SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7
Last Update 4 days ago
Total Questions : 165
C_TPLM22_67 is stable now with all latest exam questions are added 4 days ago. Just download our Full package and start your journey with SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 certification. All these SAP C_TPLM22_67 practice exam questions are real and verified by our Experts in the related industry fields.
What is the starting point for milestone billing?
Please choose the correct answer.
Response:
Which function allows you to check consistency of the dates within the project structure with or without taking activities into account?
Please choose the correct answer.
Response:
When the system derives settlement rules, it generates profitability segments that contain the characteristic values of which of the following assigned to them?
There are 2 correct answers to this question.
Response:
A customer wants to maintain basic data and dates of a WBS element on the same tab. Also, basic start and basic finish should be mandatory fields. What do you recommend?
There are 2 correct answers to this question.
Response:
You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined.
What are the possible reasons for this?
There are 2 correct answers to this question.
Response:
What are the different procurement types you can choose between if you choose direct procurement with item category N?
There are 2 correct answers to this question.
Response:
When you create service activity in your network, what data can be entered? (3)
In which transactions can you specify whether networks are scheduled together with maintenance orders that have been assigned as sub networks?
There are 2 correct answers to this question.
Response:
What do you call a closed sequence of relationships and activities where you start from an activity and end up back at the same activity, by way of relationships?
Please choose the correct answer.
Response:
In addition to manual planning in the WBS, you sometimes assign different types of orders (internal orders or maintenance orders, for example) to the WBS element that are flagged as account assignment elements. What is the use of this assignment?
There are 3 correct answers to this question.
Response:
Which indicator automates the grouping of project stock assigned to individual WBS elements to the top WBS element?
Please choose the correct answer.
Response:
How are various stock types managed for each material component?
Please choose the correct answer.
Response:
Which of the following information regarding cost activity is not relevant for the calculation of planned costs?
Please choose the correct answer.
Response:
What are the two basic elements that SAP Project system provides for mapping the structures of projects?
There are 2 correct answers to this question.
Response:
Which version serves as a proof of the project status in the past and also serves as a comparison with the operative project?
Please choose the correct answer.
Response:
Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning?
Please choose the correct answer.
Response:
Externally processed activities give rise to planned costs that are equivalent to the prices of the following?
There are 2 correct answers to this question.
Response:
In which of the following is the Capacity planning Indicator set?
Please choose the correct answer.
Response:
You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?
Please choose the correct answer.
Response:
You are using the billing and down payment processing in Sales and Distribution and updating the actual data to billing elements in the project system.
Which of the following business processes can be mapped in Sales and Distribution?
There are 3 correct answers to this question.
Response:
Which type of billing is generally used in plant engineering and construction projects?
Please choose the correct answer.
Response:
Most of the reports in the SAP Project System can be refreshed without exiting or closing the report. Which report must be restarted to update the displayed data?
Please choose the correct the answer.
Response:
In which type of billing the total value to be billed is apportioned to individual dates in the billing plan according to defined rules?
Please choose the correct answer.
Response:
Consider a scenario where you have started by displaying the planned costs for the entire project and how these planned costs are distributed among the various value categories for WBS element WBS 2.
You then want to analyze the planned costs of WBS element WBS 2 for value category 620 according to cost distribution to the various periods.
Which type of reporting allows you to achieve this?
Please choose the correct answer.
Response:
TESTED 28 Apr 2024
Hi this is Romona Kearns from Holland and I would like to tell you that I passed my exam with the use of exams4sure dumps. I got same questions in my exam that I prepared from your test engine software. I will recommend your site to all my friends for sure.
Our all material is important and it will be handy for you. If you have short time for exam so, we are sure with the use of it you will pass it easily with good marks. If you will not pass so, you could feel free to claim your refund. We will give 100% money back guarantee if our customers will not satisfy with our products.