeholders, the project sponsor and the product owner to define the features that will be released after the next iteration. The purpose of the meeting is to review the product backlog prioritization, considering that during the past iteration some deliverables were not completed.

Which two items should be taken into account first to review and update the product backlog priorities during the meeting? (Choose two)

Options:

A.  

Complexity and the cost of development

B.  

Industry trends and the technical approach

C.  

Cost of delaying some features against business value

D.  

Reusing components from another product

E.  

Length of time each feature has been on the backlog

Discussion 0
Question # 302

The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies

What should the project manager do?

Options:

A.  

Make sure the project team is aware of all agile techniques

B.  

Skip the training because the team already understands agile

C.  

Ensure the team has a common understanding of agile

D.  

Teach one agile methodology fully and completely

Discussion 0
Question # 303

A project for Company A was successfully delivered within scope schedule, and budget by the end of the last iteration However during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value.

What should the project manager have done to avoid this perception?

Options:

A.  

Involved the business stakeholders in the sprint review

B.  

Defined product backlog priorities with the sponsor and key stakeholders to deliver business benefits

C.  

Implemented a closing survey for key stakeholders

D.  

Confirmed that there is a communications management plan in place to make business stakeholders aware of the success

Discussion 0
Question # 304

A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25% The project manager updated the risk register and kept the project running as normal The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.

What should the project manager have done to avoid this?

Options:

A.  

Ensured the risk tolerance of the company was property updated

B.  

Implemented the communications management plan properly

C.  

Implemented the stakeholder engagement plan correctly.

D.  

Provided a proper risk response

Discussion 0
Question # 305

A company is changing their current business model The change requires implementing a complex project using multiple agile teams.

What three options should the project manager have the testing team adopt as testing mechanisms? (Choose three)

Options:

A.  

Independent personal testing

B.  

Security and performance testing

C.  

An experimental approach to cover all possible choices

D.  

Story testing

E.  

Tests based on behavior and test-driven development

Discussion 0
Question # 306

A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder’s behavior on the development team.

What training should the project manager choose for their team to help with this situation?

Options:

A.  

Communication training

B.  

Negotiation training

C.  

Emotional intelligence training

D.  

Agile training.

Discussion 0
Question # 307

A project manager just started managing agile projects The project manager realizes that due to the lack of a clear definition of project objectives and definition of done (DoD) their colleague's projects have had many difficulties Sponsors keep asking for more features and the projects have yet to be completed

What should the project manager do to avoid these issues?

Options:

A.  

Arrange meetings to ensure every necessary task to complete the project is included in the project management plan

B.  

Convince the project sponsor to incorporate quality experts so the product can be tested and accepted as completed.

C.  

Convince the product owner to approach the team and look for options to find a solution to the problem

D.  

Schedule meetings with key stakeholders to build the agile project charter and set clear expectations for the project

Discussion 0
Question # 308

An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach What factor should the project manager consider when determining if the project is suitable for an agile approach?

Options:

A.  

The project is an information technology project and has minimal impact to the organization

B.  

The project scope can be decomposed into smaller parts, the first representing a minimum viable product (MVP).

C.  

The project scope is well defined and the requirements are prioritized

D.  

The project team has a colocated space and is capable of working together

Discussion 0
Question # 309

A team has been working on a project for several months,, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.

How can the project manager prevent this situation from happening in the future?

Options:

A.  

Create a prioritized backlog and define iteration review sessions with stakeholders

B.  

Create a detailed work breakdown structure (WBS) and milestone schedule approved by all stakeholders

C.  

Schedule a daily meeting to review team performance and impediments

D.  

Schedule a kick-off meeting for every project phase to share the project management plan with all stakeholders

Discussion 0
Question # 310

A large project is affecting the neighborhood in which it is located The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline

What two actions should the project manager take'? (Choose two)

Options:

A.  

Send letters to the neighbors and ask them kindly not to disturb the project.

B.  

Set up a meeting with neighborhood representatives to win their cooperation

C.  

Analyze the situation and find out what is causing the neighborhood's negative attitude.

D.  

Ask the customer to extend the project deadline to allow time for conflict resolution

E.  

Ask the mayor of the city to use their authority to stop neighborhood resistance

Discussion 0
Question # 311

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?

