In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?
The key benefit of the Monitoring and Controlling Process Group is the ability to:
A project is in the planning phase and ready for plan review and approval when a sponsor switch happens. What should the next course of action be?
A project team is working on a complex product and the work breakdown structure (WBS) is finalized. The team determines that the best approach is to use an adaptive delivery method and is now tasked with converting the WBS for adaptive delivery.
How can the team manage the conversion of the existing WBS to an adaptive approach?
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
The following is a network diagram for a project.

The critical path for the project is how many days in duration?
What can increase the complexity of the Manage Stakeholder Engagement process?
A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?
An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?
An adaptive project manager is migrating the company ' s new website. The project manager must work with the team to invest full capacity on this project because it is the company ' s top-ranked project in the portfolio. In order to increase throughput and provide consistent delivery, the project manager needs to assign members who are currently involved with other projects.
How should the project manager assign the team members to this project?
Which process in Project Time Management includes reserve analysis as a tool or technique?
It you established a contingency reserve including time, money, and resources, how are you handling risk?
Which knowledge area includes the processes to identify, define, and unify the various project management processes?
Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
A graphic display of project team members and their reporting relationships is known as a:
How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?
A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?
What type of meeting is held to discuss prioritized product backlog items?
Stakeholder identification and engagement should begin during what phase of the project?
A project team member identifies a possibility......the team member ' s idea?
A project team member identifies a possibility of increasing project performance by adopting an innovative approach to a proposed solution. This also will save resources for the company and increase stakeholder satisfaction.
How should the project manager evaluate the team member ' s idea?
At what stages of project should the identify Stakeholder process be performed?
A large portion of a projects budget is typically expended on the processes in which Process Group?
The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule performance index (5PI) for Task 4?
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?
A stakeholder asked the project manager to add an additional feature to the project scope. The project manager is unsure whether the project budget will allow this additional scope.
What component of the project management plan should the project manager reference to determine whether the budget will allow a new feature to be added?
While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?
Variance and trend analysis is a tool and technique used in which process?
The process of identifying the stakeholders ' information needs is completed during:
After recommending to Tan (client) to leave the feature out, what should the project manager do?

A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
Which tool should a project manager use to calculate cost variance for a project?
During a kickoff meeting, the project sponsor presents a very ambitious project. Unfortunately, the stakeholders are not very excited as the work associated with the new project seems inefficient.
What could be missing from the business case?
Progressively elaborating high-level information into detailed plans is performed by the:
An adaptive team ' s velocity dropped significantly in the last sprint due to the planned vacation of two team members. The project sponsor wants to know how many more sprints it would take to complete the remaining project.
How should the project manager calculate the anticipated velocity for future sprints?
What are the project management processes associated with project quantity management?
The project manager and the project team are in the process of documenting procurement decisions. Which of the following will be the procurement strategy?
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?
A project manager has reached an agreement on the requirements and now needs to define the workflow for the end user. A critical step must be completed and validated by the end user before proceeding.
Which modeling tool best describes this process?