CAPM Practice Questions
Certified Associate in Project Management (CAPM)
Last Update 4 days ago
Total Questions : 1320
Dive into our fully updated and stable CAPM practice test platform, featuring all the latest CAPM exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.
Our free CAPM practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about CAPM. Use this test to pinpoint which areas you need to focus your study on.
A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?
A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?
Which three of the following interpersonal skills does a project manager rely on when developing the project management plan? (Choose three)
A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?
What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?
The process of defining how the project scope will be validated and controlled is known as:
The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
A project manager is seeking assistance from the business analyst for an IT project. What assistance can the business analyst provide?
A tool and technique used during the Perform Qualitative Risk Analysis process is:
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
In the Define Activities process, the schedule management plan is used to:
Which of the following are components of the technical project management skill?
Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?
When establishing a contingency reserve, including time, money and resources, how is the risk being handled?
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?
Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?
A business manager wants to start a project to launch a new product. How should the manager initiate the project?
A project manager should consider the impact of project..............manager following
A project manager should consider the impact of project decisions on supporting and maintaining the product along with project results Which process is the project manager following?
A project stakeholder is requesting changes to the project plan. Which process group addresses this?
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?
Which three of the following are key traits of a project leader? (Choose three)
In an organization with a projectized organizational structure, who controls the project budget?
The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager ' s disposal?
The process improvement plan details the steps for analyzing processes to identify activities which enhance their:
The process of identifying and documenting relationships among the project activities is known as:
The project manager has following information about duration for an activity:
* Most likely [tM] - 15 days
* Pessimistic [tP] - 20 days
* Optimistic [tO] - 10 days
What is the estimated duration of this activity, according to the triangular distribution technique?
The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:
What tool or technique will establish expected behaviors for project team members?
A project is in its final stages when a competitor releases a similar product. This could make the project redundant. What should the project manager do next?
Which set of activities should a project manager use as part of the Develop Team process?
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:
During a kickoff meeting, the project sponsor presents a very ambitious project. Unfortunately, the stakeholders are not very excited as the work associated with the new project seems inefficient.
What could be missing from the business case?
The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:
A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure an effective requirements elicitation.
What should the business analyst do?
A new project was approved by the project management office (PMO), and the scope of the project is to build a new detachable classroom. What delivery method and artifacts should the project manager use to deliver this project?
Which organizational process assets update is performed during the Close Procurements process?
A project manager is searching for solutions that bring some degree of satisfaction to all parties in order to temporarily resolve a conflict. What conflict management technique is described in this situation?