Options:

A.  

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones

B.  

Create a reward system granting incentives to the team members who are able to catch more defects

C.  

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.

D.  

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems

Discussion 0
Question # 312

As part of the strategic plan, a company decides to implement a new software platform to manage a centralized document repository. Some requirements are clear and some need more detail.

What should the project manager do first to decide how to manage this project?

Options:

A.  

Select a predictive development life cycle based on the team's experience

B.  

Determine the most appropriate life cycle approach for the project

C.  

Register all requirements into a backlog for further detailed analysis.

D.  

Split the requirements, put them into two separate projects, and apply different approaches

Discussion 0
Question # 313

A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts

What should the project manager do next?

Options:

A.  

Raise the issues in the retrospective and propose solutions

B.  

Inform management that commitments will not be met.

C.  

Involve management to help resolve the conflicts

D.  

Coach the team both as a whole and individually

Discussion 0
Question # 314

A project manager has two projects that are being executed at the same time The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal In addition, the schedule does not have activities that can be overlapped

What should the project manager do?

Options:

A.  

Analyze both projects to determine the most effective use of common resources

B.  

Use resource optimization to justify requesting more resources for the critical project

C.  

Provide schedule optimization training to the project teams to improve their skills.

D.  

Apply fast-tracking techniques to compress the schedule of the critical project

Discussion 0
Question # 315

To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations

What should the project manager do?

Options:

A.  

Review the organizational process assessment to determine if a contingency reserve was considered in the budget estimate

B.  

Review the historical information and lessons learned from last year’s project to justify the new budget estimate

C.  

Change the budgeting technique to a more accurate, bottom-up cost estimation.

D.  

Use soft skills to convince the project sponsor to approve the new budget estimate

Discussion 0
Question # 316

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.

What should the project manager do?

Options:

A.  

Delay the project until the issue is addressed and no longer presents as a risk to the project.

B.  

Inform the sponsor that the issue has arisen and that the project's success may be uncertain

C.  

Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.

D.  

Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue

Discussion 0
Question # 317

Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track When all of the teams integrated at the product level, many integration issues were observed The overall product release progress declined with predictions showing the committed content will not be able to be accomplished

What should the project manager have done differently?

Options:

A.  

Formed a separate quality assurance team to test all items coming from each team at the end of each sprint

B.  

Performed a Scrum of Scrums on a regular basis to help the teams remove impediments

C.  

Ensured frequent and continuous integration of work to obtain early feedback and continuous learning

D.  

Arranged an online session on the integration concept and suggested tools to the teams

Discussion 0
Question # 318

A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings

What is one of the key activities that the project manager should undertake to ensure company success?

Options:

A.  

Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables

B.  

Request more funding from the project sponsor to hire additional skilled resourcesand to incorporate additional quality in the project delivery approach and outcome

C.  

Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions

D.  

Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives

Discussion 0
Question # 319

A project has a very tight delivery schedule. The project is approaching the delivery date, and the project sponsor often sends the project manager alerts to avoid any schedule slippage . The project team has performed at an acceptable level until new, but the project manager wants to ensure that team’s performance level is performance is maintained until the end.

What action should the project manager take to motivate the project team's performance?

Options:

A.  

Award certificates of appreciation to encourage the team

B.  

Inform the team about the delivery pressure from the project sponsor

C.  

Send a formal notice to team members instructing them to maintain performance

D.  

Hire a few temporary team members to help with the additional work.

Discussion 0
Question # 320

A project manager for a maintenance project has a contract that is renewed annually The project started 6 years ago After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year

What has happened in this situation?

Options:

A.  

The contract has not been appropriately reviewed by the project team

B.  

The stakeholder engagement plan has not been correctly implemented

C.  

The legal department has not disseminated the law correctly to all staff.

D.  

The project manager does not have enough knowledge on this legal matter

Discussion 0
Question # 321

An external project manager is managing the construction of new corporate offices for a large company The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component The client has rejected hiring the external resource because of the high cost even though it is within the project budget.

What should the project manager do to resolve this issue?

Options:

A.  

Hire the resource in order to achieve the project objectives.

B.  

Ask the client for a meeting and explain that the task will not be performed

C.  

Evaluate the consequences and meet with the client to explain the possible scenarios.

