PSP Practice Exam Questions and Answers

Planning & Scheduling Professional (PSP) Exam

Last Update 1 day ago
Total Questions : 120

PSP is stable now with all latest exam questions are added 1 day ago. Just download our Full package and start your journey with AACE International Planning & Scheduling Professional (PSP) Exam certification. All these AACE International PSP practice exam questions are real and verified by our Experts in the related industry fields.

PSP PDF

PSP PDF (Printable)
$48
$119.99

PSP Testing Engine

PSP PDF (Printable)
$56
$139.99

PSP PDF + Testing Engine

PSP PDF (Printable)
$70.8
$176.99
Question # 1

What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

Options:

A.  

ADM is limited to finish-to-start logic relationships, while PDM is not.

B.  

PDM is a bar chart with network logic, while ADM is a pure logic network.

C.  

ADM is manual CPM calculations, while PDM is computerized.

D.  

ADM uses arrows, while PDM uses boxes.

Discussion 0
Question # 2

Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

Options:

A.  

Non-excusable delay

B.  

Compensable delay

C.  

Non-compensable delay

D.  

Excusable delay

Discussion 0
Question # 3

Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

Question # 3

Options:

A.  

06-11-02.

B.  

06-04-02.

C.  

06-18-02.

D.  

06-05-02.

Discussion 0
Question # 4

Budgeted cost of work scheduled is _______________________.

Options:

A.  

The value of the completed work expressed in terms of the budget assigned to that work

B.  

The total authorized budget for accomplishing the project scope

C.  

The expected total cost of an activity, group of activities or the project

D.  

The sum of all budgets for work scheduled to be accomplished within a given time period

Discussion 0
Question # 5

An early start constraint dictates

Options:

A.  

An activity's remaining duration.

B.  

The planned start of a successor activity

C.  

The planned start of an activity.

D.  

The actual start of an activity.

Discussion 0
Question # 6

Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

Question # 6

Options:

A.  

02-19-04

B.  

03-21-04

C.  

03-11-04

D.  

03-20-04

Discussion 0
Question # 7

In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

Options:

A.  

The delay must affect the critical path.

B.  

The delay must be concurrent with the delay attributable to both parties.

C.  

The delay must not cause monetary harm to the defendant.

D.  

The delay must affect the contractor's planned construction schedule.

Discussion 0
Question # 8

Which of the following phases does NOT describe the commonly accepted construction life cycle?

Options:

A.  

Claims and disputes phase.

B.  

Installation phase.

C.  

Planning and design phase.

D.  

Turnover and start-up phase.

Discussion 0
Question # 9

What is the remaining work duration of Active D?

Question # 9

Options:

A.  

4.

B.  

11

C.  

8.

D.  

3.

Discussion 0
Question # 10

What is the actual duration as of the status date or data date of Activity B?

Question # 10

Options:

A.  

7.

B.  

3.

C.  

0.

D.  

4.

Discussion 0
Question # 11

Which of the following are NOT considerations or constraints of the planning process for construction scheduling?

Options:

A.  

Consideration of all stakeholders.

B.  

Value engineering.

C.  

Project variables.

D.  

Interest rate of owner's construction bonds.

Discussion 0
Question # 12

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

Options:

A.  

Detailed listing of working days for each calendar used

B.  

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

C.  

Assigned party responsibility for each work task

D.  

Tabular listing of activities showing duration, calendar ID, early and late dates

Discussion 0
Question # 13

What is the result of a forward pass calculation?

Options:

A.  

Value of total float for individual activities

B.  

Early start and early finish date for individual activities

C.  

Value of free float for individual activities

D.  

Critical path

Discussion 0
Question # 14

Each of the following accurately describes total float in a schedule EXCEPT:

Options:

A.  

The amount of time an activity can be delayed without delaying the overall project completion time.

B.  

Can be positive or negative.

C.  

The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.

D.  

Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.

Discussion 0
Question # 15

An earned value-based project control system can use either of which two budgets as the basis of its calculations?

Options:

A.  

Labor hours or dollars.

B.  

Direct or indirect cost.

C.  

Earned or budgeted cost yearly.

D.  

Linear feet or dollars.

Discussion 0
Question # 16

What method offers the best chance of the schedule being used effectively to implement the project in the field?

Options:

A.  

Issue detailed schedule updates as frequently as possible.

B.  

Obtain consent and agreement to the schedule from the key project personnel.

C.  

Include detailed and stringent set of scheduling specifications in the contract.

D.  

Allow large time contingencies on milestones and completion deadlines.

Discussion 0
Question # 17

Identify the late finish to develop plans and specs.

Question # 17

Options:

A.  

9 months.

B.  

10 months.

C.  

8 months.

D.  

7 months.

Discussion 0
Question # 18

The expected remaining cost needed to complete an activity, group of activities or the project is the____________.

Options:

A.  

Budget at completion (BAC)

B.  

Budgeted cost of work performed (BCWP)

C.  

Estimate to complete (ETC)

D.  

Estimate at completion (EAC)

Discussion 0