Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-ACP Practice Questions

PMI Agile Certified Practitioner (PMI-ACP)

Last Update 17 hours ago
Total Questions : 476

Dive into our fully updated and stable PMI-ACP practice test platform, featuring all the latest PMI Agile exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI Agile practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-ACP. Use this test to pinpoint which areas you need to focus your study on.

PMI-ACP PDF

PMI-ACP PDF (Printable)
$43.75
$124.99

PMI-ACP Testing Engine

PMI-ACP PDF (Printable)
$50.75
$144.99

PMI-ACP PDF + Testing Engine

PMI-ACP PDF (Printable)
$63.7
$181.99
Question # 81

What should the agile practitioner do?

Options:

A.  

Coach the product owner to update only the acceptance criteria.

B.  

Instruct the agile team to fix the user stories during the next retrospective.

C.  

Facilitate a user story workshop with the agile team.

D.  

Inform the product owner's manager that the work items provide insufficient detail.

Discussion 0
Question # 82

A project team's standups often run over the allotted time as members attempt to resolve issues. With a large team, this is leading to productivity impacts and bringing complaints from some members that the meetings are wasting their time when they are not directly involved in an issue’s resolution.

How can the project leader help to manage the team's time?

Options:

A.  

Set up individual status meetings and find ways to make sure issues are resolved in advance so that time is not wasted for all team members during the standups

B.  

Add time to the standups to accommodate issue-resolution discussions so that everyone is up to date on the decisions made

C.  

Change the standups to weekly status meetings with a longer duration to allow team members to resolve issues collaboratively

D.  

Ask team members to raise issues during standups and then discuss resolution options with specific members in separate conversations

Discussion 0
Question # 83

An agile team had unexpected technical problems in a project and was not able to complete the deliverables on time. During the retrospective meeting, the team openly discussed the causes for these issues and what can be done to avoid similar situations in the future.

What agile values and principles did the team demonstrate?

Options:

A.  

The team is being proactive by discussing how to better balance demands and capacity and make sure they have the right competencies.

B.  

The team shows respect for one another by listening to everyone's opinions and valuing human interaction during face-to-face meetings.

C.  

The team is providing one another with fast feedback to find those responsible for any mistakes so they can be avoided in the future.

D.  

The team eliminates potential waste by discussing who should be responsible for future risk management by actively applying the pi an-do-check-act (PDCA) method.

Discussion 0
Question # 84

An agile project leader notices that the team's velocity has decreased. In examining data provided by team members, the project leader discovers that one team member has been slow to enter story statuses.

What can happen as a result?

Options:

A.  

The team will be unable to understand the iteration's status

B.  

The team will be unable to judge the project design's validity

C.  

The team cannot give accurate updates to management

D.  

Team collaboration cannot be measured effectively

Discussion 0
Question # 85

Midway through an iteration, an agile team learns that a team member will be unavailable for the next two iterations. As a high-performance team, what should the team do?

Options:

A.  

Raise an impediment that resource tasks will be blocked and notify the Product Owner

B.  

Ask the delivery manager for a temporary resource

C.  

Ask the Scrum Master to assign that team member's tasks to the next available resource

D.  

Assume the team member's tasks to meet iteration goals and notify the Product Owner

Discussion 0
Question # 86

During agile training, an aspiring scrum master with experience in predictive projects asks about the differences between the Kanban approach and the agile approach.

How should the agile trainer respond?

Options:

A.  

The Kanban approach relies on storyboards.

B.  

The Kanban approach focuses on adaptive, simultaneous workflows.

C.  

There are no work-in-process limits in the Kanban approach.

D.  

Kanban teams employ a pull system.

Discussion 0
Question # 87

What should the agile project leader do?

Options:

A.  

Bring up the new member's impediments at the next meeting to demonstrate team support of input

B.  

Assure the new member that inputs on impediments are valued and demonstrate this at the next meeting

C.  

Have a senior lead work with the new member to avoid a negative impact on team productivity

D.  

Privately work with the new member to address any impediments

Discussion 0
Question # 88

A scrum master is observing the daily coordination meeting of an agile development team. The scrum master realizes that one of the developers is confused about a business rule for the solution they are building.

How should the scrum master address this issue?

Options:

A.  

Take a few minutes to speak with the developer after the daily coordination meeting and provide clarification.

B.  

Follow the appropriate channels by contacting the product owner and asking them to address the issue with the team.

C.  

Wait until the sprint review to explain how the product increment needs to be changed to be acceptable.

D.  

Speak up immediately during the daily coordination meeting and clarity the issue to avoid any further confusion.

Discussion 0
Question # 89

The coach on a new agile team notices that one team member is influencing most of the team's decisions. What should the coach do?

Options:

A.  

Replace the team member with a more collaborative individual.

B.  

Permit the team member to continue influencing because agile teams are self-organizing.

C.  

Ask probing questions to other team members to encourage dissenting viewpoints.

D.  

Intervene if the team's velocity drops.

Discussion 0
Question # 90

A new Scrum team is struggling with the various ceremonies of Scrum. Among other things, the product owner and stakeholders find the technical architecture and design presentations during sprint reviews less than informative.

What should the team do?

Options:

A.  

Refocus the sprint review meetings to demonstrate working software and seek feedback on the product.

B.  

Reach out to other, more experienced teams to seek input as to how to present the technical details in a more informative manner.

C.  

Explain the importance of the technical architecture and design presentations and improve the presentation format.

D.  

Invite technical managers and architects who will be a more appropriate audience to their sprint reviews.

Discussion 0
Get PMI-ACP dumps and pass your exam in 24 hours!

Free Exams Sample Questions