Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

CAPM Certified Associate in Project Management (CAPM) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

CAPM Practice Questions

Certified Associate in Project Management (CAPM)

Last Update 20 hours ago
Total Questions : 1317

Dive into our fully updated and stable CAPM practice test platform, featuring all the latest CAPM exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free CAPM practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about CAPM. Use this test to pinpoint which areas you need to focus your study on.

CAPM PDF

CAPM PDF (Printable)
$43.75
$124.99

CAPM Testing Engine

CAPM PDF (Printable)
$50.75
$144.99

CAPM PDF + Testing Engine

CAPM PDF (Printable)
$63.7
$181.99
Question # 351

A project team is starting to work on a project based on a Kanban approach. In order to frame the capacity of the team's workflow at any moment, the project manager will need to restrict the maximum amount of activities to be performed.

Which element will the project manager handle?

Options:

A.  

Capacity limit

B.  

Pull system

C.  

Work in progress

D.  

Virtual board

Discussion 0
Question # 352

An organization's project management office (PMO) has issued guidelines that require a specific template to be used for onboarding resources for a project. Where can the project manager find this template?

Options:

A.  

Organizational systems access

B.  

Organizational process assets

C.  

Resources management plan

D.  

Procurement management plan

Discussion 0
Question # 353

What document gathers all of the lessons learned at the end of a phase or project

Options:

A.  

Lessons learned register

B.  

Lessons learned list

C.  

Lessons learned project asset

D.  

Lessons learned repository

Discussion 0
Question # 354

A company has implemented an adaptive project management framework for a new project. When planning for an iteration, how should risks be addressed? Choose two.

Options:

A.  

Risks should be considered when selecting the content of each iteration.

B.  

Risks should be tailored for each iteration.

C.  

Risks should be identified, analyzed, and managed during each iteration.

D.  

Risks should be documented prior to each iteration.

E.  

Risks should be reviewed only once during each iteration.

Discussion 0
Question # 355

A project manager is developing the work breakdown structure (WBS) for a project. The team is asking at what level should they decompose their assigned work.

What should the project manager answer?

Options:

A.  

Activity level

B.  

Deliverable level

C.  

Task level

D.  

Work package level

Discussion 0
Question # 356

Which of the following factors within a company cloud trigger the creation of a project?

Options:

A.  

Need to lower production costs to remain competitive

B.  

Need to submit a warranty claim for a faulty product

C.  

Need to submit the monthly production report

D.  

Need to define next month's production goals

Discussion 0
Question # 357

What estimating technique is used when there is limited information?

Options:

A.  

Analogous estimating

B.  

Parametric estimating

C.  

Bottom-up estimating

D.  

Three-point estimating

Discussion 0
Question # 358

During what project management process does the project team begin identifying risks?

Options:

A.  

Initiating

B.  

Planning

C.  

Executing

D.  

Monitoring and Controlling

Discussion 0
Question # 359

A project manager has reached an agreement on the requirements and now needs to define the workflow for the end user. A critical step must be completed and validated by the end user before proceeding.

Which modeling tool best describes this process?

Options:

A.  

Traceability

B.  

User interface design

C.  

Use case

D.  

Wireframe

Discussion 0
Question # 360

A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization. Which document should be used in this case?

Options:

A.  

Project plan

B.  

Business case

C.  

Budget requirement

D.  

Project charter

Discussion 0
Question # 361

Which project life cycle follows a plan reviewed and approved by the stakeholders?

Options:

A.  

Predictive

B.  

Adaptive

C.  

Iterative

D.  

Incremental

Discussion 0
Question # 362

Which of these statements is true of subsidiary management plans?

Options:

A.  

Subsidiary management plans are mandatory for any project

B.  

Subsidiary management plans use the project charier as input

C.  

Subsidiary management plans can be independently managed

D.  

Subsidiary management plans do not need regular updates

Discussion 0
Question # 363

An adaptive team schedules 20 story points in the upcoming sprint. Historically, the team completes 25 story points on average per sprint. Each sprint is two weeks, and there is one day of float.

What is the likelihood the team will complete all 20 story points in the upcoming sprint?

Options:

A.  

50-75%

B.  

25-50%

C.  

75-100%

D.  

0-25%

Discussion 0
Question # 364

A business analyst has encountered a conflict related to competing requirements on an existing project. What tool should the business analyst use to resolve this issue?

Options:

A.  

Peer review

B.  

Procurement management

C.  

Weighted ranking

D.  

Risk assessment

Discussion 0
Question # 365

Which of the following projects is a quality candidate for adaptive approaches?

