Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-ACP Practice Questions

PMI Agile Certified Practitioner (PMI-ACP)

Last Update 17 hours ago
Total Questions : 476

Dive into our fully updated and stable PMI-ACP practice test platform, featuring all the latest PMI Agile exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI Agile practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-ACP. Use this test to pinpoint which areas you need to focus your study on.

PMI-ACP PDF

PMI-ACP PDF (Printable)
$43.75
$124.99

PMI-ACP Testing Engine

PMI-ACP PDF (Printable)
$50.75
$144.99

PMI-ACP PDF + Testing Engine

PMI-ACP PDF (Printable)
$63.7
$181.99
Question # 61

What can an agile practitioner conclude about team A and team B's estimates?

Options:

A.  

Team B has underestimated scope compared to team

A.  

B.  

Team A is more confident in delivering velocity than team

B.  

C.  

Both teams need to indicate their proposed technology before the estimates can be analyzed.

D.  

Both teams have estimated the project to be of same size.

Discussion 0
Question # 62

A development team is calculating the number of story points they have completed at the end of an iteration. Although quality assurance (QA) passed and successfully demonstrated one feature, it is not being included in the release package.

Should the team add the feature's story points to their burndown chart?

Options:

A.  

Yes because the story has been tested and accepted by the business as per the definition of done (Do

B.  

Yes, because the development work is complete and quality assurance (QA) and release are external dependencies.

C.  

No. any work that is not released cannot be considered complete as per the definition of done (Do

D.  

No, because the product owner has not reviewed the release implementation checklist for potential issues.

Discussion 0
Question # 63

A new team member asks what changes could accelerate a change to the project plan.

What should be the proper response?

Options:

A.  

Competitors joined forces with the team

B.  

The customer changed requirements

C.  

Project team members obtained additional certifications

D.  

Technology which did not interfere with the final product

Discussion 0
Question # 64

In several recent agile team status meetings, there have been discussions about increases in costly bugs and late product deliveries, resulting in lower quality and higher costs. Team members feel they spend too much time in planning and process meetings, then feel rushed to complete their work.

How should the agile lead implement an effective and efficient solution?

Options:

A.  

Review the quality assurance and control processes with the team to ensure that even new team members understand the service level agreement (SLA) made with the customer.

B.  

Suggest the team commit to a 2-month trial using Kanban. Focus on delivering value to the customer using pull criteria before advancing work. The team will have planning meetings as needed with no special meetings about the process.

C.  

Hire a consultant team to perform a root cause analysis, which will determine the fundamental issues from both perspectives, then meet with the team to determine the best method to get the project back on track.

D.  

Work with the team to create a spike story for the next iteration to investigate the issue. Create a plan to get the project back on track and present it at the next status meeting to gain stakeholder acceptance.

Discussion 0
Question # 65

A product owner with experience in a predictive approach wants the team to develop very detailed schedules and cost estimates for the next 10 sprints. What should the Scrum Master do?

Options:

A.  

Suggest the product owner start by focusing on the next 2 sprints instead of 10.

B.  

Spend the first few sprints to develop detailed schedules and budgets.

C.  

Invite the product owner to the retrospective to explain the team's approach to schedule and budget.

D.  

Explain that detailed project schedules and budgets are not artifacts in agile projects.

Discussion 0
Question # 66

An organization wants to increase value delivery in its agile projects.

What should the agile teams do?

Options:

A.  

Perform analysis and development work, but no testing because that should be managed by another specialized team.

B.  

Master available technology and tools to provide informative dashboards to the stakeholders.

C.  

Work with product owners and turn product backlog items into potentially shippable product increments.

D.  

Complete projects by their deadlines and share the budgets upfront with project sponsors.

Discussion 0
Question # 67

The agile coach of a development team uses a servant leadership approach. The team is starting the third iteration of an upgrade to a software product, and work is going slower than initially planned.

What should the coach do to help the team?

Options:

A.  

Help the team to remove impediments that stall project progress.

B.  

Work with the development team to adjust the work plan.

C.  

Ask the product owner to assign more resources to the project.

D.  

Command and control the team to achieve plan goals.

Discussion 0
Question # 68

An agile team lead noticed their team’s velocity was slowing down. They did not deliver a working software during the last iteration and there have been miscommunications between team members.

What should the agile team lead do at the end of this iteration?

Options:

A.  

Focus on performance in the retrospective, then present performance indices and validate with the team.

B.  

Start using feedback loops in every sprint to reevaluate project and team performance.C Emphasize business requirements and investigate the pair-programming approach

C.  

Run a spike at the end of the sprint to investigate the issue and reduce project risk.

Discussion 0
Question # 69

What should the Scrum Master mention at the next retrospective?

Options:

A.  

Solutions to project problems that were built into the last sprint

B.  

Problems that arose

C.  

Solutions that saved the organization the most time and money

D.  

Problems that were solved

Discussion 0
Question # 70

What could help eliminate misunderstandings?

Options:

A.  

Agree on requirements with all stakeholders

B.  

Begin planning every four iterations

C.  

Consider previous sprint demo feedback when planning the next sprint

D.  

Include the reasons for the project in the contract

Discussion 0