Prince2-Practitioner Practice Questions

PRINCE2 7 Practitioner (7th Edition) Exam

Last Update 3 days ago
Total Questions : 263

Dive into our fully updated and stable Prince2-Practitioner practice test platform, featuring all the latest PRINCE2 Certification exam questions added this week. Our preparation tool is more than just a PRINCE2 study aid; it's a strategic advantage.

Our free PRINCE2 Certification practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about Prince2-Practitioner. Use this test to pinpoint which areas you need to focus your study on.

Prince2-Practitioner PDF

Prince2-Practitioner PDF (Printable)
$43.75
$124.99

Prince2-Practitioner Testing Engine

Prince2-Practitioner PDF (Printable)
$50.75
$144.99

Prince2-Practitioner PDF + Testing Engine

Prince2-Practitioner PDF (Printable)
$63.7
$181.99
Question # 71

Project Scenario

Project Scenario

Calendar Project (Note: The companies and people within the scenario are fictional.)

There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:

    Design for each month - correctly showing at public holidays and new company logo

    Selected photographs- 12 professionally-produced photographs, showing different members of staff

    Selected paper and selected envelope - for printing and mailing the calendar

    Chosen label design - a competition to design a label will be held as part of this project

    List of customers - names and addresses of customers to whom the calendar will be sent.

The project is currently in initiation and will have two further stages:

Stage 2 will include tie activities to:

    Create the customer fast using information from the Accounts and Marketing departments

    Confirm compliance with the Data Protection Legislation

    Create a design for each month - this will be done by the internal creative team

    Select and appoint a professional photographer

    Gather photograph design ideas from previous project and agree photographic session schedule

    Prepare a production cost forecast

    Select paper and envelope.

Stage 3 will include the activities to:

    Produce and select tie professionally-taken photographs

    Hold the label design competition and choose the label design

    Assemble the prepared calendar pack.

A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.

It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.

Lines 1 to 6 in the table below consist of an assertion statement and a reason statement For each line identify the appropriate option, from options 1 to 6, that applies. Each option can be used once, more than once or not at all.

Question # 71

Options:

Discussion 0
Question # 72

There are two time driven controls in PRINCE2, which are they?

Options:

A.  

Highlight and End Stage Reports

B.  

Highlight and Checkpoint Reports

C.  

Checkpoint and End Project Reports

D.  

Highlight and Lessons Reports

Discussion 0
Question # 73

Which of the following is not a factor to consider when determining the length of a stage?

Options:

A.  

The amount of resources available h the short term

B.  

How far ahead you can sensibly plan n detail

C.  

The technical stages within the project

D.  

The amount of risk associated with the project

Discussion 0
Question # 74

Scenario:

Techniques, processes and procedures

1. Any threat that may result in a loss of MFH data must be escalated immediately.

Joint agreements

2. Work is to start at the beginning of week 2 (Stage 4).

3. The project will take two years to complete, at an estimated cost of £2.5m.

Tolerances

4. None.

Constraints

5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.

6. Installation work must take place during MFH normal working hours.

7. +£10,000 / -£25,000.

Reporting arrangements

8. Highlight Report every Monday by 10.00 am.

9. The report must contain a summary of all products worked on during the previous week.

10. Project Manager must be notified of any issues immediately by telephone.

Problem handling and escalation

11. Impact analysis of all issues must be completed within 24 hours.

Extracts or references

12. The Stage Plan for stage 4 is available from Project Support.

Approval method

13. Project Assurance will review the completed Work Package and confirm completion.

Which 2 statements apply to either the Development Interfaces or Operations and maintenance interfaces sections?

Options:

A.  

Delete entry 2 because this interface will be contained in the Communication Management Strategy.

B.  

Delete entry 3 because this interface will be contained in the project control section of the Project Initiation Documentation.

C.  

Amend entry 4 to 'The transferred products relating to the services provided by the Facilities Division'.

D.  

Add 'Project Board, with responsibility for communicating progress to corporate management' to

E.  

Operations and maintenance Interfaces.

F.  

Add 'Facilities Team Manager, with responsibility for the transfer of services provided by the Facilities Division' to Development Interfaces.

Discussion 0
Question # 75

If Project tolerances were threatened, who needs to be notified?

Options:

A.  

Project Board

B.  

Project Manager

C.  

Corporate or Programme Management

D.  

Executive

Discussion 0
Question # 76

During which process would the stage tolerances be set?

Options:

A.  

Controlling a Stage

B.  

Initiating a Project

C.  

Managing a Stage Boundary

D.  

Directing a Project

Discussion 0
Question # 77

Which statement is TRUE with regard to technical stages?

Options:

A.  

Technical stages can only occur sequential

B.  

Technical stages define where management decisions are appropriate

C.  

Technical stages often overlap

D.  

Technical stages define the commitment of resources and authority to spend

Discussion 0