D.  

Try to accomplish the task internally by leveling resources from other projects

Discussion 0
Question # 322

During the course of the project several obstacles are identified that are preventing the project from moving forward. What should the project manager do to remove the obstacles?

Options:

A.  

Have the project team work on other activities

B.  

Implement plans to remove the obstacles

C.  

Escalate to the project steering committee

D.  

Prioritize the obstacles for resolution

Discussion 0
Question # 323

A transportation company is transforming its operational processes and the mam system this company uses to move freight The scope statement is in place An iterative delivery approach has been agreed by all stakeholders. What does the project manager need to do next to help the team understand the work that needs to be done?

Options:

A.  

Work with the team to decompose the scope into a WBS and work packages in order to create required deliverables and timelines.

B.  

Work directly with stakeholders on the work breakdown structure (WBS) and assign tasks with a required timeline for each team member to start the work.

C.  

Create the requirements management plan to outline how project requirements will be collected analyzed and documented and then assign requirements to team members

D.  

Start working on the project management plan with work packages, a detailed schedule, and work assignments for team members

Discussion 0
Question # 324

An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right

Question # 324

Options:

Discussion 0
Question # 325

A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program.

How should the project manager prepare for the next steps of the project?

Options:

A.  

Escalate to the management team to increase the timeline based on the complexity of the project

B.  

Wait for the other project estimates before planning the schedule

C.  

Prioritize and estimate the milestones for the high-level requirements based on historical data

D.  

Ask the project management office (PMO) to estimate the tasks for all the projects and share the project management plan

Discussion 0
Question # 326

A project manager works in a matrix organization and is managing an internal software development project that is intended to reduce conflicts in the company's internal tracking system. During development, the project manager is informed that the software has to account for an unexpected change to government accounting requirements. The development team was able to make the change with no additional cost; however, the project manager notices that the testing costs are beginning

to exceed the testing budget.

What should the project manager do?

Options:

A.  

Update the basis of estimates and the cost management plan to track the additional funding required for testing.

B.  

Ask the project sponsor to allocate funds from the contingency reserve to fund the additional testing.

C.  

Submit a change request to the cost baseline through the governance process to fund the additional testing.

D.  

Conduct a cost-benefit analysis to determine if the funds can be reallocated from the development team.

Discussion 0
Question # 327

During project implementation, one team finds out that a key project deliverable was not budgeted. What should the project manager do first?

Options:

A.  

Escalate the issue to the project sponsor for resolution.

B.  

Meet with the team to discuss alternatives.

C.  

Hold the team accountable and ask for an immediate solution.

D.  

Remove the deliverable from the project scope.

Discussion 0
Question # 328

A project manager is working on an agile project in a changing business environment. The project sponsor is worried about benefits realization

and asks the project manager to pay attention to changes that can affect the project.

Which action should the project manager take to identify changes that may affect the product?

Options:

A.  

Implement face-to-face communication between the team and product owner to change the iteration objectives as needed.

B.  

Stop the iteration as soon as possible in case an external change that makes the product invaluable is identified.

C.  

Take action to reprioritize the backlog after every iteration to evaluate if user stories are still valuable to the business.

D.  

Apply a pair programming technique to react to changes immediately, even in the middle of the interaction.

Discussion 0
Question # 329

After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are

being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting

market requirements.

What should the project manager do?

Options:

A.  

Continue the iteration and add the requested changes.

B.  

Continue the iteration and review the change with the customer.

C.  

Cancel the iteration and meet with the product owner.

D.  

Cancel the iteration and add the requested changes.

Discussion 0
Question # 330

In the initiating phase of a project, the project manager and team members are prioritizing the product backlog along with the product owner. What should the project

manager do next?

Options:

A.  

Produce a value-added product for the customer as continuously as possible.

B.  

Produce a value-added product for the customer in the beginning of the project.

C.  

Produce a value-added product along with the supporting documentation.

D.  

Produce a value-added product for the customer in each phase of the project.

Discussion 0
Question # 331

After meeting with stakeholders, a project manager working at a computer gaming company is creating a project management plan for the company's newest offering. The project manager learns that the company's main competitor is scheduled to release a similar offering leveraging the newest technology. The project manager fears that the competitor's offering is better in multiple ways compared to the project manager's project.

