Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-ACP Practice Questions

PMI Agile Certified Practitioner (PMI-ACP)

Last Update 4 days ago
Total Questions : 481

Dive into our fully updated and stable PMI-ACP practice test platform, featuring all the latest PMI Agile exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI Agile practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-ACP. Use this test to pinpoint which areas you need to focus your study on.

PMI-ACP PDF

PMI-ACP PDF (Printable)
$54.25
$154.99

PMI-ACP Testing Engine

PMI-ACP PDF (Printable)
$59.5
$169.99

PMI-ACP PDF + Testing Engine

PMI-ACP PDF (Printable)
$74.55
$212.99
Question # 91

What should the team do next?

Options:

A.  

Use agile estimation techniques to create a shared understanding of when the user stories will be completed.

B.  

Agree upon development and testing activities for the user stories.

C.  

Complete the user stories, and provide a demo for the product owner and customer.

D.  

Complete the user stories, and hold a retrospective to discuss them.

Discussion 0
Question # 92

A new agile project manager accepts an assignment to manage a well-established team. Many team members have worked together on this product for several years. During a meeting, the project manager notices that team members offer little vocal interaction, yet all required tasks are completed on time.

What type of behavior does this describe?

Options:

A.  

Synchronous

B.  

Collaborative

C.  

Passive-aggressive

D.  

Random

Discussion 0
Question # 93

What should the customer do?

Options:

A.  

Expand the Scrum Master ' s role to other projects, while allowing them to support the current project.

B.  

Release the Scrum Master, since the team is adequately skilled with agile practices.

C.  

Expand the product owner ' s role to serve as the Scrum Master, while providing additional product knowledge.

D.  

Increase the functional manager ' s role to act as the Scrum Master, while providing additional information about functional areas.

Discussion 0
Question # 94

A large, corporate organization is forced to hire new team members in a geographically remote location from the current team. The manager of the department is concerned about the team not being colocated.

What behavior would indicate the team is not working well together?

Options:

A.  

Team members are sending more emails to the team.

B.  

The duration of feedback cycles has increased.

C.  

The velocity has increased by having the new team work on items.

D.  

New team members requested to move meetings due to time differences.

Discussion 0
Question # 95

During an iteration, an urgent customer request for support reaches the team. If they work on it, the team ' s commitments in this iteration are at risk.

What should the team do next?

Options:

A.  

Work overtime to meet the customer request and the iteration commitments.

B.  

Ask another team that is less busy to handle the situation.

C.  

Work with the product owner to assess the impact for reprioritization.

D.  

Work on the customer request in the next iteration as a top priority.

Discussion 0
Question # 96

Question # 96

The team is considering committing to 44 story points for the upcoming sprint. Based on the

velocity chart, what advice should the scrum master offer the team?

Options:

A.  

Reduce the commitment to 40 story points to ensure a higher chance of meeting the commitment.

B.  

Maintain a commitment of 46 story points, representing the most frequently completed velocity.

C.  

Increase the commitment to 48 story points to push the team toward higher performance.

D.  

Commit to 44 story points as it aligns with the team ' s average velocity for completed story points.

Discussion 0
Question # 97

A high-profile project team is struggling to meet planned velocity. During a retrospective, the team agreed that their lack of experience in the technology resulted in an excess of rework.

What should be done to resolve this challenge?

Options:

A.  

Increase the duration of iterations to minimize the frequency of priority changes that are distracting the team.

B.  

Reduce the duration of iterations so that the product owner can reprioritize work to ensure business value alignment.

C.  

Increase the level of effort in testing to ensure that all defects are identified and properly documented so they can be resolved before the end of the iteration.

D.  

Implement a spike to enhance creativity by experimenting with new techniques and process ideas in order to discover more efficient and effective ways of working.

Discussion 0
Question # 98

What should the project leader do?

Options:

A.  

Assign the spike to another resource to continue research for the long-term solution

B.  

Re-establish the spike; encourage experimentation and collaborate with the team

C.  

Stop experimentation and negotiate the short-term solution with the customer

D.  

Schedule a root-cause analysis with the development team on the main issues with the spike

Discussion 0
Question # 99

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

Options:

A.  

End the discussion until there is consensus.

B.  

Wait for the problem to resolve itself.

C.  

Choose the option that is best for the team.

D.  

Restate the positions to find what is in common.

Discussion 0
Question # 100

What should the agile practitioner do?

Options:

A.  

Ask the opinion of key stakeholders and the client to ensure the correct approach is being used

B.  

Work with the team to use this approach and request a quality assurance iteration after every three iterations

C.  

Propose to completely eliminate test automation, since this is a quality assurance function

D.  

Suggest merging the quality assurance and delivery teams to enhance each iteration ' s test-automation levels and reduce redundancy

Discussion 0
Get PMI-ACP dumps and pass your exam in 24 hours!

Free Exams Sample Questions