Options:

A.  

Installing new computers across offices

B.  

Retrofitting an old building

C.  

Upgrading an information system

D.  

Designing a new suspension bridge

Discussion 0
Question # 366

Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?

Options:

A.  

Three-point

B.  

Bottom-up

C.  

Parametric

D.  

Analogous

Discussion 0
Question # 367

A Project manager received a change request from a key stakeholder, documented it reviewed it with the team, and then presented if for decision. What was project manager trying to do?

Options:

A.  

Develop consensus among stakeholders

B.  

Get the budget approved for change

C.  

Make sure management is aware of the change

D.  

Get approval from the change control board

Discussion 0
Question # 368

What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?

Options:

A.  

Project Cost Management

B.  

Project Integration Management

C.  

Project Risk Management

D.  

Project Schedule Management

Discussion 0
Question # 369

A project team of telecommuters located in three different time zones regularly misses project deadlines Daily meetings often start and end with the same person talking and the rest of the team listening The project manager determines that communication among team members must be addressed.

What communication step is missing from the daily meetings?

Options:

A.  

Interpersonal communication

B.  

Feedback response communication

C.  

Push communication

D.  

Pull communication

Discussion 0
Question # 370

During the project planning process, which three of the following stakeholders are required to take part in the risk assessment meeting? (Choose three)

Options:

A.  

End user

B.  

Product owner

C.  

Subject matter experts (SMEs)

D.  

Project sponsor

E.  

Project team

Discussion 0
Question # 371

Which additional considerations should the project manager make when managing risks in an agile/adaptive project?

Options:

A.  

Add more risk categories

B.  

Identify, analyze, and manage risk during each iteration of the project

C.  

Add new values to the probability and impact matrix

D.  

Increase the reserves because of the high variability environment

Discussion 0
Question # 372

A project manager is calculating the current budget. The earned value (EV) of the project is lower than the actual cost (AC) of the project.

How should the project manager report the status of the project?

Options:

A.  

The project is at risk as the cost variance (CV) is negative.

B.  

The project is within budget and within schedule.

C.  

The project is within budget but is delayed.

D.  

The project is tracking well as the cost variance (CV) is negative.

Discussion 0
Question # 373

When developing a schedule which tools and techniques should a project manager use?

Options:

A.  

Schedule Networfc Analysis and Critical Path Method

B.  

Activity I ist and Fxpert Judgement

C.  

Milestone Iist and Risk Register

D.  

Basis ot estimates and Rolling Wave Planning

Discussion 0
Question # 374

Which three of the following interpersonal skills does a project manager rely on when developing the project management plan? (Choose three)

Options:

A.  

Focus groups

B.  

Facilitation

C.  

Meeting management

D.  

Conflict management

E.  

Interviews

Discussion 0
Question # 375

Project governance refers to framework.......which of the following is a portfolio?

Pioject governance refers lo framework, functions, and processes that guide project management activates with a defined hierarchy between projects, programs and poctfotos. According to this hierarchy, which ot Die following is a portfolio?

Options:

A.  

A portfolio is a group of projects, programs, subsidiary portfolios and operations managed together to achieve strategic objectives.

B.  

A portfolio is the mam project of the company, supervised directly by the CEO.

C.  

A portfolio is a group of projects managed by the same project manager.

D.  

A portfolio is a group of related proiecls, programs, subsidary portfolios, and operation*, thai provides similar products or services.

Discussion 0
Question # 376

A project is in its final stages when a competitor releases a similar product. This could make the project redundant. What should the project manager do next?

Options:

A.  

Initiate change control.

B.  

Address risk mitigation.

C.  

Escalate this to the project sponsor.

D.  

Initiate project closure.

Discussion 0
Question # 377

What statement describes the function or responsibility of a project manager?

Options:

A.  

Works with the sponsor to address internal political and strategic issues that may impact the team

B.  

Seeks ways to develop relationships that assist the team in achieving organizational goals and objectives

C.  

Ensures that the project's business operations are efficient

D.  

Provides management oversight for a project’s functional or business units

Discussion 0
Question # 378

A project is at the closing stage. The project manager asks the team to perform closing functions at the next meeting. Which two procedures will the project team perform? (Choose two)

Options:

A.  

Project audit

B.  

Deliverable acceptance

C.  

Risk register tracking

D.  

Stakeholder mapping

E.  

Issue log update

Discussion 0
Question # 379

What is the most important skill that project managers should possess to lead stakeholders throughout a project?

Options:

A.  