What should the project manager do?

Options:

A.  

Perform a Kano analysis factoring in the competitor's offering and present it to the stakeholders.

B.  

Meet with the development team to see what changes will improve the project compared to the competition's deliverable.

C.  

Meet with the project team to discuss the concerns and determine how to ensure the project's deliverable can compete with the competitor's.

D.  

Note this concern in the risk register and meet with the sales team to identify mitigation options factoring in the competitor's offerings.

Discussion 0
Question # 332

A large matrix organization is adopting a new communications approach. This is necessary because their projects often require the resourcing of expert knowledge in the form of specialists from various departments and divisions.

What should the project manager do to set up effective communications?

Options:

A.  

Plan on transmitting the information in an easily understandable manner.

B.  

Focus on the recipients’ needs and not the information itself.

C.  

Use the highest possible technical language and avoid using metaphors.

D.  

Ensure that messages sent to the recipients are delivered.

Discussion 0
Question # 333

A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the different requirements?

Options:

A.  

Include only the common requirements of each stakeholder group in the project goals.

B.  

Include only the key requirements and keep the stakeholders informed about scope decisions.

C.  

Analyze the interests and influence of stakeholders and evaluate their requirements.

D.  

Add only the opinions of the team, because they know the objectives of the project.

Discussion 0
Question # 334

There are two interdependent projects: the first project is in execution, and the second one is about to be deployed. The first project has been delayed, which is now affecting the second project due to the sharing of resources.

What should the project manager do in this situation?

Options:

A.  

Ask for written commitment from the team manager assuring the deployment team can work on only one of the projects.

B.  

Ask the procurement team to solicit offers from external providers in order to replace the internal resources for the deployment.

C.  

Assess the issue with the deployment resources' availability and define a plan to deploy extra resources to the deployment team.

D.  

Organize a meeting with the deployment team and explain that, due to a resource shortage, the project will be delayed.

Discussion 0
Question # 335

A company is launching a new product that has to be ready before the summer season begins. After the discovery process, the team realizes that the requirements are very uncertain.

What should the project manager do?

Options:

A.  

Invite stakeholders to discuss project requirements prioritization.

B.  

Register a risk and define a contingency plan to finish the project on time.

C.  

Ask to include some business subject matter experts (SMEs) in the team.

D.  

Assist the team in proposing a minimum viable product (MVP).

Discussion 0
Question # 336

In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?

Options:

A.  

Reach an agreement with the team on how to handle the situation.

B.  

Reach out to the procurement team to hire a substitute for the team member.

C.  

Allow senior management to decide how to proceed with the project.

D.  

Convince the team member not to leave until the project is completed.

Discussion 0
Question # 337

A large multi-national company works on a project in an emerging-economy country. All business matters are conducted in local currency. During the course of the project,

the budget becomes the primary concern due to currency instability in the country.

What should the project manager do next?

Options:

A.  

Evaluate the situation with the team

B.  

Escalate the risk to the project sponsor

C.  

Use the project's contingency reserve

D.  

Ask for additional budget from the client

Discussion 0
Question # 338

A project manager is leading a product feature rollout that will gain more subscribers for a video-streaming application. During the backlog grooming phase, the business stakeholders were unable to understand the feature integration with the product and raised concerns.

What can the project manager do to demonstrate the feature integration?

Options:

A.  

Involve business stakeholders in the iteration retrospective.

B.  

Include the business stakeholders in the iteration review.

C.  

Review the backlog in detail with the business stakeholders.

D.  

Create a task for the iteration review and add it to the backlog.

Discussion 0
Question # 339

A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application.

Which estimation technique should the project manager recommend?

Options:

A.  

Planning poker

B.  

Parametric estimating

C.  

Three-point estimating

D.  

Analogous estimating

Discussion 0
Question # 340

A steering committee member is complaining about the weekly report. They stated that the report is too long and has unnecessary details. As a result, they are unable to obtain the main message and take action.

What should the project manager do to avoid similar complaints?

Options:

A.  

Present the status at a weekly meeting with the steering committee.

B.  

Verify the information needed for steering committee members.

C.  

Send a shorter daily report to this steering committee member.

D.  

Demonstrate the weekly reports in a presentation for the steering committee member.

