PMI-ACP Practice Questions

PMI Agile Certified Practitioner (PMI-ACP)

Last Update 17 hours ago
Total Questions : 476

Dive into our fully updated and stable PMI-ACP practice test platform, featuring all the latest PMI Agile exam questions added this week. Our preparation tool is more than just a PMI study aid; it's a strategic advantage.

Our free PMI Agile practice questions crafted to reflect the domains and difficulty of the actual exam. The detailed rationales explain the 'why' behind each answer, reinforcing key concepts about PMI-ACP. Use this test to pinpoint which areas you need to focus your study on.

PMI-ACP PDF

PMI-ACP PDF (Printable)
$43.75
$124.99

PMI-ACP Testing Engine

PMI-ACP PDF (Printable)
$50.75
$144.99

PMI-ACP PDF + Testing Engine

PMI-ACP PDF (Printable)
$63.7
$181.99
Question # 31

A product owner wants to create a release plan given the team is working in a chaotic environment. They want to set expectations about what is likely to be developed and in what timeframe for some of the stakeholders.

What should the product owner include in the release plan to achieve this?

Options:

A.  

The objective, iterations and underlying features, iteration timelines, other pre-release activities, dependencies, and responsible team.

B.  

The key objectives and a brief description of each user story to be delivered in each iteration release timelines and release dependencies

C.  

The developer who will work on a specific feature and key DevOgs engineering activities to be performed during each iteration for the code integration.

D.  

The sequence of user stories to be developed in each iteration, along with their start and end timelines, dependencies, and responsible team.

Discussion 0
Question # 32

An agile team is working on the first sprint, and has already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?

Options:

A.  

Communicate the importance of the business need to the team and refine the product backlog.

B.  

Ask the team to discuss the changes to the features with the customer.

C.  

Meet with the agile team lead to prioritize the requirements.

D.  

Discuss and prioritize the requirements with the team.

Discussion 0
Question # 33

An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.

What should the agile coach do to address this requirement?

An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.

What should the agile coach do to address this requirement?

Options:

A.  

Explain to the client that the sprint deadline is approaching and the feature can be included in the next iteration.

B.  

Remind the team and the client of the importance of assessing the risks of these features before deciding to include them

C.  

Negotiate with the team to add the additional features in this sprint because they are important requirements.

D.  

Ask the client for an extension of the deadline to enable delivery of this sprint with the additional features.

Discussion 0
Question # 34

A scrum team is working together virtually. One of the team members sends a daily email to the other team members listing impediments that they find. During retrospective meetings, the team member complains that their colleagues fail to take actions on the impediments.

How should the team address this issue?

Options:

A.  

The team member that is complaining should talk individually with the scrum master to remove impediments.

B.  

They should ask for more details about the impediments and then resolve them when the team has more time to investigate.

C.  

The team member that is complaining should address the impediments in daily scrum, communicating them directly.

D.  

Team members should state that they need to prioritize their work instead of responding to daily emails about impediments.

Discussion 0
Question # 35

One of the senior stakeholders on a project did not want to be engaged on a daily basis. During the iteration, the team encounters complexities but are convinced these issues can be resolved in time for the demo.

What should the agile practitioner do?

Options:

A.  

Be transparent with all the stakeholders and make them aware of the issues encountered and the current project's status.

B.  

Ensure the agile leader documents a risk in the risk register and communicates the risk to the project sponsor.

C.  

Support the team's decision, and since the team is confident about being able to resolve the issues in time, do not raise the issues as risks with the stakeholders.

D.  

Ask the product owner to make a decision as to whether or not all the stakeholders should be kept informed about the current project's status.

Discussion 0
Question # 36

A large, corporate organization is forced to hire new team members in a geographically remote location from the current team. The manager of the department is concerned about the team not being colocated.

What behavior would indicate the team is not working well together?

Options:

A.  

Team members are sending more emails to the team.

B.  

The duration of feedback cycles has increased.

C.  

The velocity has increased by having the new team work on items.

D.  

New team members requested to move meetings due to time differences.

Discussion 0
Question # 37

During product development, changes in technology and regulations require the team to reassess product architecture.

How should this technical debt be captured?

Options:

A.  

Include it in the product backlog and use a new indicator to annotate that it is technical debt

B.  

Include it in the product backlog as a low-priority issue

C.  

Since it is not a part of Agile methodologies, it should not be tracked

D.  

Have team members maintain personal lists of issues and consolidate the lists during review

Discussion 0
Question # 38

A software company is developing an accounting software system to market to customers. The team has been working on the project for six weeks and has great velocity. One of the major stakeholders approached the Scrum Master and asked for a bi-weekly status report because they feel they are not being properly updated.

How should the Scrum Master respond to this request?

Options:

A.  

Inform the stakeholder that all updates are provided in the sprint review sessions and encourage them to attend.

B.  

Create and update bi-weekly project status reports for the stakeholder who requested the report.

C.  

Escalate this to the stakeholder's supervisor because this is an unreasonable request.

D.  

Ignore the stakeholder's request and continue working on the project as they have been for the past six weeks.

Discussion 0
Question # 39

A new project is scheduled to begin next month. The project manager has had plenty of time to review and plan all the activities and has adopted the best approach for the project and the organization.

Which action did the project manager most likely take when choosing the approach?

Options:

A.  

They most likely used a process that was successfully used for other projects; what has worked before is less likely to fail.

B.  

They most likely discussed the best approach for this project with the team and will adapt and tailor the approach periodically by reviewing and verifying the scope with the customer.

C.  

They most likely requested an increase in the management reserve; this will help the project manager to be more flexible during change requests and risk response activities.

D.  

They most likely implemented a predictive approach; this approach might limit the freedom of making changes but secures the project from unknown risks.

Discussion 0
Question # 40

A new project has been approved and is critical for an organization. The project sponsor has a limited budget, and the deadline to have all requirements meet the definition of done (DoD) is short.

Which approach should the agile practitioner take to facilitate the project's success?

Options:

A.  

Set up weekly calls with the key stakeholders to participate in iteration reviews and release decisions.

B.  

Analyze the impacts of these constraints on the project followed by a report sent to the sponsor to anticipate any risk of delays.

C.  

Set up a meeting with the client to review the scope and timelines to manage expectations.

D.  

Encourage the team to build increments and ensure the customer provides early feedback for a minimum viable product.

Discussion 0