Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) is now Stable and With Pass Result | Test Your Knowledge for Free

Exams4sure Dumps

PMI-ACP Practice Questions

PMI Agile Certified Practitioner (PMI-ACP)

Last Update 20 hours ago
Total Questions : 476

Dive into our fully updated and stable PMI-ACP practice test platform, featuring all the latest PMI Agile exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI Agile practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-ACP. Use this test to pinpoint which areas you need to focus your study on.

PMI-ACP PDF

PMI-ACP PDF (Printable)
$43.75
$124.99

PMI-ACP Testing Engine

PMI-ACP PDF (Printable)
$50.75
$144.99

PMI-ACP PDF + Testing Engine

PMI-ACP PDF (Printable)
$63.7
$181.99
Question # 131

During a sprint demo, a business representative identifies missing requirements. The agile practitioner realizes that all key stakeholders were not included during requirements detailing.

What should the agile practitioner have done to avoid the situation?

Options:

A.  

Included the stakeholders in the project planning meeting

B.  

Organized an earlier demo to solicit business feedback

C.  

Ensured all business leaders signed off on requirements

D.  

Engaged key stakeholders periodically to collect requirements

Discussion 0
Question # 132

An agile practitioner is in the process of refining requirements. The requirements keep changing based on with whom the agile practitioner speaks.

What should the agile practitioner do in this situation?

Options:

A.  

Ask the Scrum Master to help reduce the rate of change.

B.  

Work with the Agile Coach to document the requirements in a collaborative way.

C.  

Work with the stakeholder directly rather than go through different layers of people.

D.  

Work with the development team to confirm the requirements.

Discussion 0
Question # 133

Following a successful product release, senior management asks an agile team how to improve the value of the product for the next release.

What should the team do?

Options:

A.  

Conduct frequent demos and obtain feedback from users throughout the development of the next release

B.  

Inform senior management that since the product was successfully released, the project is considered delivered and should be closed

C.  

Request additional budget to implement a Scrum of Scrums approach to scale the teams and add capacity

D.  

Implement a better definition of done to ensure that continuous integration processes are managed effectively

Discussion 0
Question # 134

A mobile application project is halfway through development. The team reaches a stabilized velocity after 8 iterations. The sprint duration is two weeks and requirements assigned by the product owner are not changing frequently.

What is the estimated time remaining for the project?

Options:

A.  

Eight months

B.  

Two months

C.  

Four months

D.  

Six months

Discussion 0
Question # 135

An experienced product owner presents the epics and corresponding stories during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.

What should the agile team do?

Options:

A.  

Evaluate how much can be delivered based on the Scrum Master's estimation

B.  

Identify a set of user stories based on the team's velocity

C.  

Initiate an estimation session

D.  

Consult historical data for project completion

Discussion 0
Question # 136

To help the team gain confidence, what should the agile practitioner suggest?

Options:

A.  

Develop a spike

B.  

Create an Ishikawa diagram

C.  

Perform a pre-mortem analysis

D.  

Complete a variance and trend analysis

Discussion 0
Question # 137

A large project team is assigned to a complex technical project with many interdependent epics. The team starts to experience problems in the second sprint as the technical leads are independently unable to determine the needed solutions.

What should the project lead do to help the team?

Options:

A.  

Coordinate a collaboration session so all the team members are involved in the solution process.

B.  

Plan a minimum viable product (MVP) in collaboration with the product owner to reduce technical complexity and move issues to the next release.

C.  

Provide training for all team members to enable higher technical skills and the ability to resolve complex issues.

D.  

Hire external consultants to advise on solution options and train team members in any technical gaps.

Discussion 0
Question # 138

What should the agile practitioner do?

Options:

A.  

Transfer the senior member to another team that will more fully utilize their skill set.

B.  

Conduct a performance evaluation to determine whether or not this member is a team player.

C.  

Encourage the project team to involve the senior member in more project activities.

D.  

Ask the functional manager to determine the best course of action.

Discussion 0
Question # 139

After completing the release plan, the team realizes that the project is very likely to have a negative ROI.

What should the team do?

Options:

A.  

Prioritize the backlog, and remove low-priority stories from the release plan to ensure a positive ROI

B.  

Replace some team members to reduce the release costs and minimize a negative ROI

C.  

Perform a root-cause analysis to remove waste from the delivery process and increase the ROI

D.  

Communicate the risk of a negative ROI to the stakeholders, and update the release plan

Discussion 0
Question # 140

A project team tasked with delivering a solution with extremely aggressive timelines is facing an issue with meeting their sprint velocity targets.

To address this issue and bring the project back on track, what action should the team take?

Options:

A.  

Perform value stream analysis to eliminate the processes with wastage.

B.  

Reevaluate the minimum viable product (MVP) deliverables to remove high-risk stories and meet timelines.

C.  

Adjust the story points included in each sprint to represent the actual velocity.

D.  

Include high-risk stories in earlier sprints to deliver incremental velocity.

Discussion 0
Get PMI-ACP dumps and pass your exam in 24 hours!

Free Exams Sample Questions