Discussion 0
Question # 341

A multinational company is rolling out a new software platform within its subsidiaries. However, the distributed project team struggles to meet regularly. As a result, the project milestones are not being achieved.

What should the project manager do first?

Options:

A.  

Inform the project sponsor and request additional team members to crash the project schedule to meet the target

B.  

Introduce an award system to promote member participation and establish some competition between the subteams

C.  

Evaluate the effectiveness of the virtual teams and support them with the necessary technology and equipment

D.  

Propose to roll out the new software in one subsidiary and then use the lessons learned to improve the project

Discussion 0
Question # 342

By the end of the first sprint, a project lead notices that one of the team members is not performing very well. Which form of communication should the project lead use to handle the situation?

Options:

A.  

Informal written communication, such as a friendly reminder

B.  

Formal written communication, such as an email with a copy sent to the manager

C.  

Informal verbal communication, such as a conversation

D.  

Formal verbal communication, such as a conversation at the end of the sprint retrospective

Discussion 0
Question # 343

A project manager starts to receive emails from different stakeholders requesting information about the project status. What should the project

manager do to avoid this in the future?

Options:

A.  

Schedule weekly project status meetings with all stakeholders including the customer and internal resources.

B.  

Include the project stakeholders’ needs while planning the project communications strategy.

C.  

Designate a team member to respond to the emails from these stakeholders.

D.  

Include the stakeholders’ emails in all of the project status communications.

Discussion 0
Question # 344

A team is focusing on quickly developing and shipping new product features due to very aggressive market demands. The team is setting aside long-term work not directly related to the current business objective, which affects product performance and generates more customer support requests.

How can the team minimize the impact of the reduced focus on quality?

Options:

A.  

Adapt the management plan to reduce the quality constraints.

B.  

Reduce complexity to focus on the minimum viable product (MVP).

C.  

Consider implementing test-driven methodology.

D.  

Work on the technical debt at a later stage in the project.

Discussion 0
Question # 345

A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.

What should the project manager do next?

Options:

A.  

Suggest that the team member contact the IT department.

B.  

Facilitate a priority resolution of the issue with the IT department.

C.  

Update the issue log and escalate the problem to the product owner.

D.  

Ask the other team members to step in and do the work.

Discussion 0
Question # 346

A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause

analysis (RCA) shows that a component added as part of the latest change request was not tested throughout the development cycle.

What should the project manager do next?

Options:

A.  

Review the change control process to ensure quality management artifacts are updated as part of the change.

B.  

Review the quality management process and perform a process audit as part of ongoing quality assurance.

C.  

Review the communications management plan to ensure change requests are communicated to the affected team members.

D.  

Review the quality management process with the project management office (PMO) to ensure compliance with best practices.

Discussion 0
Question # 347

A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is

identified regarding an indirect tax regulation that is being changed by the government in the next 6 months. This risk will have a significant impact

on the project outcomes.

What should the project manager do next?

Options:

A.  

Determine the impact of the risk and prioritize outcomes that do not affect the tax module.

B.  

Delay developing the indirect tax module until the tax regulation comes into effect.

C.  

Assess the impact of the risk with an expert and prioritize further outcomes with the client.

D.  

Analyze the impact of the risk and discuss with the team to determine how to separate the tax module.

Discussion 0
Question # 348

The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path.

What should the project manager do in this situation?

Options:

A.  

Escalate the supplier-related issues to the sponsor for resolution.

B.  

Review the work breakdown structure (WBS) with the suppliers.

C.  

Review the critical path with the stakeholders to define next steps.

D.  

Discuss the critical path issues with the purchasing department.

Discussion 0
Question # 349

Drag the items on left side to the matching term within the correct project approach on the right side.

Question # 349

Options:

Discussion 0
Question # 350

A project manager is working on an agile project that is within the scope of a recently announced corporate audit. The project manager was

appointed to attend the first meeting with the auditors scheduled for the following week.

What should the project manager do to prepare for the audit?

Options:

A.  

Reserve story points for the next iteration if needed.

B.  

Review the project information.

C.  

Ask the development team to provide compliance information.

D.  

Ask for a waiver during the audit.

Discussion 0
Get PMP dumps and pass your exam in 24 hours!

Free Exams Sample Questions