Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-ACP Practice Questions

PMI Agile Certified Practitioner (PMI-ACP)

Last Update 4 days ago
Total Questions : 481

Dive into our fully updated and stable PMI-ACP practice test platform, featuring all the latest PMI Agile exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI Agile practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-ACP. Use this test to pinpoint which areas you need to focus your study on.

PMI-ACP PDF

PMI-ACP PDF (Printable)
$54.25
$154.99

PMI-ACP Testing Engine

PMI-ACP PDF (Printable)
$59.5
$169.99

PMI-ACP PDF + Testing Engine

PMI-ACP PDF (Printable)
$74.55
$212.99
Question # 121

A senior manager has asked an agile team to ensure that the data for the burndown charts are updated in real-time. However, the team is not comfortable with this approach as they think this is not productive.

What should the scrum master do?

Options:

A.  

Ask the product owner to manage and share the metrics with appropriate stakeholders.

B.  

Meet with requestors to agree and align on reporting requirements.

C.  

Deny the request and explain the team ' s stance to the stakeholders.

D.  

Work with the team to create the metrics requested by the stakeholders.

Discussion 0
Question # 122

How should the agile team lead respond?

Options:

A.  

Emphasize to the stakeholder that a common, detailed vision will better ensure team understanding of the project.

B.  

Personally meet with the stakeholder to understand their requirements, and then share the vision with the team.

C.  

Work with the team to create a vision from the stakeholder ' s supplied requirements.

D.  

Explain to the team that creating a vision is not critical in agile projects, as requirements may change over time.

Discussion 0
Question # 123

A product owner is responsible for a new product. The internal customer questions using an agile approach because they need a product that works without any bugs or missing features once it is launched.

What should the product owner do?

Options:

A.  

Plan regular retrospectives with the development team to continuously improve processes to eliminate any potential issues with the product.

B.  

Apply an agile approach to write the specifications in an incremental way and develop the product once the final specifications are agreed upon.

C.  

Set up test-driven development to focus on customer requirements and eliminate issues in the software as testing progresses,

D.  

Ask the customer to provide additional representatives to help test and evaluate the product for early and frequent feedback.

Discussion 0
Question # 124

Daily coordination meeting attendance has been declining recently. Those who attend have little to contribute outside of what they are currently working on. The project manager met with the team to remind them of the importance of regular, face-to-face communication. The project team feels the daily coordination meetings are not adding value.

What should the project manager do?

Options:

A.  

Keep the meetings because some find them valuable and assume that those not attending are working steadily and have no blockers.

B.  

Change the meeting to the end of the day ensure it lasts only 15 minutes and require all team members to attend.

C.  

Work with team members to create a wiki where they can record their current accomplishments.

D.  

Reduce the occurrence of meetings because team members regularly communicate with the another and the customer

Discussion 0
Question # 125

The initial roadmap and release dates for an agile project were set based on data from similar projects and some expert opinions. Halfway through the project, however, the team’s estimates are different. Based on the team’s velocity, two more iterations were necessary to accomplish the initial scope.

How should the agile lead explain the difference to the project sponsor?

Options:

A.  

Explain how many scope changes were requested by the product owner and how many hours the team dedicated to unplanned tasks.

B.  

Explain that initial estimates help measure project feasibility but the real estimates depend on how much the team learns in each sprint.

C.  

Explain some features and requirements made aspects of the project unique and are not comparable to previous experiences.

D.  

Explain the list of materialized risks not considered at the beginning of the project ted to extra work hours and costs.

Discussion 0
Question # 126

A mobile application project is halfway through development. The team reaches a stabilized velocity after 8 iterations. The sprint duration is two weeks and requirements assigned by the product owner are not changing frequently.

What is the estimated time remaining for the project?

Options:

A.  

Eight months

B.  

Two months

C.  

Four months

D.  

Six months

Discussion 0
Question # 127

At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised.

How should this situation have been prevented?

Options:

A.  

The team should have reviewed the definition of done prior to the iteration review.

B.  

The testers should have ensured that test cases accurately reflected the product owner ' s expectations.

C.  

The team should have conducted more demonstrations with the product owner during the iteration.

D.  

The product owner should have provided clearer explanations during the planning meeting.

Discussion 0
Question # 128

Conversation transcript between the customer and the product owner (PO):

Customer: I am requesting a calendar feature for scheduling and reminding of upcoming releases that we can manage. We also need the calendar to indicate quarterly metrics deadlines, code freeze dates for financial close, and things like that.

PO: My understanding is that this is for tracking project deadlines. Would you need to see the project deadlines on your phone calendar?

Customer: Yes. I need to see a single snapshot on my phone. So, is it possible for me to connect my phone to this calendar app?

PO: Let me write up the requirements and get the development team on board with the deadlines. What phone do you own?

Customer: I own an Android phone, but I also need integration with the Apple phones.

Identify three minimum viable product (MVP) items. (Refer to Conversation transcript between the customer and the product owner (PO). Choose three.)

Options:

A.  

Monthly calendar view

B.  

Android phone integration

C.  

Windows end of support deadlines

D.  

Vacation calendar for team members

E.  

Scheduler to add events

F.  

Product increment release dates

Discussion 0
Question # 129

A Product Owner new to the role is very enthusiastic about an agile project with an energetic team.

What should be done first to ensure successful delivery of the product?

Options:

A.  

Hold a meeting with the team and the Product Owner to develop the team charter, working agreement, guiding principles, and product vision

B.  

Ask the Product Owner to create the project vision and charter, and then discuss the guiding principles with the team

C.  

Hold a meeting during which the team can present the project charter, high-level project plan, and team values to the Product Owner

D.  

Send the Product Owner to formal Product Owner training where the Product Owner can learn how to create a product vision

Discussion 0
Question # 130

Several potential risks have been identified for a new project that started last month. The project manager is worried that the team is not fully aware of these potential threats.

What should the project manager do?

Options:

A.  

Mention the risks during the daily standups and ensure all agreed-upon response actions are discussed by the team.

B.  

Remind the team daily about the threats and request a response regarding which risks have been identified and resolved

C.  

Arrange weekly meetings and invite the project sponsor to discuss the importance of the project with the team.

D.  

Create a space on the board to prioritize the threats, along with an update on the actions that are in progress and what still needs to be done.

Discussion 0
Get PMI-ACP dumps and pass your exam in 24 hours!

Free Exams Sample Questions