Labour Day Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 2493360325

Good News !!! PMI-SP PMI Scheduling Professional is now Stable and With Pass Result

PMI-SP Practice Exam Questions and Answers

PMI Scheduling Professional

Last Update 5 days ago
Total Questions : 323

PMI-SP is stable now with all latest exam questions are added 5 days ago. Just download our Full package and start your journey with PMI Scheduling Professional certification. All these PMI PMI-SP practice exam questions are real and verified by our Experts in the related industry fields.

PMI-SP PDF

PMI-SP PDF (Printable)
$48
$119.99

PMI-SP Testing Engine

PMI-SP PDF (Printable)
$56
$139.99

PMI-SP PDF + Testing Engine

PMI-SP PDF (Printable)
$70.8
$176.99
Question # 1

You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?

Options:

A.  

Push technique

B.  

Many-to-many

C.  

One-to-one

D.  

Pull technique

Discussion 0
Question # 2

Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.

Options:

A.  

Quality inspections and compliance

B.  

Location, logistics, and resource availability analysis

C.  

Labor productivity studies from previous similar projects in the area

D.  

The average price of general labor in the area

Discussion 0
Question # 3

Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy's project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

Options:

A.  

-$75,000

B.  

-$42,000

C.  

-$45,000

D.  

-$65,000

Discussion 0
Question # 4

Which one of the following estimate types is a form of expert judgment?

Options:

A.  

Parametric estimate

B.  

Analogous estimate

C.  

Bottom-up estimate

D.  

Definitive estimate

Discussion 0
Question # 5

Harry works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, he has spent $725,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. What is the estimate at completion for this project that Harry will need to report to management?

Options:

A.  

$1,312,504

B.  

$787,504

C.  

$1,812,498

D.  

$725,000

Discussion 0
Question # 6

Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?

Options:

A.  

Perform resource leveling for the project.

B.  

Crash the project schedule.

C.  

Fast track the project.

D.  

Remove things from the project scope.

Discussion 0
Question # 7

You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the difference between total float and free float. What is the difference between total float and free float?

Options:

A.  

Total float is the amount of time an activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.

B.  

Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project successors.

C.  

Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project predecessors.

D.  

Total float is the amount of time a non-critical activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.

Discussion 0
Question # 8

You are the project manager of the GHY Project. Management wants you to create a process improvement plan for your project. Your project will be studied by management and will become a standard for all future organizational projects based on your project's performance, approach, and implementation of project processes. All of the following should be included in your project's process improvement plan except for which one?

Options:

A.  

Process boundaries

B.  

Process configuration

C.  

Targets for improved performance

D.  

Identification of project risks

Discussion 0
Question # 9

What is the term assigned to graphic in the figure given below?

Question # 9

Options:

A.  

Communications bull's eye

B.  

Performance goals

C.  

Earned value management goals

D.  

Project exception report

Discussion 0
Question # 10

Lily works as a project manager for BlueWell Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95. What time will she record for this activity?

Options:

A.  

48

B.  

55

C.  

54

D.  

40

Discussion 0
Question # 11

Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?

Options:

A.  

It is a term used to describe activities whose effort cannot be directly measured to the project objectives.

B.  

It is a term used to describe activities whose effort can be directly measured and linked to the project objectives.

C.  

It is a term used to describe activities that are supportive of the project work, but not linked to the project deliverables.

D.  

It is a term used to describe activities that are core project management processes, but not core project activities.

Discussion 0
Question # 12

Holly is the project manager of her project. She has chosen to crash the project due to time constraints that have been imposed on her project. When Holly crashes the project what project document must be updated to reflect this change to the approach?

Options:

A.  

Develop schedule process

B.  

Risk register

C.  

Project risk management plan

D.  

Activity attributes

Discussion 0
Question # 13

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

Options:

A.  

-$135,000

B.  

.67

C.  

.81

D.  

-$65,000

Discussion 0
Question # 14

Laura is the project manager for her organization and management has requested her to create a report on her project's performance. Laura needs to analyze her current project performance and then compare it against what, in order to create a performance report?

Options:

A.  

Cost variances and Cost Performance Index

B.  

Scope baseline

C.  

Performance measurement baseline

D.  

Schedule variances, planned value, and the Schedule Performance Index

Discussion 0
Question # 15

Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.

Options:

A.  

Quality inspections and compliance

B.  

Location, logistics, and resource availability analysis

C.  

Labor productivity studies from previous similar projects in the area

D.  

The average price of general labor in the area

Discussion 0
Question # 16

Which of the group creativity techniques enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or prioritization?

Options:

A.  

Idea/mind mapping

B.  

Delphi technique

C.  

Nominal group technique

D.  

Affinity diagram

Discussion 0
Question # 17

Which organizational theory explains the factors that promote performance of people in any organization?

Options:

A.  

Herzberg's theory

B.  

