By familiarizing yourself with the PRINCE2-Foundation written Exam exam format, identifying knowledge gaps, applying theoretical knowledge in PRINCE2 practical scenarios, you are setting yourself up for success. Prince2-Foundation exam dumps provide a realistic preview, helping you to adapt your preparation strategy accordingly.
Prince2-Foundation exam questions often include scenarios and problem-solving exercises that mirror real-world challenges. Working through Prince2-Foundation dumps allows you to practice pacing yourself, ensuring that you can complete all PRINCE2-Foundation written Exam exam questions within the allotted time frame without sacrificing accuracy.
When should the Project Board refer to corporate or programme management for a decision?
Which does NOT reflect the PRINCE2 principle of continued business justification?
Which process is triggered towards the end of the final stage when all the assigned work has been completed?
What is the collective name for individuals or groups who may be affected by a project?
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
Which of the following statements about stakeholders are true?
1. Someone who thinks they will be affected by a project is a stakeholder on that project.
2. Stakeholders may be internal or external to the corporate organization.
Which plan provides the Business Case with costs during the Initiating a Project process?
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
Which does the Executive need to ensure is in place before the project is initiated?
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
Identify the missing words in the following sentence.
PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
What does the communication management approach define?
1. How versions of products will be described on information sent to interested parties
2. How information should be sent to interested parties
3. How often information should be sent to interested parties
4. How the PRINCE2 roles will be combined during the project
According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?
Which statement describes the 'Implement' step within the recommended risk management procedure?
What should be recorded in a quality register?
1. Activities to ensure the products are fit for purpose
2. Identified threats and opportunities
3. Problems and concerns to be managed informally
4. Roles responsible for reviewing the project's products
Identify the missing words in the following sentence.
The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.
Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.
Which control must be used as a minimum requirement for applying the 'progress' theme?
How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?
During the ‘initiating a project’ process, who specifies the required level of management control?
TESTED 04 May 2024
Hi this is Romona Kearns from Holland and I would like to tell you that I passed my exam with the use of exams4sure dumps. I got same questions in my exam that I prepared from your test engine software. I will recommend your site to all my friends for sure.
Our all material is important and it will be handy for you. If you have short time for exam so, we are sure with the use of it you will pass it easily with good marks. If you will not pass so, you could feel free to claim your refund. We will give 100% money back guarantee if our customers will not satisfy with our products.