Halloween Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Good News !!! PK0-005 CompTIA Project+ Certification (2024) is now Stable and With Pass Result

PK0-005 Practice Exam Questions and Answers

CompTIA Project+ Certification (2024)

Last Update 3 days ago
Total Questions : 291

CompTIA Project+ Certification (2024) is stable now with all latest exam questions are added 3 days ago. Incorporating PK0-005 practice exam questions into your study plan is more than just a preparation strategy.

PK0-005 exam questions often include scenarios and problem-solving exercises that mirror real-world challenges. Working through PK0-005 dumps allows you to practice pacing yourself, ensuring that you can complete all CompTIA Project+ Certification (2024) practice test within the allotted time frame.

PK0-005 PDF

PK0-005 PDF (Printable)
$42
$119.99

PK0-005 Testing Engine

PK0-005 PDF (Printable)
$49
$139.99

PK0-005 PDF + Testing Engine

PK0-005 PDF (Printable)
$61.95
$176.99
Question # 1

Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

Options:

A.  

Sprint retrospective

B.  

Sprint review

C.  

Sprint planning

D.  

Daily Scrum

Discussion 0
Question # 2

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

Options:

A.  

Trigger the contingency plan and communicate with the stakeholders.

B.  

Work with the functional managers to create a work-around.

C.  

Submit a change request to the change control board.

D.  

Transfer the risk by hiring a new vendor who was successful on a previous project.

E.  

Set up an escalation meeting with the sponsor.

Discussion 0
Question # 3

A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?

Options:

A.  

List both positively and negatively impacted stakeholders.

B.  

Update the communication plan with the new findings.

C.  

List the negatively impacted stakeholders only.

D.  

List the positively impacted stakeholders only.

Discussion 0
Question # 4

Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?

Options:

A.  

Smoke testing

B.  

Regression testing

C.  

Unit testing

D.  

User acceptance testing

Discussion 0
Question # 5

Which of the following provides the best justification for undertaking a project?

Options:

A.  

Scope statement

B.  

Business case

C.  

Sponsor request

D.  

Project charter

Discussion 0
Question # 6

A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?

Options:

A.  

Use an on-premises project management scheduling tool.

B.  

Limit access to members of the project team.

C.  

Mandate overtime to get the project completed sooner.

D.  

Ensure all team members have signed a non-disclosure agreement.

Discussion 0
Question # 7

A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

Options:

A.  

Ticketing system

B.  

Videoconference

C.  

Simple messaging system

D.  

Corporate social media

Discussion 0
Question # 8

A project team member wrote a user guide over the past ten days. Given the following scatter diagram.

Question # 8

Which erf the following can be formally conducted?

Options:

A.  

The team member prioritized other tasks over the completion of this task

B.  

The learn member had performance issues over time.

C.  

There is a negative correlation with 6me and output

D.  

This is a display of units of outstanding work to predict completion

Discussion 0
Question # 9

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

Options:

A.  

Ask a developer to create a change request.

B.  

Do nothing because recommendation is scope creep.

C.  

Ask a developer to implement the recommendation.

D.  

Communicate the change status.

Discussion 0
Question # 10

Which of the following activities should a project manager perform during the closing phase? (Select three).

Options:

A.  

Lessons learned

B.  

Risk analysis

C.  

Removing resources

D.  

Acquiring resources

E.  

Statement of work sign-off

F.  

Stakeholder analysis

G.  

Removing access

Discussion 0
Get PK0-005 dumps and pass your exam in 24 hours!

Free Exams Sample Questions