Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

LEED-AP-BD+C LEED AP Building Design + Construction (LEED AP BD+C) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

LEED-AP-BD+C Practice Questions

LEED AP Building Design + Construction (LEED AP BD+C)

Last Update 2 days ago
Total Questions : 404

Dive into our fully updated and stable LEED-AP-BD+C practice test platform, featuring all the latest Leadership in Energy and Environmental Design (LEED) exam questions added this week. Our preparation tool is more than just a USGBC study aid; it's a strategic advantage.

Our free Leadership in Energy and Environmental Design (LEED) practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about LEED-AP-BD+C. Use this test to pinpoint which areas you need to focus your study on.

LEED-AP-BD+C PDF

LEED-AP-BD+C PDF (Printable)
$54.25
$154.99

LEED-AP-BD+C Testing Engine

LEED-AP-BD+C PDF (Printable)
$59.5
$169.99

LEED-AP-BD+C PDF + Testing Engine

LEED-AP-BD+C PDF (Printable)
$74.55
$212.99
Question # 81

Which of the following strategies is allowed under Energy Atmosphere Credit, Renewable Energy Production, and will help a project achieve Energy Atmosphere Credit, Optimize Energy Performance?

Options:

A.  

Install an on-site photovoltaic array

B.  

Purchase Green-e certified carbon offsets

C.  

Purchase Green-e certified Renewable Energy Certificates (RECs)

D.  

Install a ground-source heat pump

Discussion 0
Question # 82

The Sustainable Sites Credit, Heat Island Reduction takes into account both new and three-year aged Solar Reflectance Index (SRI) values for roofing material because

Options:

A.  

SRI generally increases with age

B.  

SRI generally decreases with age

C.  

SRI generally remains the same with age

D.  

SRI generally does not impact the Heat Island Effect

Discussion 0
Question # 83

Which of the following Water Efficiency credits differ between LEED Building Design and Construction: New Construction and LEED Building Design and Construction: Healthcare?

Options:

A.  

LEED Building Design and Construction: Healthcare has no Water Efficiency Credit, Cooling Tower Water Use

B.  

LEED Building Design and Construction: New Construction has no Water Efficiency Credit, Cooling Tower Water Use

C.  

LEED Building Design and Construction: Healthcare has additional appliance and process water requirements in Water Efficiency Prerequisite, Indoor Water Use Reduction

D.  

LEED Building Design and Construction: New Construction has additional appliance and process water requirements in Water Efficiency Prerequisite, Indoor Water Use Reduction

Discussion 0
Question # 84

What is the sequence of the process for LEED certification?

Options:

A.  

Submit documentation through LEED Online, Choose Rating System, Review, Register, Certify

B.  

Submit documentation through LEED Online, Choose Rating System, Register, Review, Certify

C.  

Choose Rating System, Register, Submit documentation through LEED Online, Review, Certify

D.  

Choose Rating System, Register, Submit documentation through LEED Online, Certify, Review

Discussion 0
Question # 85

Which of the following projects are eligible for LEED certification?

Options:

A.  

Prefabricated sandwich panel house

B.  

New office building 900 ft² (83.6 m²)

C.  

Houseboat

D.  

Mobile home

Discussion 0
Question # 86

Which of the following is true regarding LEED Pilot Credits?

Options:

A.  

Pilot Credits are not specific to the rating systems

B.  

Pilot Credits can be attempted in the design review stage only

C.  

A registered Pilot Credit must be replaced on the LEED project's scorecard if that pilot credit is removed from the Pilot Credit Library

D.  

Pilot Credit feedback surveys must be completed

Discussion 0
Question # 87

Which of the following project types is required to consider the perimeter floor area instead of the regularly occupied floor area under the Indoor Environmental Quality Credit, Daylight calculations?

Options:

A.  

Retail

B.  

Schools

C.  

Healthcare

D.  

Core and Shell

Discussion 0
Question # 88

When required to measure residential and non-residential densities, Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 1. Surrounding Density requires project teams to measure the residential and non-residential densities in what way?

Options:

A.  

Measure densities within a 1/4 mi. (0.40 km) radius of the project boundary

B.  

Measure densities within a 1/2 mi. (0.80 km) radius of the project boundary

C.  

Measure densities within a 1/3 mi. (0.53 km) radius of the project boundary

D.  

Measure densities within a 3/4 mi. (1.20 km) radius of the project boundary

Discussion 0
Question # 89

The owner of a large multi-building property is seeking LEED certification. In determining the LEED project boundaries the LEED AP may include non-contiguous parcels of land if

Options:

A.  

the parcels are used for temporary uses such as parking or staging that is owned and managed by a third party

B.  

the parcels directly support or are associated with normal building operations and are accessible to the project's occupants

C.  

the parcels are part of an existing public preservation easement or resource protection area that is directly adjacent to the LEED project boundary

D.  

the parcels are part of a land trust or conservation organization for which the LEED project provides financial support for in the Sustainable Sites Credit, Site Development Credit, Protect or Restore Habitat, Option 2. Financial Support

Discussion 0
Question # 90

Which of the following acoustical units are used in Indoor Environmental Quality Credit, Acoustic Performance to measure reverberation time?

Options:

A.  

T60

B.  

STC

C.  

Hz

D.  

dBA

Discussion 0