Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-ACP Practice Questions

PMI Agile Certified Practitioner (PMI-ACP)

Last Update 4 days ago
Total Questions : 481

Dive into our fully updated and stable PMI-ACP practice test platform, featuring all the latest PMI Agile exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI Agile practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-ACP. Use this test to pinpoint which areas you need to focus your study on.

PMI-ACP PDF

PMI-ACP PDF (Printable)
$54.25
$154.99

PMI-ACP Testing Engine

PMI-ACP PDF (Printable)
$59.5
$169.99

PMI-ACP PDF + Testing Engine

PMI-ACP PDF (Printable)
$74.55
$212.99
Question # 21

A project is to be started with a team of nine existing and nine new members. The Scrum Master feels that the team is too large and wants to break it into three teams. The Scrum Master sets a constraint that each team have an equal number of existing team members for knowledge sharing and experience.

What should the Scrum Master do to accomplish this?

Options:

A.  

Ask the team members ' functional managers for guidance on how to group the team members.

B.  

Observe which team members are comfortable working together, then assign accordingly.

C.  

Ensure that members begin to self-organize as small teams with efficiently distributed skills.

D.  

Assign team members to their respective teams based on the skills known to the Scrum Master.

Discussion 0
Question # 22

The project lead of a newly created Agile project delivery team realizes that there are gaps in the knowledge of some team members. The lack of specific skills will add risk to the project delivery if the project becomes too dependent on specific resources for complete delivery.

What should the project lead do to address the gaps and develop a high-performing team?

Options:

A.  

Ask each team member to document their solutions extensively in a knowledge repository for knowledge exchange between the team.

B.  

Pair team members and ensure review of technical deliverables by partners in each sprint before integration of the solution.

C.  

Create an environment of continued learning by providing opportunities for team members to develop their skills as generalized specialists.

D.  

Replace the team members with highly qualified individuals that have experience in the specific technologies required for completing delivery.

Discussion 0
Question # 23

An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.

What should the agile coach do to address this requirement?

An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.

What should the agile coach do to address this requirement?

Options:

A.  

Explain to the client that the sprint deadline is approaching and the feature can be included in the next iteration.

B.  

Remind the team and the client of the importance of assessing the risks of these features before deciding to include them

C.  

Negotiate with the team to add the additional features in this sprint because they are important requirements.

D.  

Ask the client for an extension of the deadline to enable delivery of this sprint with the additional features.

Discussion 0
Question # 24

Question # 24

A project manager is working on a database migration project to cloud services (Refer to Migration Strategy to Cloud Services table). The project team has accumulated significant technical debt over several sprints due to pressure to deliver features quickly. This debt is now impacting their ability to deliver new features, leading to a notable decline in product performance and customer satisfaction.

Identify the actions the team should take to effectively manage technical debt while consistently delivering high-value features that align with stakeholder expectations.

Options:

A.  

Form a separate learn dedicated lo handling technical debt, allowing the current team to focus on new features to maintain a competitive advantage and stakeholder satisfaction.

B.  

Include technical debt tasks in every sprint, treating them with the same level of priority as new features, and continuously review the impact on the project ' s overall goals.

C.  

Ignore the technical debt foe now and focus exclusively on delivering new features so that the project can maintain a competitive advantage and stakeholder satisfaction.

D.  

Dedicate multiple consecutive sprints solely to addressing technical debt, halting new feature development temporarily to minimize the impact on the project ' s overall goals.

Discussion 0
Question # 25

One of the overseas stakeholders on an agile project has not been actively involved in the project ' s development. What would be the first step to reengage the stakeholder?

Options:

A.  

Increase the frequency of emails and/or try to call the stakeholder.

B.  

Remind the stakeholder of their obligation to engage in the project.

C.  

Talk to the stakeholder ' s superior so they can offer coaching and guidance on project involvement.

D.  

Set up a meeting with the stakeholder to modify the working agreement and ensure future engagement.

Discussion 0
Question # 26

What should the agile team lead do?

Options:

A.  

Create a central repository for information, and provide access to Team B

B.  

Use an information board that will be visible to all passing through the workspace

C.  

Email all stakeholders with status updates

D.  

Provide Team B with the information on an " as needed " basis

Discussion 0
Question # 27

When working with Lean approaches, which process includes the sequence of steps for delivering value and those required to carry them out?

Options:

A.  

Value stream mapping

B.  

Long-term Lean planning

C.  

Business process modeling

D.  

Planning poker

Discussion 0
Question # 28

What do the principles of Extreme Programming (XP) include?

Options:

A.  

Communication, respect, and courage

B.  

Communication, process flow, and authoritarian structure

C.  

Value people over processes, communication, respect disagreement, and strive for consensus

D.  

Rapid feedback, assume simplicity, incremental change, embrace change, and quality work

Discussion 0
Question # 29

An infrastructure team had to revamp so downstream channels could consume data from the data lake, thereby improving operational efficiency for the end customers. Which primary components should the product manager consider while plotting performance and dependencies on the product roadmap?

Options:

A.  

Product vision, business objectives, themes, timeframes, and disclaimers

B.  

Product improvements, resource management, risk management, and deadlines

C.  

Product goals, strategic objectives, major features, and release plans

D.  

Features, stages of development, technology and infrastructure, dependencies, and risks

Discussion 0
Question # 30

The Agile team has failed to meet their iteration goal, and contention has developed between members. The Agile Leader would like to determine how to improve the team’s productivity and morale.

How should the Agile Leader address this?

Options:

A.  

Standup meeting

B.  

Retrospective meeting

C.  

Demo of the new features to energize the team

D.  

Offsite meeting with stakeholders

Discussion 0