Pre-Winter Special Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 2493360325

Good News !!! PSP Planning & Scheduling Professional (PSP) Exam is now Stable and With Pass Result

PSP Practice Exam Questions and Answers

Planning & Scheduling Professional (PSP) Exam

Last Update 13 hours ago
Total Questions : 120

Planning & Scheduling Professional (PSP) Exam is stable now with all latest exam questions are added 13 hours ago. Incorporating PSP practice exam questions into your study plan is more than just a preparation strategy.

PSP exam questions often include scenarios and problem-solving exercises that mirror real-world challenges. Working through PSP dumps allows you to practice pacing yourself, ensuring that you can complete all Planning & Scheduling Professional (PSP) Exam practice test within the allotted time frame.

PSP PDF

PSP PDF (Printable)
$48
$119.99

PSP Testing Engine

PSP PDF (Printable)
$56
$139.99

PSP PDF + Testing Engine

PSP PDF (Printable)
$70.8
$176.99
Question # 1

What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

Options:

A.  

ADM is limited to finish-to-start logic relationships, while PDM is not.

B.  

PDM is a bar chart with network logic, while ADM is a pure logic network.

C.  

ADM is manual CPM calculations, while PDM is computerized.

D.  

ADM uses arrows, while PDM uses boxes.

Discussion 0
Question # 2

Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

Options:

A.  

Non-excusable delay

B.  

Compensable delay

C.  

Non-compensable delay

D.  

Excusable delay

Discussion 0
Question # 3

Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

Question # 3

Options:

A.  

06-11-02.

B.  

06-04-02.

C.  

06-18-02.

D.  

06-05-02.

Discussion 0
Question # 4

Budgeted cost of work scheduled is _______________________.

Options:

A.  

The value of the completed work expressed in terms of the budget assigned to that work

B.  

The total authorized budget for accomplishing the project scope

C.  

The expected total cost of an activity, group of activities or the project

D.  

The sum of all budgets for work scheduled to be accomplished within a given time period

Discussion 0
Question # 5

An early start constraint dictates

Options:

A.  

An activity's remaining duration.

B.  

The planned start of a successor activity

C.  

The planned start of an activity.

D.  

The actual start of an activity.

Discussion 0
Question # 6

Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

Question # 6

Options:

A.  

02-19-04

B.  

03-21-04

C.  

03-11-04

D.  

03-20-04

Discussion 0
Question # 7

In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

Options:

A.  

The delay must affect the critical path.

B.  

The delay must be concurrent with the delay attributable to both parties.

C.  

The delay must not cause monetary harm to the defendant.

D.  

The delay must affect the contractor's planned construction schedule.

Discussion 0
Question # 8

Which of the following phases does NOT describe the commonly accepted construction life cycle?

Options:

A.  

Claims and disputes phase.

B.  

Installation phase.

C.  

Planning and design phase.

D.  

Turnover and start-up phase.

Discussion 0
Question # 9

What is the remaining work duration of Active D?

Question # 9

Options:

A.  

4.

B.  

11

C.  

8.

D.  

3.

Discussion 0
Question # 10

What is the actual duration as of the status date or data date of Activity B?

Question # 10

Options:

A.  

7.

B.  

3.

C.  

0.

D.  

4.

Discussion 0
Get PSP dumps and pass your exam in 24 hours!

Free Exams Sample Questions