Maslow's Hierarchy theory

C.  

McGregor's theory

D.  

Expectancy theory

Discussion 0
Question # 18

You are the project manager of the JKM Project for your organization. Your project is supposed to be 60 percent complete but you are only 45 percent complete. The project has an assigned budget of $765,000 but you have already spent $365,000 to reach this point in the project due to some errors and rework. Management is pressing you on when you'll complete the project and how much the project will likely cost based on the current performance. You need to tell management what the project's current cost performance index (CPI) is. What value should you report to management based on your project's performance?

Options:

A.  

$306,000

B.  

.94

C.  

$344,250

D.  

.75

Discussion 0
Question # 19

The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?

Question # 19

Options:

A.  

Static

B.  

Deterrent

C.  

Noise

D.  

Barrier

Discussion 0
Question # 20

A construction company is about to start a new project. It requires hiring a project manager for this project. Which of the following are the most important skills that a person must have to be selected as a project manager?

Options:

A.  

Problem solving

B.  

Team building and human resources

C.  

Leading

D.  

Communication

E.  

Negotiation and influential

Discussion 0
Question # 21

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?

Options:

A.  

$142,000

B.  

$232,000

C.  

$41,750

D.  

$23,750

Discussion 0
Question # 22

Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response?

Options:

A.  

Diane

B.  

Project sponsor

C.  

Risk owner

D.  

Subject matter expert

Discussion 0
Question # 23

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget-to-date. What is your schedule performance index for this project?

Options:

A.  

80

B.  

1.02

C.  

102

D.  

0.80

Discussion 0
Question # 24

Examine the figure given below: Which path is considered the critical path?

Options:

A.  

ACDFJ

B.  

ACGIJ

C.  

ABEFJ

D.  

ABDFJ

Discussion 0
Question # 25

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

Options:

A.  

Project change control process

B.  

Perform integrated change control process

C.  

Configuration management

D.  

Communications management

Discussion 0
Question # 26

You are the project manager of the NDF project. You need to determine how often a complete project report can be made, including forecasted project completion information for your project. How often should the report be created?

Options:

A.  

Weekly

B.  

One per status milestone reached

C.  

Regularly or on an exception basis

D.  

Exception-by-exception basis

Discussion 0
Question # 27

Wendy is the project manager for the NHQ project. She is working with her project to begin creating the project duration estimate. Her organization is in weak matrix and several of the project team members are scheduled to complete work on other projects. What input will most likely be of the biggest assistance as Wendy and the project team begin creating the duration estimate for this project?

Options:

A.  

Project charter

B.  

Project scope statement

C.  

Project communications management plan

D.  

Resource calendar

Discussion 0
Question # 28

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone, which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's planned value?

Options:

A.  

$2,025,000

B.  

There is not enough information to know

C.  

$4,500,000

D.  

$2,250,000

Discussion 0
Question # 29

You are the project manager for your organization. Your current project has a schedule variance of -$37,500 and a schedule performance index of 0.94. What do these values mean in regard to project performance?

Options:

A.  

Your project is likely to be late and over budget.

B.  

Your project is performing well.

C.  

Your project has a planned value of $600,000.

D.  

Your project is six percent off schedule and has a considerable schedule variance.

Discussion 0
Question # 30

Which of the following is an output of the Develop Project Charter process?

Options:

A.  

Enterprise environmental factors

B.  

Contract

C.  

Business case

D.  

Project charter

Discussion 0
Question # 31

You are the project manager for your organization. You are working with your project team to develop the project schedule. You would like to automate much of the scheduling by using Microsoft project. Microsoft project as a scheduling tool is an example of what tool and technique for the Develop Schedule Process?

Options:

A.  

Organizational process asset

B.  

Scheduling tool

C.  

Project Management Information System

D.  

Project office software

Discussion 0
Question # 32

Which of the following characteristics of conflict and the conflict management process should be recognized by the project managers while handling conflict in a team environment? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.  

Conflict resolution should focus on issues, not personalities.

B.  

Conflict is natural and forces a search for alternatives.

C.  

Openness resolves conflict.

D.  

Conflict is an individual issue.

Discussion 0
Question # 33

Alicia works as a project manager for NacTec project. She is undergoing the project monitoring phase in her project. Which of the following will she choose to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.  

Reports

B.  

Meetings

C.  

Diaries

D.  

Future planning

Discussion 0
Question # 34

In which of the following process groups does Integration Change Control Process fall?

Options:

A.  

Execution

B.  

Initiating

C.  

Planning

D.  

Monitoring and Controlling

Discussion 0
Question # 35

You are the project manager for your organization. You have worked with the project team to create the project scope statement. The key stakeholders have signed off on the project scope and they are eager for you and the project team to begin creating the deliverables identified within the project scope. What process must you and the project team complete next in this scenario?

Options:

A.  

Create the activity list.

