Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-ACP Practice Questions

PMI Agile Certified Practitioner (PMI-ACP)

Last Update 4 days ago
Total Questions : 481

Dive into our fully updated and stable PMI-ACP practice test platform, featuring all the latest PMI Agile exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI Agile practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-ACP. Use this test to pinpoint which areas you need to focus your study on.

PMI-ACP PDF

PMI-ACP PDF (Printable)
$54.25
$154.99

PMI-ACP Testing Engine

PMI-ACP PDF (Printable)
$59.5
$169.99

PMI-ACP PDF + Testing Engine

PMI-ACP PDF (Printable)
$74.55
$212.99
Question # 41

What should the agile project manager do?

Options:

A.  

Since the team has extra time, notify the product owner and secure approval for the extra work on this feature.

B.  

Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now.

C.  

Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration.

D.  

Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog.

Discussion 0
Question # 42

An agile practitioner is in the process of refining requirements. The requirements keep changing based on with whom the agile practitioner speaks.

What should the agile practitioner do in this situation?

Options:

A.  

Ask the Scrum Master to help reduce the rate of change.

B.  

Work with the Agile Coach to document the requirements in a collaborative way.

C.  

Work with the stakeholder directly rather than go through different layers of people.

D.  

Work with the development team to confirm the requirements.

Discussion 0
Question # 43

An organization highly values security. However, a team member on a project has found a way to save time and money with less robust security features.

What should the team member do?

Options:

A.  

Influence the customer

B.  

Mention the idea at the next retrospective

C.  

Show the customer how much time and money would be saved

D.  

Present the idea at the next ceremony attended by stakeholders to obtain their input

Discussion 0
Question # 44

An agile team is preparing a release plan for a project. What information will the team need to complete this plan?

Options:

A.  

Amount of work needed to complete a single user story

B.  

Amount of work that can be accomplished by each team member

C.  

Amount of work that can be accomplished in an iteration

D.  

Amount of work that can be accomplished by the entire team

Discussion 0
Question # 45

A project manager is working on a user story about migrating to a new version of a database but is unsure of the dependencies. What can the product owner request from the team to understand the risks?

Options:

A.  

Refinement meeting

B.  

Daily standup meetings

C.  

Retrospective

D.  

Spike

Discussion 0
Question # 46

To help the team gain confidence, what should the agile practitioner suggest?

Options:

A.  

Develop a spike

B.  

Create an Ishikawa diagram

C.  

Perform a pre-mortem analysis

D.  

Complete a variance and trend analysis

Discussion 0
Question # 47

What should the agile practitioner do?

Options:

A.  

Coach the product owner to update only the acceptance criteria.

B.  

Instruct the agile team to fix the user stories during the next retrospective.

C.  

Facilitate a user story workshop with the agile team.

D.  

Inform the product owner ' s manager that the work items provide insufficient detail.

Discussion 0
Question # 48

An executive sponsor of a new Scrum team actively attends Scrum ceremonies.

How does this benefit the team?

Options:

A.  

It helps the team to focus on and meet sprint goals.

B.  

It reminds the team about who sponsors the project.

C.  

It provides high-level project updates to the sponsor.

D.  

It helps to quickly resolve issues using the sponsor ' s influence.

Discussion 0
Question # 49

Which agile practice would most significantly increase a team ' s velocity?

Options:

A.  

Daily standups

B.  

Iteration and release planning

C.  

Training in areas of weakness

D.  

Iteration

Discussion 0
Question # 50

How can the scrum master respond to a stakeholder who suggests using velocity as a metric to measure team efficiency in an agile project?

Options:

A.  

Velocity of a Scrum team will stop once it becomes stable and only then the team will become efficient with its deliverables.

B.  

Velocity can only measure if a Scrum team has a stable and predictable run rate but not whether or not they are delivering better deliverables efficiently.

C.  

Velocity will become more predictable only in stable teams and velocity should not be measured in Scrum teams until that occurs.

D.  

Velocity is a great way of measuring the Scrum team ' s efficiency, and a stable velocity means the team is predictable and efficient.

Discussion 0
Get PMI-ACP dumps and pass your exam in 24 hours!

Free Exams Sample Questions