Communication

B.  

Problem-solving

C.  

Negotiating

D.  

Trust-building

Discussion 0
Question # 380

During a project team meeting, one of the team members suggested a product functionality that would immensely benefit the customer. The project manager documents the request for later analysis.

What is this an example of?

Options:

A.  

Monitoring the traceability matrix

B.  

Managing the scope

C.  

Maintaining the product backlog

D.  

Managing the cost benefit

Discussion 0
Question # 381

What can the project manager find among the factors that could lead a project to be tailored

Options:

A.  

Company Culture

B.  

Return on investment

C.  

Earned Value

D.  

Schedule Performance Index

Discussion 0
Question # 382

A newly developed project team is working together, building trust and adjusting its work habits to support the team What stage of the Tuckman ladder does this describe?

Options:

A.  

Forming

B.  

Norming

C.  

Storming

D.  

Performing

Discussion 0
Question # 383

What tools or techniques can be used in all cost management processes'?

Options:

A.  

Decision making and expert judgment

B.  

Expert judgment and data analysis

C.  

Data analysis and meetings

D.  

Meetings and cost aggregation

Discussion 0
Question # 384

During a kickoff meeting, the project sponsor presents a very ambitious project. Unfortunately, the stakeholders are not very excited as the work associated with the new project seems inefficient.

What could be missing from the business case?

Options:

A.  

Work breakdown structure (WBS)

B.  

Approval from the stakeholders

C.  

Feasibility study of the solution

D.  

Root cause analysis of the problem

Discussion 0
Question # 385

In which project risk management process is the data analysis technique not used?

Options:

A.  

Plan Risk Management

B.  

Implement Risk Response

C.  

Monitor Risks

D.  

Perform Quantitative Risk Analysis

Discussion 0
Question # 386

A project manager is responsible for delivering new software for their company. Based on previous experiences, the project manager decides to use the dynamic systems development method (DSDM). The project manager will use this method to prioritize the scope to meet project constraints.

Which elements are included in the DSDM framework?

Options:

A.  

Time, integration, cost, and deliverables

B.  

Schedule, risk, integration, and features

C.  

Cost, time, quality, and functionality

D.  

Cost, requirements, schedule, and outputs

Discussion 0
Question # 387

What is the Project Schedule Management practice used to deliver incremental value to the customer'?

Options:

A.  

Resource optimization

B.  

Iterative scheduling with a backlog

C.  

On-demand scheduling

D.  

Critical path method

Discussion 0
Question # 388

Which is a method of prototyping that creates a functioning representation of the final finished product to the user?

Options:

A.  

Low-fidelity prototyping

B.  

High-fidelity prototyping

C.  

Data prototyping

D.  

Report prototyping

Discussion 0
Question # 389

When presenting a product roadmap to an adaptive team, which form of communication is the most appropriate?

Options:

A.  

Requirements matrix

B.  

Presentation slides

C.  

Story map

D.  

Project management plan

Discussion 0
Question # 390

A project team is brainstorming about the best methods and practices to adopt for an upcoming project. What is the project team trying to follow?

Options:

A.  

Portfolios

B.  

Standards

C.  

Concepts

D.  

Programs

Discussion 0
Question # 391

In a preliminary meeting for a project, team members decide to execute the project with methodology A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?

Options:

A.  

Use a lightweight cost estimation due to the nature of angile projects.

B.  

Use a detailed cost estimation for agile projects.

C.  

Retrieve a dudget from a previous project and create a baseline of this project based on it.

D.  

Use a detailed work breakdown structure (WBS) to get cost estimation.

Discussion 0
Question # 392

A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members knows their roles and responsibilities.

What are the four elements of a RACI chart?

Options:

A.  

Recommend, approve, coordinate, and inform

B.  

Responsible, accountable, consult, and inform

C.  

Recommend, accountable, consult, and inform

D.  

Responsible, accountable, coordinate, and inform

Discussion 0
Question # 393

Which of the following items is a technique for data gathering?

Options:

A.  

Facilitation

B.  

Meeting management

C.  

Conflict management

D.  

Interviews

Discussion 0
Question # 394

A project manager needs information to finish their work on the project charter for a clinical trial.

Which procedure is used to obtain the requirements information?

Options:

A.  

Forecasting

B.  

Simulations

C.  

Elicitation

D.  

Quantitative analysis

Discussion 0
Question # 395

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three)

Options:

A.  

High-level deliverables

B.  

Phase transitions

C.  

Project objectives

D.  

Success criteria

E.  

Cost

Discussion 0