Weekend Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 2493360325

Good News !!! PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam is now Stable and With Pass Result

PMI-RMP Practice Exam Questions and Answers

PMI Risk Management Professional (PMI-RMP) Exam

Last Update 4 days ago
Total Questions : 131

PMI Risk Management Professional (PMI-RMP) Exam is stable now with all latest exam questions are added 4 days ago. Incorporating PMI-RMP practice exam questions into your study plan is more than just a preparation strategy.

By familiarizing yourself with the PMI Risk Management Professional (PMI-RMP) Exam exam format, identifying knowledge gaps, applying theoretical knowledge in PMI practical scenarios, you are setting yourself up for success. PMI-RMP exam dumps provide a realistic preview, helping you to adapt your preparation strategy accordingly.

PMI-RMP exam questions often include scenarios and problem-solving exercises that mirror real-world challenges. Working through PMI-RMP dumps allows you to practice pacing yourself, ensuring that you can complete all PMI Risk Management Professional (PMI-RMP) Exam exam questions within the allotted time frame without sacrificing accuracy.

PMI-RMP PDF

PMI-RMP PDF (Printable)
$48
$119.99

PMI-RMP Testing Engine

PMI-RMP PDF (Printable)
$56
$139.99

PMI-RMP PDF + Testing Engine

PMI-RMP PDF (Printable)
$70.8
$176.99
Question # 1

A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.

What three artifacts should the project manager consult or review during this process? (Choose three.)

Options:

A.  

Project contracts

B.  

Lessons learned registers from analogous projects

C.  

Risk register

D.  

Risk management plan

E.  

Code of regulations

Discussion 0
Question # 2

When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.

How does centralizing the risk management function help resolve the problem?

Options:

A.  

Enhance the process of identification of different Individual project risks.

B.  

Allows monitoring the impact against the overall project risk exposure.

C.  

Establishes risk sources and ownership for trigger monitoring.

D.  

Creates a single repository for all project risk documents.

Discussion 0
Question # 3

Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?

Options:

A.  

Reduce the probabilities of those risks on the risk register

B.  

Transfer ownership of those risks to the customer

C.  

Implement the risk handling strategies for those risks

D.  

Request additional management reserve for those risks

Discussion 0
Question # 4

A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.

Which risk identification technique should the risk manager use?

Options:

A.  

Prompt lists

B.  

Interviews

C.  

Delphi technique

D.  

Nominal group technique

Discussion 0
Question # 5

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.

How should the risk manager interpret such a low CPI value?

Options:

A.  

The cost control processes is ineffective.

B.  

The cost baseline is inaccurate.

C.  

The actual reported costs are inaccurate.

D.  

The cost related risks are effectively managed.

Discussion 0
Question # 6

A company in the mining industry accommodates a lot of innovation and changing work conditions. Because of this, the company experiences difficulty in predicting long term business plans.

How should a professional risk manager manage the risks in such situations?

Options:

A.  

Adopt a predictive approach to manage the risks.

B.  

Adopt agile approaches to manage the risks.

C.  

Utilize proper documentation to help manage the risks.

D.  

Conduct weekly risk management meetings with all stakeholders.

Discussion 0
Question # 7

A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.

What should the project manager do?

Options:

A.  

Avoid the risk

B.  

Transfer the risk

C.  

Ignore the risk

D.  

Accept the risk

Discussion 0
Question # 8

During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?

Options:

A.  

Contact the risk managers of the other projects and inform them

B.  

Include an escalation process in the risk management plan

C.  

Take note of the extensive impact of these risks in the risk register

D.  

Address the unique characteristics of these risks on a case-by-case basis

Discussion 0
Question # 9

The project manager asks the risk manager to determine the initial risk assessment for a six month initiative that is about to kick-off. Which two artifacts will help the risk manager conduct the related analysis? (Choose two.)

Options:

A.  

Work breakdown structure (W&S)

B.  

Project organizational chart

C.  

Configuration management plan

D.  

Brainstorming

E.  

Monte Carlo analysis

Discussion 0
Question # 10

A project manager wants to introduce a new technology to improve a project's performance. However, there are some costs associated that are beyond the current budget, and the proposed technology has not been applied to any previous company projects.

What should the project manager do in this situation?

Options:

A.  

Escalate this initiative to project decision makers and sponsors.

B.  

Accept the fact that there is a risk associated with this new technology.

C.  

Take advantage of this opportunity of Improving the project performance.

D.  

Outsource the implementation of the new technology as soon as possible.

Discussion 0
Question # 11

An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?

Options:

A.  

Ensure sufficient resources are available

B.  

Revise the risk management plan

C.  

Update the risk register

D.  

Meet with the project's stakeholders

Discussion 0
Question # 12

A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.

What should the project manager have done differently?

Options:

A.  

Executed the risk strategy response and recorded it in the risk register.

B.  

Performed an analysis to affirm the request is valid before submitting.

C.  

Informed the client and the project sponsor that the request is being submitted.

D.  

Contacted the other stakeholders so they know the request is in process.

Discussion 0
Question # 13

Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

Options:

A.  

When the forecast activity date has been met or exceeded

B.  

When the stakeholders agree a risk is no longer applicable

C.  

When the risk has been realized and can no longer happen again

D.  

When iterative data analysis determines the risk is not applicable

Discussion 0
Question # 14

At an oil and gas company, a major unified management information system is to be implemented. The project manager noted that risks gathered from the organization's business functions are not properly identified and categorized, making it difficult to develop an effective risk response.

How should the project manager handle this situation?

Options:

A.  

Outsource conducting the risk response plan to risk consultants.

B.  

Ask functional managers to improve their risk register and process.

C.  

Adjust the risk response plans to effectively handle the identified risks.

D.  

Coach the functional groups on how to properly conduct the process.

Discussion 0
Question # 15

During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.

What action should the project manager take?

Options:

A.  

Reassess the design for the two pieces.

B.  

Escalate the situation and request approval to move forward.

C.  

Confirm the results through a second pilot.

D.  

Update the assumptions log and assess the risk associated with it.

Discussion 0
Question # 16

A project manager running a high risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The project manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project related tasks appear.

What should the project manager do next regarding the new risks?

Options:

A.  

Apply a risk acceptance strategy to the new risks as there is no risk response plan.

B.  

Update the risk management plan with the new probability/impact and change the response.

C.  

Escalate the new risks immediately to the project stakeholders to ensure proper risk communication is in place.

D.  

Address these secondary risks as per the risk management plan.

Discussion 0
Question # 17

After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.

What should the risk manager do to facilitate the sponsor's ask?

Options:

A.  

Monte Carlo analysis

B.  

Qualitative risk analysis

C.  

Sensitivity analysis

D.  

Quantitative risk analysis

Discussion 0
Get PMI-RMP dumps and pass your exam in 24 hours!

Free Exams Sample Questions