B.  

Create the WBS.

C.  

Create the risk assessment.

D.  

Determine the project budget.

Discussion 0
Question # 36

You're a project manager and you've completed your project schedule. The schedule will take 18 months to complete the project work. Throughout the schedule there are instances that the project work will require the project team members to work more than fifty hours per week. If you must adhere to a maximum of 45 hours of project work per team member, per week, what will likely happen to your project schedule as it stands right now?

Options:

A.  

Nothing, the 45 hours limit is a guideline.

B.  

The project will take longer to complete.

C.  

The project will take less time to complete.

D.  

The project will require more resources.

Discussion 0
Question # 37

Gary is the project manager for his organization. The projects that Gary manages for project customers are often very similar in nature so Gary uses a schedule network template to help plan the project work. For Gary's current project, he has used a network template that includes just a portion of the project work adapted to the current project. When Gary uses a portion of a network template diagram this is called what term?

Options:

A.  

Analogous

B.  

Hanger

C.  

Fragment network

D.  

Parametric

Discussion 0
Question # 38

Tom is the project manager for the ABC Construction Company. As part of the project scheduling for the construction of a new office building, he has allotted time for the inspectors of the building structure, as well as electrical, plumbing, and safety into the project's schedule. These inspectors can be considered what type of dependency in the project?

Options:

A.  

Mandatory dependencies

B.  

Required dependencies

C.  

Discretionary dependencies

D.  

External dependencies

Discussion 0
Question # 39

There are seven inputs to the estimate activity durations process. Which one of the following is NOT an input to this process?

Options:

A.  

Scope baseline

B.  

Activity attributes

C.  

Activity list

D.  

Activity resource requirements

Discussion 0
Question # 40

You work as a project manager for BlueWell Inc. You must communicate on a regular basis with all of your project stakeholders. In your project, you have 755 stakeholders. How many communication channels exist in the project?

Options:

A.  

284,635

B.  

570,025

C.  

569,270

D.  

755

Discussion 0
Question # 41

Frank is the project manager in BlueWell Inc. He is working with his project to subdivide the project work packages into smaller, more manageable components. He and the project team are planning in detail all of the things the team will need to create, purchase, or do in order to satisfy the project scope. Management is concerned with the activity which Frank is using in this scenario, as they believe that Frank is taking too long to complete this pre-execution activity. Which of the following techniques of the activity process is Frank using in this example?

Options:

A.  

Rolling wave planning

B.  

Expert judgment

C.  

Creating a project template

D.  

Decomposition

Discussion 0
Question # 42

You are the project manager for your organization. You have recently noted some risks associated with some of the activities in your project. These risks can have schedule and costs impacts on your project and you need to address the risks through qualitative and quantitative analysis to confirm the depth of possible impact. Where should you document the risk information concerning the activities in your project schedule?

Options:

A.  

Risk management plan

B.  

Schedule management plan

C.  

Risk register

D.  

Activity attributes

Discussion 0
Question # 43

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

Options:

A.  

Project change control process

B.  

Perform integrated change control process

C.  

Configuration management

D.  

Communications management

Discussion 0
Question # 44

You work as a Project Manager for Media Perfect Inc. Several projects are running under your supervision. Rick, team leader of a project, provides you performance indexes of his project. The schedule variance (SV) of his project is 25. What does this figure depict?

Options:

A.  

Project is behind the schedule.

B.  

Costs are higher than planned.

C.  

Project is right on target.

D.  

Project is ahead of the schedule.

Discussion 0
Question # 45

You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?

Options:

A.  

Decomposition

B.  

Rolling wave plan

C.  

Precedence diagramming method

D.  

Templates

Discussion 0
Question # 46

Steve is the project manager for the POK Project. He is working with the project customers to determine how frequently they'd like to receive the project information. The customers would like weekly status reports on how the project is performing. Where should Steve document this information?

Options:

A.  

Communications management plan

B.  

Issues log

C.  

Project schedule

D.  

Schedule management plan

Discussion 0
Question # 47

You work as a project manager for BlueWell Inc. Which of the following techniques will you use to determine whether particular work can best be accomplished by the project team or must be purchased from the outside sources?

Options:

A.  

Contract Types

B.  

Expert Judgment

C.  

Procurement Negotiations

D.  

Make-or-Buy Analysis

Discussion 0
Question # 48

Terri is the project manager for her organization and she is working with her project team to develop the project schedule. She has identified the float in her project although some of the activities where float exists may be susceptible to risk in the project execution. She is also concerned that the critical path may change during the project if the risk events come into execution. What scheduling method is Terri using in this example?

Options:

A.  

Critical chain method

B.  

Risk analysis method

C.  

Activity on the arrow method

D.  

Critical path method

Discussion 0
Get PMI-SP dumps and pass your exam in 24 hours!

Free Exams Sample Questions