PMI-ACP Practice Questions

PMI Agile Certified Practitioner (PMI-ACP)

Last Update 17 hours ago
Total Questions : 476

Dive into our fully updated and stable PMI-ACP practice test platform, featuring all the latest PMI Agile exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI Agile practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-ACP. Use this test to pinpoint which areas you need to focus your study on.

PMI-ACP PDF

PMI-ACP PDF (Printable)
$43.75
$124.99

PMI-ACP Testing Engine

PMI-ACP PDF (Printable)
$50.75
$144.99

PMI-ACP PDF + Testing Engine

PMI-ACP PDF (Printable)
$63.7
$181.99
Question # 41

A product owner has various items in a product backlog and does not know how to prioritize them. How should the agile practitioner coach the product owner?

Options:

A.  

Sort the stories in the backlog by descending story points and release the stories at the top of the list equal to the team's velocity.

B.  

Prioritize the most valuable product features in the backlog first.

C.  

Determine the features with the highest risk and release those first.

D.  

Determine which features comprise the smallest feature set that could be successful in the market and establish viability of the product.

Discussion 0
Question # 42

What should the agile team lead do?

Options:

A.  

Require the team to try only those ideas that will ensure success.

B.  

Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.

C.  

Associate idea successes and failures with the team's incentive plan to ensure accountability.

D.  

Encourage the team to try the ideas, even if failure may be the outcome.

Discussion 0
Question # 43

An agile team is having a meeting with a customer to formulate the product requirements for the next iteration. The outcome of the meeting is a set of clear and detailed requirements.

What should the team do next?

Options:

A.  

Run automated tests on the legacy functionality.

B.  

Ask the customer to write tests that will be used to know when a story has been correctly developed.

C.  

Start coding on the selected user stories to meet the requirements.

D.  

Write tests that will be used to know when a story has been correctly developed.

Discussion 0
Question # 44

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

Options:

A.  

Coach the team to decompose the backlog activities to granular, simple tasks that are easier to estimate and complete.

B.  

Evaluate the team's capacity and help them select user stories for the iteration based on 60% of their capacity utilization.

C.  

Discuss options to add more people to the team so they can complete the tasks on time and within budget.

D.  

Evaluate the team's capacity and help them select user stories for the iteration based on 80% of their capacity utilization.

Discussion 0
Question # 45

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration.

What must the agile practitioner do?

Options:

A.  

Add the new change request as a new user story in the product backlog for the upcoming iteration

B.  

Evaluate the impact of the change request and let the team and Product Owner decide and reprioritize based on value

C.  

Recommend canceling the current iteration and plan the change request into the next iteration

D.  

Recommend that the Product Owner add this change request as a user story to the backlog for the current iteration

Discussion 0
Question # 46

Following approval of a business case, a company will introduce a new mobile app for customers to place orders. Time to market is a key concern. The product has entered into the 3rd iteration, but the team is concerned because they feel the technical designs do not meet the agreed-on definition of done (DoD). An agile coach has been hired to help validate product delivery against business requirements.

What should the agile coach do?

Options:

A.  

Incorporate quality assurance in the planning stage of product development.

B.  

Schedule a dedicated meeting with the product owner to tackle this roadblock.

C.  

Conduct a brainstorming exercise to get to the root of the issue and devise action plans.

D.  

Conduct a retrospective meeting at the end of the current iteration to identity necessary improvements.

Discussion 0
Question # 47

Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project.

What should the product owner do next?

Options:

A.  

Obtain approval from the change control board to discontinue the component

B.  

Ask the team to continue developing the component

C.  

Ask the team to discontinue developing the component

D.  

Request the sponsor's formal approval to discontinue the component

Discussion 0
Question # 48

A team lead reviews processes and identifies bottlenecks that prevent the teams from quickly delivering minimum viable products (MVPs). Which responsibility falls within the context of servant leadership?

Options:

A.  

Facilitate the team's agile retrospective meeting

B.  

Guard the team against external distractions

C.  

Escalate points of conflict the team cannot resolve

D.  

Identify the sequence for developing stories within an iteration

Discussion 0
Question # 49

A software development team is working in an environment in which increased competition, demanding customer expectations, and new technological developments pose significant challenges.

How should the team plan improvements to their product?

Options:

A.  

Follow the project schedule created at the start of the project.

B.  

Hold regular retrospectives and have team members commit to specific actions.

C.  

Allow team members to choose improvement items and trust their judgment.

D.  

Encourage team members to write code that is tightly coupled together.

Discussion 0
Question # 50

What should the team do?

Options:

A.  

Inform the sponsor about the regional sales manager's disruptiveness and ask that all questions be diverted to the weekly meetings.

B.  

Stay focused on the current iteration and let the project manager deal with the regional sales manager's questions.

C.  

Invite the regional sales manager to the next iteration review to share the progress.

D.  

Create a risk on the risk register to account for some potentially new requirements from the regional sales manager.

Discussion 0